grabowski 31d89faf03 Add Payap University land as a site candidate
Payap University (Chiang Mai) is interested in leasing land to the
project; a pharmaceutical facility is under construction on the same land.

New docs/site-candidates.md puts the three options side by side (Mueang
Chi lease, Northern Region Industrial Estate, Payap) with the public facts
on Payap (Mae Khao campus on the Chiang Mai-Lampang superhighway, bought
as low-lying land, ~275 acres; Faculty of Pharmacy cosmetics production
facility tendered July 2024; RPAH cannabis/herbal bioreactor centre), why
it is attractive (5 km from the old city, a university partner with music,
pharmacy and labs, production already being built there) and the checks
that could rule it out, in order: zoning for pressing, boiler and later
electroplating; whether the university can lease to a company; the GMP
neighbour's sensitivity to our emissions (argues against biomass steam
there); flooding; plot fit; galvanics consent. Questions for the next
meeting listed. Nothing re-sited: model, RFQ and site code stay on
Mueang Chi until a plot is known.

README (intro, bullet, layout), roadmap item 9 and the lease fork in
project-timeline link to it.
2026-10-03 21:31:25 +02:00
grabowski 81f3279efd Add Pheenix galvanics flyers and Sibert stamper prep specs
Deploy test site / deploy (push) Successful in 45s
docs/equipment/pheenix-alpha/: the four Pheenix Alpha electroforming flyers
(2024: PASU silvering, PPPU pre-plating, PDPU dual-cell plating, PMPB
passivation bench), renamed from their download hashes.
docs/equipment/sibert/: the VSP, VSF and VSC technical specifications
(2021), plus Sibert's 2008-09 optical-disc SPS literature and the 2008
Blu-ray stamper characteristics paper in sps-optical-disc-2009/. Two
byte-identical duplicates in the download were dropped.

New docs/equipment/galvanics.md, the metal-path counterpart to
pressing-line.md: datasheet tables for both ranges and what they change.
Pheenix is a second turnkey galvanics vendor next to Digital Matrix and
can quote lacquer-to-record as one vendor; neither range includes water
treatment. Utilities from the sheets (~27 kVA connected per line, DI water,
12-20 C cooling water, extraction sizes), ~5.6 m2 of footprint, and a cell
count estimate (one PDPU at the low end, two at the high end). The Sibert
machines are single-phase, 200/250/600 kg on castors, centre manually and
list no data interface; the VSC locates on the punched hole; the finisher's
water carries nickel. Weights, cycle times, prices and mould fit are listed
as quote questions.

Backlinks and small updates: README (bullet, layout tree, vendor list),
roadmap items 6 and 23, vendor landscape, supplier map, exhibitor briefing
(on-file notes, Sibert three-phase question answered), digital factory
(Pheenix PLC data, Sibert data question, RFQ clause 5), quality automation
(hardness on the centre slug, BD paper as the acceptance-spec model),
sustainability (finisher water), total investment block label (numbers
unchanged), scale (galvanics feeder note), crane weight table, process
flow, pressing-line stamper-fit question, plant page detail lines.
2026-10-03 21:05:00 +02:00
grabowski 293979bef8 Supplier list: drop the last em dash 2026-10-02 21:54:25 +02:00
grabowski 88220bcd1f Supplier list: drop the two remaining em dashes 2026-10-02 21:54:14 +02:00
grabowski 725f0cc9d1 Add the Newbilt flyers from Making Vinyl Europe 2026
Deploy test site / deploy (push) Successful in 35s
docs/equipment/newbilt/flyers-2026/: the six 2026 product flyers
(Classic, Duplex, EX 35, Edge Trimmer, Granulator 400, Label Punch) and
the 2024 Classic print flyer, collected at the booth in Haarlem.

pressing-line.md gets a range table with the flyer figures and what they
change: Classic and Duplex share inserts (one mould family for a
Newbilt-only fleet, Classic now named as automated candidate next to the
Pheenix AD12), edge trim of 20 to 40 g per 12" 180 g record brackets the
~20 % regrind share, the Granulator 400 runs in batches, central
hydraulics is an option, and the EX 35 is not in the 2024 quote.

