Commit Graph
21 Commits
Author SHA1 Message Date
grabowski bd357ab03f Business plan draft 0.3 in two versions: Plan A ~180M and Plan B ~225M THB
Deploy test site / deploy (push) Successful in 52s
- One build makes both documents: plan_variant.py switches the
  plan-specific text (pick / is_a / label); build_plan.py writes
  CNX-Vinyl-Business-Plan-A and -B (docx), export_pdf.py exports both PDFs
  with the table of contents filled in. Draft 0.2 (single launch-plant
  plan with contingency) is removed; it stays in the history.
- Plan A: the launch plant with every machine and six cost levers, ~177M
  THB with the ramp-up reserve, no contingency. Plan B: the second Duplex
  at launch, five presses, ~224M THB on the same basis. Each version reads
  as a complete plan with one table comparing it with the other; the
  216M investor-question text is gone, Pheenix is priced at OMS's
  reference plus 20 %.
- Calculator renders in both documents, each from its own preset: the
  plant at a glance (Figure 4), the budget check (Figure 5) and ten years
  of cash (Figure 6), in docs/renders/calculator/.
- Calculator budget card: the verdict and third KPI now name the tightest
  budget the midpoint fits (Plan A: 3.3M to spare under 180M; Plan B:
  0.8M under 225M) instead of always 225M.
- Fixes: CD replication cross-references point to section 4.10; the
  blended price in section 3.3 and roadmap item 1 is 3.76 to 5.27 USD at
  60 % specials (3.50 to 4.60 at a standard-heavy mix).
2026-10-17 15:42:35 +07:00
grabowski f2ff1eac1f Two plans for the investor: Plan A ~180M, Plan B ~225M THB; Pheenix at OMS +20 %
Deploy test site / deploy (push) Successful in 53s
User (October 2026): price the Pheenix galvanics line at OMS's reference
plus 20 %, and work on a new business plan in two versions, one at
roughly 180M THB and one at +25 %; the plans do not include contingency;
Plan A keeps every machine and uses cost levers only.

- total-investment.md: Pheenix block 324k to 445k USD (OMS 4-cell wet
  room with know-how transfer, EUR 234k to 321k, plus 20 %; was 320k to
  650k estimate); launch plant now ~161M to 285M THB with contingency,
  midpoint ~223M. New section "Two plans": Plan A = launch plant with
  solar PPA, metrology launch tier, corridor later, cassette and CD-R
  later, rented crane, Chinese boilers and compressor: subtotal ~161.7M
  + ramp-up reserve 10 to 20M = ~177M THB (127M to 226M). Plan B = second
  Duplex at launch (five presses), everything in: subtotal ~209.2M +
  reserve = ~224M THB (162M to 286M). Contingency listed as not in
  either price (~24M / ~31M at 15 %). The 180M / 216M answer marked
  superseded.
- revenue-model.md: operating pictures of both plans at 60 % specials.
  Plan A central EBITDA 1.73M USD, operating profit 1.34M, payback ~3.1
  yr on the plan price; adverse loses money. Plan B (1.0 / 1.25 / 1.5M
  records) central EBITDA 3.14M, operating profit 2.63M, payback ~2.2 yr;
  adverse just covers depreciation; needs ~1.25M records sold.
- Calculator: Pheenix price basis "OMS +20 %" and "OMS directly"; new
  contingency switch (in the total / shown separately); presets Plan A
  and Plan B (replace "investor levers" and "five-press"); budget card
  against 180M and 225M.
- galvanics.md price note, README, roadmap.

Checks: calculator regression updated and passing (0 fails, no page
errors), node --check on all scripts, site build (no dead links), no em
dashes added.
2026-10-17 14:47:43 +07:00
grabowski 3f1e4452b8 Press hall: five Duplex bays and four Classic positions (balanced at 60 % specials)
Deploy test site / deploy (push) Successful in 44s
User (October 2026): "change the hall layout" after the finding that the
60/40 floor split leaves the Classics about half loaded at 60 %+
specials (specials run only on the Duplex systems).

