Add Payap University land as a site candidate
Payap University (Chiang Mai) is interested in leasing land to the project; a pharmaceutical facility is under construction on the same land. New docs/site-candidates.md puts the three options side by side (Mueang Chi lease, Northern Region Industrial Estate, Payap) with the public facts on Payap (Mae Khao campus on the Chiang Mai-Lampang superhighway, bought as low-lying land, ~275 acres; Faculty of Pharmacy cosmetics production facility tendered July 2024; RPAH cannabis/herbal bioreactor centre), why it is attractive (5 km from the old city, a university partner with music, pharmacy and labs, production already being built there) and the checks that could rule it out, in order: zoning for pressing, boiler and later electroplating; whether the university can lease to a company; the GMP neighbour's sensitivity to our emissions (argues against biomass steam there); flooding; plot fit; galvanics consent. Questions for the next meeting listed. Nothing re-sited: model, RFQ and site code stay on Mueang Chi until a plot is known. README (intro, bullet, layout), roadmap item 9 and the lease fork in project-timeline link to it.
This commit is contained in:
1 parent
81f3279efd
commit
31d89faf03
4 files changed
+121
-5
No files matched your search
@@ -1,10 +1,11 @@
|
||||
# CNX Vinyl / Poy Records
|
||||
|
||||
A vinyl record factory in planning for the Chiang Mai area of northern
|
||||
Thailand (site candidates include Lamphun and Lampang provinces). This
|
||||
repository is the source of truth for the project: planning documents and
|
||||
cost data today. As the factory takes shape it will also hold the data and
|
||||
software used to run it.
|
||||
Thailand (site candidates include Lamphun and Lampang provinces and, since
|
||||
October 2026, Payap University land in Chiang Mai). This repository is
|
||||
the source of truth for the project: planning documents and cost data
|
||||
today. As the factory takes shape it will also hold the data and software
|
||||
used to run it.
|
||||
|
||||
## Team
|
||||
|
||||
@@ -139,6 +140,10 @@ The detail lives in dedicated documents:
|
||||
- [Project timeline](docs/project-timeline.md): the calendar from today to
|
||||
first paying release, the BOI-to-machinery critical path, and where the
|
||||
float actually sits
|
||||
- [Site candidates](docs/site-candidates.md): the land options side by
|
||||
side (the Mueang Chi lease, the Northern Region Industrial Estate, and
|
||||
Payap University's offer of land next to a pharmaceutical facility under
|
||||
construction) and what has to be checked before any of them is chosen
|
||||
- [Project scale](docs/scale.md): rough numbers for everything on one page:
|
||||
output capacity, building area, land, electrical demand, solar and
|
||||
storage, steam and fuel, headcount, and money cross-references
|
||||
@@ -191,6 +196,7 @@ docs/
|
||||
├── quality-automation.md Stamper metrology and layered record QC
|
||||
├── roadmap.md Next steps in dependency order
|
||||
├── scale.md Rough project sizing on one page
|
||||
├── site-candidates.md Land options and the checks before choosing
|
||||
├── sustainability.md Energy, water, materials commitments
|
||||
├── traceability.md Process logging and per-order traceability
|
||||
└── worker-safety.md Training, clean rooms, PPE
|
||||
|
||||
@@ -208,6 +208,11 @@ galvanics option alive.
|
||||
resolving before more design effort goes into the parametric model,
|
||||
because the model is only useful on one side of it.
|
||||
|
||||
A further lease option arrived in October 2026: Payap University offers
|
||||
land in Chiang Mai next to a pharmaceutical facility under construction
|
||||
([site candidates](site-candidates.md)). Its zoning is as unverified as
|
||||
Mueang Chi's, so it adds a candidate without moving the critical path.