Sources disagree on the Classic's panel (two 21" vs one 10"), extruder
power (7.5 kW drive in the 2024 flyer vs 15 kW noted earlier) and 10"
support; recorded as re-quote points instead of picking one. Supplier
table and exhibitor briefing corrected to match and given Erwin Neubauer
as a second contact; plant page grinder detail cites the flyer figures.
2026-10-02 21:53:45 +02:00
grabowski e23be20b13 Plant operation page: work on phones and tablets held sideways
Deploy test site / deploy (push) Successful in 37s
The header no longer forces a 1,600 px layout: it wraps on tablets and
narrow desktops (all nine KPIs now fit at 1,600 px, one was clipped
before), and on short screens (max-height 560 px, i.e. phones in
landscape) it collapses to one row with a scrolling KPI strip. There the
detail, event log and legend move into a side sheet (Info button, opens
by itself when a station is tapped), so the drawing gets the full height.

The drawing pans and zooms by viewBox, so the sim coordinates are
untouched: pinch and drag on touch, wheel and drag with a mouse, plus
zoom buttons and +/-/0 keys. A drag or pinch never selects the station
under the finger. Uses 100dvh and disables iOS landscape text inflation.
Upright phones get a hint to turn sideways.

Checked in Chrome device emulation at 667x375, 740x360, 844x390,
932x430, 1024x768, 1180x820, 1366x1024, 1258x800, 1600x900, 1920x1080
(no horizontal overflow, zoom controls clear of every station) with real
touch input (tap, tab switching, pinch, drag) and a 10x sim run without
errors.
2026-10-02 21:33:04 +02:00
grabowski 52bf35f183 Deploy workflow: check the SSH key and log its fingerprint
Deploy test site / deploy (push) Successful in 36s
A first run failed with "Permission denied (publickey)": s1 accepts only
the blog key (deploy@s1.b4l.co.th, SHA256:o4w7HL...) for the deploy user,
and the secret held a different key. The SSH step now strips CR, refuses
a secret that is not an unencrypted private key, and logs the key's
fingerprint for comparison with authorized_keys. The ssh host alias is
renamed so the masked VPS_USER value no longer hides it in the log.
2026-10-02 21:14:33 +02:00
grabowski 560d073019 Add the cnxvinyl.lol test site with a Gitea deploy workflow
Deploy test site / deploy (push) Canceled after 0s
site/ builds the internal test site: public/ served as is (landing page,
robots.txt, static sites) plus demo pages copied out of docs/ (the plant
operation page at /demos/plant-operation/). build.sh fails on dead
internal links and stamps version.txt.

.gitea/workflows/deploy-site.yml rsyncs site/dist to the buildfor.life
web server with the blog's two-directory rename swap, checks version.txt
on the server, purges Cloudflare when a token is set, and checks the
public URL. Secret names match the blog's workflow.

site/Caddyfile is the virtual host to append on s1 (noindex everywhere,
Cloudflare-only like the blog apex, www redirect). site/README.md has the
one-time setup: DNS, Caddy, web root, secrets, runner.
2026-10-02 20:59:38 +02:00
grabowski 0e033784a2 Note the internal testing domain cnxvinyl.lol 2026-10-02 20:44:10 +02:00
grabowski 4607a4da58 Plan the artist platform: price calculator and fan-funded pressing
New docs/artist-platform.md: upload master and artwork with automatic
audio, artwork and rights checks; an itemised price calculator for every
customer (per-title vs per-copy lines, price-per-copy curve, lead time
from the production-timeline quote table, versioned price list); and
fan-funded campaigns that press and dropship per fan once the goal is
reached, refund otherwise. Covers goal maths, payments (charge into a
ring-fenced account, CNX as seller of record, legal opinion first; the
Qrates failure as the design rule), repress pre-orders, architecture on
the cnx-factory stack with the public side on a fleet machine, PDPA,
phasing (calculator public early as a run-size probe, campaigns only
after first releases ship), cost and open decisions.