- Press hall now keeps five Duplex bays (four along the visitor
  corridor, the fifth at the head of the second row) and four Classic
  positions: 550 + 200 = ~750 m2 of ~870 m2, ~73/27 by floor, 10 to 4 by
  presses; launch plant fills one of each, growth adds Duplex first.
- Full hall: ~2.9 to 4.4M records a year at 60 % specials, Classics ~80
  to 100 % loaded (60/40 gave ~2.3 to 3.6M); ~3.2 to 4.4M at ~20 %;
  fourteen presses as before: ~2.1 to 2.5 t/h steam, up to ~1.8 MW
  cooling, a utility phase of its own.
- pressing-line.md, scale.md, site-candidates.md, crane-workshop-tours.md,
  roadmap.md, README (FreeCAD model still the earlier layout, not
  redrawn); calculator preset "Full hall (5 D + 4 C)" and ladder; plant
  view reserves 5 Duplex bays and 4 Classic positions; business plan
  draft 0.2 rebuilt.

Checks: renderer 720 checks and functional checks pass, calculator
regression 0 fails, level checks clean; PDF 47 pages, TOC filled.
2026-10-16 20:57:51 +07:00
grabowski d8b2c1e2db Press hall laid out 60/40 for Duplex systems (special pressings first)
Deploy test site / deploy (push) Successful in 46s
User (October 2026): "the factory should have more space for duplex
setups than classic, we will mainly focus on special prints and not mono
colours plan it to be 60/40 duplex classic".

- Press hall (~870 m2) planned 60/40 by floor: four Duplex bays along the
  visitor corridor and six Classic positions in the second row (440 + 300
  = ~740 m2 at 110 / 50 m2), the rest open for mould carts and staging;
  the launch plant fills one of each, growth adds Duplex systems first.
  Replaces "room for ten more Classics".
- Full hall: 8 semi-automatic presses + 6 Classics, 57/43 by press count,
  ~1,250 to 1,410 records/h gross, ~3.6 to 4.7M a year on the scale.md
  basis (was 4.7 to 5.8M for 2 Duplex + 11 Classics); ~2.1 to 2.5 t/h
  steam and up to ~1.8 MW cooling, still a utility phase of its own.
  By hourly output the six automatic Classics still press more than the
  eight semi-automatic presses (estimate).
- pressing-line.md, scale.md (capacity table, utilities), site-candidates
  .md, crane-workshop-tours.md, roadmap.md, README (the FreeCAD Payap
  model still draws the earlier layout; noted, not redrawn).
- Calculator: preset "Full hall 60/40 (4 D + 6 C)", fleet ladder Duplex
  first (1+1, 2+1, 3+2, 4+3, 4+6) plus the same floor Classic-led (2+11)
  and Duplex-only (7+0) for comparison; plant view reserves 4 Duplex
  bays and 6 Classic positions.
- Business plan draft 0.2 rebuilt (capacity table row, plot fit, layout).

Checks: renderer 720 checks pass (node budget 2,700 for the Duplex-heavy
stress preset, 60 fps), calculator regression 0 fails, level selector and
page checks clean at 390 / 1024 / 1440 px dark and light; PDF 47 pages
with a filled table of contents.
2026-10-16 20:09:56 +07:00
grabowski 794cde228c Re-base scale, pressing line, roadmap, revenue model and calculator on the launch plant
Deploy test site / deploy (push) Successful in 48s
Launch plant (user, October 2026): one Duplex system and one Classic,
with cutting and galvanics in-house, everything in one capital round.