|
||||
|
||||
## The investor's CD and cassette request
|
||||
|
||||
Adding CD and cassette to the plant has been raised by the main
|
||||
|
||||
+3
-1
@@ -57,7 +57,9 @@ These three run in parallel and gate everything downstream:
|
||||
confirm the EPC (Solar Nicolo or other) warrants a mixed-vendor DC bus
|
||||
9. **Site selection**: candidate buildings/plots in Lamphun and Lampang
|
||||
(Northern Region Industrial Estate first for its shared effluent
|
||||
treatment and licensing simplicity), screened against the
|
||||
treatment and licensing simplicity) and, since October 2026, Payap
|
||||
University land in Chiang Mai ([site candidates](site-candidates.md)),
|
||||
screened against the
|
||||
[scale requirements](scale.md): 6 to 8 rai, 1,400 to 2,000 m² single
|
||||
story (including the workshop and visitor corridor), multiple tons per
|
||||
m² slab, 500 to 1,000 kVA connection, and a frame able to carry an
|
||||
|
||||
@@ -0,0 +1,103 @@
|
||||
# Site Candidates
|
||||
|
||||
The site strategy is a long lease of raw land on which the purpose-built
|
||||
plant is constructed (business plan section 6.1, built from
|
||||
`business-plan/build/`). What any site has to offer is unchanged: ~4 rai
|
||||
minimum and 6 to 8 rai with expansion, truck access and turning, room for
|
||||
the cooling tower and a separated battery enclosure, a 500 to 1,000 kVA
|
||||
medium-voltage connection, a slab rated 3 t/m² and a frame able to carry
|
||||
the overhead crane ([scale](scale.md),
|
||||
[crane, workshop and tours](crane-workshop-tours.md)), factory permission
|
||||
for pressing with a steam boiler, and, for Phase 5, permission for an
|
||||
electroplating line ([galvanics and stamper prep](equipment/galvanics.md)).
|
||||
|
||||
## The three candidates
|
||||
|
||||
| | Mueang Chi, Lamphun | Northern Region Industrial Estate, Lamphun | Payap University land, Chiang Mai |
|
||||
|---|---|---|---|
|
||||
| Status | Working candidate: the massing model, PV roof design and [construction RFQ](finance/phase1-construction-rfq.md) are sited here | Fallback | New lead (October 2026): the university approached the project and is interested in leasing land to us |
|
||||
| Lessor | Private owner | IEAT | Payap University (private, non-profit, founded by the Foundation of the Church of Christ in Thailand) |
|
||||
| Plot | 5-0-66.5 rai, 18.4708 N, 98.9642 E, narrow and skewed | Leased estate plots | Not yet identified. The main (Mae Khao) campus is at 18.795 N, 99.033 E |
|
||||
| Distance to Chiang Mai old city | ~35 km | Lamphun valley | ~5 km east, on the Chiang Mai–Lampang superhighway |
|
||||
| Zoning for factory use | Unverified (agricultural land) | Industrial estate; licensing through the estate | Unverified |
|
||||
| Galvanics effluent | Ours to permit; zero discharge | Shared central effluent treatment | Needs the lessor's consent on top of the permit |
|
||||
| Neighbours | Agricultural | Industrial | A pharmaceutical facility under construction on the same land |
|
||||
|
||||
## Payap University (new lead, October 2026)
|
||||
|
||||
**What we know from the conversation:** Payap University is interested in
|
||||
leasing land to the project, and a pharmaceutical facility is under
|
||||
construction on the same land. The plot, its size, the title, the term and
|
||||
the rent are not known yet.
|
||||
|
||||
**Public facts.** Payap's main campus, Mae Khao, is at 272 Moo 2, San
|
||||
Phranet, San Sai district, on the Chiang Mai–Lampang superhighway. The
|
||||
university bought it in 1974 as about 120 acres of low-lying land and has
|
||||
since grown it to about 275 acres (~700 rai) with purchases across the ring
|
||||
road (Payap's own history page). Its Faculty of Pharmacy put the
|
||||
construction of a cosmetics production facility and co-working space out to
|
||||
tender in July 2024, and the university has announced a centre for
|
||||
producing active compounds from cannabis and medicinal plants by bioreactor
|
||||
(RPAH) with an industry sponsor. Whether either of these is the
|
||||
pharmaceutical facility on the offered land is to be confirmed.