Backlinks from README, process flow, production timeline, revenue model,
digital factory and roadmap items 1 and 20; total investment added-scope
table gains the platform line.
2026-10-02 17:37:32 +02:00
grabowski 917a3eb933 Plan the overhead crane, maintenance workshop and visitor corridor
New docs/crane-workshop-tours.md: a 5 t single-girder EOT crane over the
whole production compartment (stops at the warehouse fire wall), a
machine door and crane-served workshop/machine bay at the ramp end, and
a glazed ground-level visitor corridor along the car-park elevation with
stations in process order, its own air and acoustic glazing so tours
need no PPE. Covers what each changes in the shell (crane-ready frame,
hook height under the 7.0 m eave, no full-height cross walls in the
crane zone, room lids and crane hatches), safety, costs and open
decisions.

Propagated: construction RFQ (crane-ready frame, new section 1c, machine
door, accessible 1:12 entrance now required), scale zone table (+210 to
280 m2, total ~1,400 to 2,000 m2), facility security, worker safety,
roadmap items 9 and 15, total investment added-scope table, README.
2026-10-02 17:34:24 +02:00
grabowski 81185d8013 Add the Sillitoe SDMS as a second mastering lathe candidate
Sillitoe Audio Technology (Australia) sells a complete cutting system:
lathe, MMFB feedback cutterhead, cutting amplifier, Space / Time Control
automation with a virtual groove, vacuum and microscope, at a published
USD 125,000 ex tax and shipping. Vendor landscape gets the narrative and
an Agnew-or-Sillitoe comparison; supplier map, total investment basis,
roadmap item 13 and the digital factory's no-telemetry section (STC cue
sheet, Open Groove export, stylus hours) follow.
2026-10-02 17:31:36 +02:00
grabowski ffcce42a51 Digital factory plan: build on the existing cnx-network clan
Rewrite docs/digital-factory.md against the fleet that already exists at
git.b4l.co.th/B4L/cnx-network-clan instead of a plant-only clan:

- The plant is one more site: gw-lpn-1 from the cnx.router module, plant
  machines in the same inventory, reached over the existing ZeroTier mesh
  (no VPS, no moon, no port forwards).
- Fleet pieces reused as-is: control for host metrics, journals and host
  alerts; ns1/ns2 for the gateway wildcard cert; web01 as the public
  proxy for the customer portal; clan borgbackup with a plant server.
- Process time series move from TimescaleDB to a plant-local
  VictoriaMetrics (same modules and rules as control); PostgreSQL keeps
  everything with identity. Object storage dropped for ZFS datasets.
- VLAN table on the fleet addressing convention (siteId 3 assumed, ids
  above 40); OT segments as dual-homed islands behind the collectors;
  stations reach the app only through the gateway Caddy proxy.
- New section listing every file that changes in the clan repo, the
  modules/vinyl/* to write, and three router-module extensions (NTP
  serving, static VLANs, second WAN).
- Gaps the plant closes for the fleet: Alertmanager delivery, off-site
  backup destination, TSDB backup.
- Repository layout decided: infra in cnx-network-clan, app in
  cnx-factory as a flake input, this repo stays documents.

README bullet updated to match.
2026-09-21 21:41:49 +02:00
grabowski 0fb60bcbb5 Add digital factory systems plan (NixOS fleet as one Clan)
New docs/digital-factory.md: every system needed for environmental,
machine, QC and genealogy data to land in one database keyed to one
record identity. Standing decision: all services run on NixOS machines
declared and deployed as a single clan.lol inventory (mesh, backups,
host monitoring, secrets from clan services).

Covers machine list and roles, VLAN zoning, Telegraf/MQTT acquisition
source by source with the RFQ clause for each, environment sensor zones,
QC instrument integration paths, the factory application modules and
entities, alerting tiers, backup and retention, security, procurement
clauses, build order aligned with the roadmap phases, rough cost and
open questions.