- scale.md: capacity table now launch plant 0.71-0.97M records/yr, the
  second Duplex as a growth option; launch utilities (450-540 kg/h on
  B-1/B-2, ~390 kW on 2 x 250 kW); calculator figure ~0.94M.
- pressing-line.md: launch plant section on top; five-press fleet kept as
  the layout fleet the hall and backbone are built for.
- roadmap.md: long-lead orders for the launch plant, no bridge stampers
  or outsourced cutting, commissioning order, what stays revenue-gated.
- revenue-model.md: operating picture of the launch plant: central
  revenue ~3.75M USD, EBITDA ~1.6M, operating profit ~1.1M, payback ~4
  yr on 216M THB, break-even ~0.3M records; adverse corner cannot cover
  depreciation. Five-press table kept and labelled.
- fleet-calculator.html: start fleet 1 Duplex + 1 Classic, target 850k,
  capex base 6.55M (cases 8.9 / 6.55 / 4.9M), Duplex beyond one, chiller
  500 kW, imported machinery 2.3M, ladder from the launch plant.
- total-investment.md: superseded note updated.
2026-10-16 15:34:19 +07:00
grabowski 3a758fcffb Fleet: each Duplex has an EX 50 main and an EX 35 colour extruder
Correction from the user: the two Duplex systems are not in the
two-extruder configuration. Each runs two HRP 12 presses from an EX 50
main extruder with an EX 35 auxiliary extruder beside it for a second
colour; the Classic stays. Fleet still five presses. Updated in
pressing-line (table, phasing, re-quote: EX 50 vs the VEX 50 of the 2024
quote, and whether one EX 50 keeps both presses at full rate), scale,
total investment (wording; estimates unchanged), roadmap item 4, README.
2026-10-10 16:11:46 +07:00
grabowski c50417668b Press fleet: two Newbilt Duplex systems with an extruder per press, plus a Classic
The current plan (user decision, October 2026) replaces the 50/50 target
(two semi-automatic presses and two Pheenix AD12s) with an all-Newbilt
fleet of five presses: two Duplex systems in Newbilt's two-extruder
configuration (two HRP 12 presses, an extruder each, one hydraulic unit)
and one Classic fully automatic press.

- pressing-line.md: new "Current plan" section (fleet table, what it
  means, phasing from the Single 2.1 as the first half of system 1,
  re-quote questions); site requirements per Duplex system.
- scale.md: capacity table and basis (368 to 448 records/h, ~1.06 to 1.5M
  a year on two shifts, same range as before); pressing electrical row;
  steam and cooling flagged, not re-based: five presses draw ~750 to 900
  kg/h of steam and up to ~625 kW of cooling at Newbilt's per-press
  figures, against the 400 kg/h / 250 kW sized for one Duplex.
- total-investment.md: fleet change as an added-scope row (system 2
  ~230k-300k and the Classic ~290k-460k, estimates; -60k / -160k against
  the two blocks it replaces); headline unchanged until the re-base.
- roadmap items 4, 5 and 24, revenue model mature row, crane doc (the
  Classic's weight now decides 5 t or 3.2 t), vendor landscape (AD12 is
  the comparison for the Classic), README.

The business plan docx is not regenerated.
2026-10-10 16:05:27 +07:00
grabowski f1334f4756 OMS introduction letter and links, Sibert's answer (9 October 2026)
OMS (Lou Wullms) sent its introduction letter, filed in
docs/equipment/oms/: wet-room units with reference prices, two 4-cell
configurations (EUR 224,000 basic with two EFS2-200, EUR 311,000 advanced
with one AEFS4-250 and PLC; installation days extra), capacities of 24
and 32 shells in an 8-hour day, utilities, rooms, staffing, used
equipment, and five contacts for buying a cutting lathe. Recorded in
galvanics.md (tables, our reading: the advanced units add up to EUR
314,000, know-how transfer is left out of both totals although CNX has no
plating know-how, the basic set has no passivation unit), the exhibitor
follow-ups, vendor landscape (new section on used lathes and cutting-room
contacts, plus Lou's three websites), supplier map, roadmap items 6 and
13, total investment (basis note only, block unchanged) and the scale
people estimate. Open: forward the letter to Simona, as Lou asked.

Sibert (Ian Locke, 9 October): footprints and formal quotations when we
are ready; settle the pressing side first, hopefully with Pheenix, and
mention his recommendation if we do; impressed by the green-factory
plans (supplier feedback). Open: pass on the recommendation if Pheenix is
chosen.