|
||||
|
||||
**Why it is worth pursuing.**
|
||||
|
||||
- **Location.** About 5 km from the old city and 25 to 30 km nearer the
|
||||
team, customers and the airport than Mueang Chi. The
|
||||
[visitor corridor](crane-workshop-tours.md), the
|
||||
[artist platform](artist-platform.md) and hiring all work better in town.
|
||||
- **A partner, not only a landlord.** Payap has a College of Music,
|
||||
communication arts and business faculties (artists, mastering and
|
||||
cutting trainees, the platform's first users) and a Faculty of Pharmacy
|
||||
with analytical labs that could back the PVC material lab
|
||||
([quality automation](quality-automation.md)). A formal university
|
||||
collaboration is also the kind of R&D and skills cooperation the
|
||||
[BOI](boi.md) merit measures reward; confirm which measure applies.
|
||||
- **Production is already being built there.** If the pharmaceutical
|
||||
facility has factory permission, the land may already have a path
|
||||
through licensing and a medium-voltage supply nearby. Shared
|
||||
infrastructure (MV connection, RO water, effluent treatment) is worth
|
||||
asking about.
|
||||
|
||||
**What could rule it out** (check in this order, before any design work):
|
||||
|
||||
1. **Zoning.** The plot's colour in the Chiang Mai comprehensive city plan
|
||||
and whether it allows a record-pressing factory with a steam boiler and,
|
||||
later, electroplating. A pharmaceutical or cosmetics plant and an
|
||||
electroplating line are different factory classes, so the neighbour's
|
||||
permit proves little. Ask the provincial public works and town planning
|
||||
office, as for Mueang Chi.
|
||||
2. **Can the university lease to a company?** Title type (Chanote needed),
|
||||
university council approval, and whether campus land of a private
|
||||
higher-education institution carries restrictions on commercial leases.
|
||||
This is a question for Thai counsel, together with the lease terms the
|
||||
business plan already requires (registered 30-year lease with renewal,
|
||||
building ownership, mortgageable).
|
||||
3. **The pharmaceutical neighbour.** A GMP facility is sensitive to dust,
|
||||
smoke and fumes. Ours: the boiler stack (biomass smoke next to a
|
||||
pharmaceutical plant in town would be a hard sell, which favours
|
||||
electric or LPG steam; see [biomass](biomass.md)), galvanics extraction,
|
||||
PVC extrusion fumes, press noise and truck traffic. Agree emission and
|
||||
buffer rules in the lease rather than after the first complaint.
|
||||
4. **Flooding.** Payap describes the Mae Khao land as low-lying when bought.
|
||||
Check the plot against the 2024 flood extents; the design's floor, 1.2 m
|
||||
above ground for the loading docks, helps but is not a flood
|
||||
assessment.
|
||||
5. **Plot fit.** Shape and size against the 60 × 25 m building, the
|
||||
detached utility yard and the phase 2 footprint (6 to 8 rai).
|
||||
6. **Galvanics on a campus.** Phase 5 electroplating needs the lessor's
|
||||
written consent; the zero-discharge design
|
||||
([sustainability](sustainability.md)) becomes a lease condition, not
|
||||
only a commitment.
|
||||
|
||||
**Questions for the next meeting with Payap:** which plot (map, size,
|
||||
title deed number), its zoning and current use; what the pharmaceutical
|
||||
facility is, who operates it and when it opens; what utilities it brings
|
||||
(MV, water, wastewater); lease term, rent, renewal and building ownership;
|
||||
what collaboration the university wants in return.
|
||||
|
||||
Nothing has been re-sited. The parametric model, PV roof study, RFQ and
|
||||
the fleet site code `lpn` in the [digital factory](digital-factory.md)
|
||||
stay on Mueang Chi until a Payap plot is known and has passed checks 1
|
||||
and 2.
|
||||