CNX-01 in proplan: OMS basic and advanced added as options to D-002 with
their reference prices in THB; budget line 3 notes the OMS range.
2026-10-10 15:52:23 +07:00
grabowski 21419145f8 Replies sent to Sibert (Ian Locke) and OMS (Lou Wullms)
OMS confirmation is done; next is the calculation material from Lou
Wullms. Sibert itemised quotation still open.
2026-10-09 12:08:07 +07:00
grabowski 4fec258f15 After Haarlem: Pheenix CEO follow-up, OMS first contact, SST
- Pheenix Alpha (Robert Gunnarsson, 5 Oct; Simona's reply 9 Oct): offers
  a Teams call, reference clients and a factory visit near Stockholm;
  300+ presses (vendor figure); we call once questions are concrete,
  next Europe trip planned for February 2027. CEO contact and Marsta
  address added.
- OMS (Lou Wullms, 7 Oct): first email contact, company data, contacts
  (Lou Wullms technical, Wilma Peeters accounting/logistics); open: reply
  to confirm, then OMS sends material to calculate from.
- SST Frankfurt (Daniel Krieger, 7 Oct): cut the lacquers for POY003,
  005, 006 and 013; on good terms with ResurRec; offered help. New cutting
  service entry in the supplier map and vendor landscape; corrected the
  briefing, which had SST as DMM (its site lists lacquer and dubplates).
- Roadmap items 5, 6 and 14 and the production timeline launch basis
  updated accordingly.
2026-10-09 06:38:52 +02:00
grabowski 6888abe602 Sibert follow-up: USD 250k budget, current VS specs, OMS as galvanics option
Deploy test site / deploy (push) Successful in 41s
Ian Locke's email of 5 October 2026 after Making Vinyl Europe:

- Budget of USD 250k for VSP, VSF and VSC confirmed; his time, spares,
  shipping and travel extra; itemised quotation on request. The
  total-investment block keeps its estimate until the re-base, the
  difference (+190k low case / +80k high case) goes into the
  not-yet-rolled-up table.
- Current specifications filed (VSF and VSC 2022, VSP 2023) plus the
  VSF/VSP/VSC line-up drawing (4958 x 833 mm); the 2021 issues move to
  sibert/specs-2021/. VSC is now 1000 kg with split OD hydraulic / ID
  pneumatic forming; VSF 0-30 psi, 4-station head. Crane table, supplier
  map, vendor landscape and the plant page details updated.
- Fully automatic VSPa exists; Sibert offers to move features to the VSP.
- Electroforming: OMS (Optical Media Services, Lou Wullms) named next to
  Pheenix; added as a third galvanics candidate with open questions.
- Sequencing advice (presses, boilers, operators and live feedback loops
  first) recorded in the exhibitor briefing, roadmap item 23, and as
  digital-factory design decision 9 (operators see the data first).
2026-10-07 09:24:11 +02:00
grabowski c56d403da0 Record the Making Vinyl feedback on traceability
Most people the team talked to in Haarlem were strongly interested in the
full-traceability approach. For Sibert it was one of the reasons to talk to
us at all; without it their representative would strongly advise against
the plan, and seeing buildfor.life's development and data work convinced
him the project comes from the right direction.

Exhibitor briefing gets an "After the show" section (feedback, what has
been filed since); traceability.md opens with the market signal; roadmap
item 1 notes it as supply-side evidence, with buyer prices still missing;
README project status updated (show attended, Payap lead).
2026-10-03 21:39:45 +02:00
grabowski ffbc46782a Add the Payap University partnership: joint student programmes
Payap also wants to work closely with the project on new student
programmes: audio engineering (mastering, lathe cutting), IT, business
administration and more.

New docs/payap-partnership.md: why it fits (mastering/cutting engineers
are the hardest hires; Payap has music, IT, business, communication arts,
an English-language International College and pharmacy labs; the plant has
a lathe, production data and a real factory application), programme areas
mapped to the docs they draw on, and what it changes: a reason to bring
the cutting room (roadmap item 27) forward, a cutting engineer before the
students, lacquer and stylus cost of teaching, pre-release security for
customer audio, student access and safety, IT work on staging only, the
link to the Payap land, BOI R&D merit. Suggested form: MOU, internships,
short certificate courses first, degree tracks later; what to settle in
writing and questions for the next meeting.

Links from README (bullet, layout), site-candidates, roadmap item 27, the
supplier map's open training item and the BOI open items.
2026-10-03 21:36:17 +02:00
grabowski 31d89faf03 Add Payap University land as a site candidate
Payap University (Chiang Mai) is interested in leasing land to the
project; a pharmaceutical facility is under construction on the same land.

New docs/site-candidates.md puts the three options side by side (Mueang
Chi lease, Northern Region Industrial Estate, Payap) with the public facts
on Payap (Mae Khao campus on the Chiang Mai-Lampang superhighway, bought
as low-lying land, ~275 acres; Faculty of Pharmacy cosmetics production
facility tendered July 2024; RPAH cannabis/herbal bioreactor centre), why
it is attractive (5 km from the old city, a university partner with music,
pharmacy and labs, production already being built there) and the checks
that could rule it out, in order: zoning for pressing, boiler and later
electroplating; whether the university can lease to a company; the GMP
neighbour's sensitivity to our emissions (argues against biomass steam
there); flooding; plot fit; galvanics consent. Questions for the next
meeting listed. Nothing re-sited: model, RFQ and site code stay on
Mueang Chi until a plot is known.

README (intro, bullet, layout), roadmap item 9 and the lease fork in
project-timeline link to it.
2026-10-03 21:31:25 +02:00
grabowski 81f3279efd Add Pheenix galvanics flyers and Sibert stamper prep specs
Deploy test site / deploy (push) Successful in 45s
docs/equipment/pheenix-alpha/: the four Pheenix Alpha electroforming flyers
(2024: PASU silvering, PPPU pre-plating, PDPU dual-cell plating, PMPB
passivation bench), renamed from their download hashes.
docs/equipment/sibert/: the VSP, VSF and VSC technical specifications
(2021), plus Sibert's 2008-09 optical-disc SPS literature and the 2008
Blu-ray stamper characteristics paper in sps-optical-disc-2009/. Two
byte-identical duplicates in the download were dropped.

New docs/equipment/galvanics.md, the metal-path counterpart to
pressing-line.md: datasheet tables for both ranges and what they change.
Pheenix is a second turnkey galvanics vendor next to Digital Matrix and
can quote lacquer-to-record as one vendor; neither range includes water
treatment. Utilities from the sheets (~27 kVA connected per line, DI water,
12-20 C cooling water, extraction sizes), ~5.6 m2 of footprint, and a cell
count estimate (one PDPU at the low end, two at the high end). The Sibert
machines are single-phase, 200/250/600 kg on castors, centre manually and
list no data interface; the VSC locates on the punched hole; the finisher's
water carries nickel. Weights, cycle times, prices and mould fit are listed
as quote questions.

Backlinks and small updates: README (bullet, layout tree, vendor list),
roadmap items 6 and 23, vendor landscape, supplier map, exhibitor briefing
(on-file notes, Sibert three-phase question answered), digital factory
(Pheenix PLC data, Sibert data question, RFQ clause 5), quality automation
(hardness on the centre slug, BD paper as the acceptance-spec model),
sustainability (finisher water), total investment block label (numbers
unchanged), scale (galvanics feeder note), crane weight table, process
flow, pressing-line stamper-fit question, plant page detail lines.
2026-10-03 21:05:00 +02:00
grabowski 4607a4da58 Plan the artist platform: price calculator and fan-funded pressing
New docs/artist-platform.md: upload master and artwork with automatic
audio, artwork and rights checks; an itemised price calculator for every
customer (per-title vs per-copy lines, price-per-copy curve, lead time
from the production-timeline quote table, versioned price list); and
fan-funded campaigns that press and dropship per fan once the goal is
reached, refund otherwise. Covers goal maths, payments (charge into a
ring-fenced account, CNX as seller of record, legal opinion first; the
Qrates failure as the design rule), repress pre-orders, architecture on
the cnx-factory stack with the public side on a fleet machine, PDPA,
phasing (calculator public early as a run-size probe, campaigns only
after first releases ship), cost and open decisions.

Backlinks from README, process flow, production timeline, revenue model,
digital factory and roadmap items 1 and 20; total investment added-scope
table gains the platform line.
2026-10-02 17:37:32 +02:00
grabowski 917a3eb933 Plan the overhead crane, maintenance workshop and visitor corridor
New docs/crane-workshop-tours.md: a 5 t single-girder EOT crane over the
whole production compartment (stops at the warehouse fire wall), a
machine door and crane-served workshop/machine bay at the ramp end, and
a glazed ground-level visitor corridor along the car-park elevation with
stations in process order, its own air and acoustic glazing so tours
need no PPE. Covers what each changes in the shell (crane-ready frame,
hook height under the 7.0 m eave, no full-height cross walls in the
crane zone, room lids and crane hatches), safety, costs and open
decisions.

Propagated: construction RFQ (crane-ready frame, new section 1c, machine
door, accessible 1:12 entrance now required), scale zone table (+210 to
280 m2, total ~1,400 to 2,000 m2), facility security, worker safety,
roadmap items 9 and 15, total investment added-scope table, README.
2026-10-02 17:34:24 +02:00
grabowski 81185d8013 Add the Sillitoe SDMS as a second mastering lathe candidate
Sillitoe Audio Technology (Australia) sells a complete cutting system:
lathe, MMFB feedback cutterhead, cutting amplifier, Space / Time Control
automation with a virtual groove, vacuum and microscope, at a published
USD 125,000 ex tax and shipping. Vendor landscape gets the narrative and
an Agnew-or-Sillitoe comparison; supplier map, total investment basis,
roadmap item 13 and the digital factory's no-telemetry section (STC cue
sheet, Open Groove export, stylus hours) follow.
2026-10-02 17:31:36 +02:00
grabowski 0fb60bcbb5 Add digital factory systems plan (NixOS fleet as one Clan)
New docs/digital-factory.md: every system needed for environmental,
machine, QC and genealogy data to land in one database keyed to one
record identity. Standing decision: all services run on NixOS machines
declared and deployed as a single clan.lol inventory (mesh, backups,
host monitoring, secrets from clan services).

Covers machine list and roles, VLAN zoning, Telegraf/MQTT acquisition
source by source with the RFQ clause for each, environment sensor zones,
QC instrument integration paths, the factory application modules and
entities, alerting tiers, backup and retention, security, procurement
clauses, build order aligned with the roadmap phases, rough cost and
open questions.

README index and layout tree updated; roadmap item 17 and the
traceability spec link to the new document.
2026-09-21 21:06:42 +02:00
grabowski 20c8d283d5 Rebase costs on USD/THB; add timelines and first market data
Currency
- Base currency moves from EUR to USD and THB throughout. Rates at
  5 Aug 2026: 1 USD = 33 THB, 1 EUR = 1.155 USD, 1 GBP = 1.35 USD.
  EUR/THB lands at ~38, so existing THB research needed no change.
- Vendor quotes keep their original currency with a USD/THB equivalent
  alongside, so they stay checkable against the source PDFs.
- Full vision ~4.7-8.9M USD; phased entry ~1.7-2.9M USD.

New documents
- production-timeline.md: order turnaround stage by stage. Launch
  8-14 weeks, mature 5-10, repress 2-3. Quantifies the in-house
  galvanics turnaround claim the repo had asserted without a number,
  and flags artwork as an unmodelled fourth approval gate.
- project-timeline.md: calendar to first paying release, ~Q4 2028.
  Critical path is BOI certificate to press order to build to
  commissioning. Two findings: Newbilt build time is absent from the
  repo yet carries ~40% of the schedule, and the BOI rule may be
  over-serialised since duty exemption attaches at importation rather
  than at contract signature.

First market data (ResurRec, Bangkok)
- Invoice-derived prices, a factory tour, and a confirmed fleet of one
  Newbilt Classic 12" automatic plus one semi-automatic.
- Price ladder recorded at 300/500/1000-3000/3000+ units. Decomposes
  to roughly 34-50k THB fixed per title and 535-780 THB variable per
  unit, which is 4-7x the price this model assumes.
- The incumbent presses 230-350k records/yr but buys every stamper as
  an import. That single constraint plausibly explains their 150-unit
  floor, their flat discount ladder and their large-run lead time, and
  it is what an in-house galvanics line attacks. Logged as an open
  question on whether galvanics should move from phase 5 to phase 1.
- Inferences are marked as inferences; the whole set is one buyer and
  one plant, and the model is deliberately left unrebased until a
  second data point exists.

Corrections
- Gross margin arithmetic did not follow from its own inputs. Restated
  as ~1.95 USD at the midpoint with the 0.75-3.15 spread shown; the
  previous "40 to 55%" was not supported.
- Direct cost low total 1.50 to 1.45 USD; contingency THB high 40M
  to 38M.
- README indexes the construction RFQ, which was missing.
2026-08-06 12:22:40 +07:00
grabowski c138177f67 Add project roadmap: 27 steps in dependency order across six phases
Three current gates (market validation, BOI, land title check) through
quotes, commitment, build, launch, and revenue-gated expansion; import
window correctly attributed to certificate issuance
2026-07-17 18:02:18 +07:00