README index and layout tree updated; roadmap item 17 and the
traceability spec link to the new document.
2026-09-21 21:06:42 +02:00
grabowski 122d908862 Labels are pressed into the record, not applied at finishing
The docs and the plant page had labelling as a finishing step after the
press. On a record press the bottom label, the cake and the top label go
in between the stampers every cycle and the mold bonds the paper into the
vinyl; the oven only pre-dries them. Corrected everywhere the process is
described:

- process-flow.md: labels are a parallel input to pressing with their own
  row (print inspection, oven, lot per cycle); stage 6 loads label, cake,
  label; stage 7 is trim, sleeve, shrink
- process-flow.drawio (+ regenerated png/pdf): label input now feeds
  stage 6, not stage 7
- README vision list and the business plan source (regenerated docx/pdf):
  pressing paragraph explains the pressed-in label, finishing no longer
  claims to label
- plant-operation.html: label dry oven station feeds two label discs
  into the press with every cake, the cake in the mold shows its labels,
  the cycle log records the label lot, finishing is sleeve + shrink
2026-09-21 16:16:18 +02:00
grabowski c8482b7a76 Add animated plant operation page (simulated SCADA overview)
docs/plant-operation.html: one self-contained static page showing the
whole plant running, from PVC intake and the material lab gate through
extruder, press cycle (load/close/steam/cool/open/eject), trimmer, 100%
optical inspection, sampled audio comparison, finishing, packaging
(matrix code vs barcode) and fulfillment. The metal path (audio intake,
mastering, cutting, silvering, father/mother/stamper, stamper prep) runs
above with the three artist gates; utilities (steam, cooling, air,
hydraulics, grinder/regrind, energy, traceability, HVAC) below with
live-looking tags.

Numbers are taken from the repo (Newbilt site requirements, scale.md,
quality-automation.md, process-flow.md). Every station is clickable for
what happens there and the checks that gate it. Two demo buttons show a
steam pressure dip holding the press and a new PVC lot held by the lab
until a test pressing releases it. README links the page.
2026-09-21 16:01:41 +02:00
grabowski ed0260d476 Add Making Vinyl Europe 2026 exhibitor briefing and booth questions 2026-09-19 19:24:58 +02:00
grabowski fbe6a97e39 business plan pdf 2026-09-10 10:28:03 +02:00
grabowski 3934dc1dc4 Add investor business plan (draft 0.1) with its Python builder
Leased land instead of purchase, in-house cassette duplication, CD-R
duplication with CD replication shown as a separate investor decision,
Ploy Printing as packaging partner and intended co-investor, and a
dedicated section on traceability, metrology, QC and efficiency.
2026-09-10 10:20:05 +02:00
grabowski 1bbef055c4 Remove em dashes where the replacement is unambiguous
The project has a standing style rule against em dashes that was missed
when these docs were written. This removes the 42 occurrences where the
substitution is mechanical and cannot change meaning:

- table cells using an em dash as a placeholder, now a hyphen
- em dashes immediately followed by a conjunction or subordinator
  (but, and, or, so, though, while, which, where, because, since),
  where a comma is simply correct

115 remain. Those join independent clauses, where a comma would create a
splice and a colon often reads wrong, so each needs a judgement call
rather than a pattern. A blanket regex over them was attempted and
reverted: it produced double colons and broken sentences.
2026-08-06 15:31:09 +07:00
grabowski 8c8e1be451 Rewrap an over-long line left by an earlier edit 2026-08-06 12:54:52 +07:00
grabowski caa38dcd0b Rebuild the operating roll-up and labour cost from components
Both were flagged in the review and deferred; fixing them properly
changes what the model says.

Labour
- The 0.23-0.40 USD/record line implied 44,000-63,000 THB per head per
  month, far above northern Thai production rates.
- Rebuilt from headcount and wages: 13-19 direct production staff
  (operators, galvanics, QC, maintenance) at loaded northern Thai rates
  gives 3.7M-5.4M THB/yr, or 0.08-0.16 USD per record. Build-up shown.
- Mastering and cutting engineers excluded as title-services labour;
  admin and sales moved to overheads where they belong.
- Stamper amortisation widened to 0.03-0.12 to match the in-house
  marginal cost assumed elsewhere on the page.
- Direct cost total is now 1.30-2.58 USD (43-85 THB).

Operating roll-up
- The old EBITDA and operating-profit figures did not reconcile with
  their own components and showed no loss case anywhere. Replaced with
  a three-scenario table built from the components, each column
  internally consistent, with cash overheads and depreciation separated.
- The adverse case is EBITDA-positive but does NOT cover depreciation:
  operating profit -0.32M USD at 1.0M records on the low price and high
  cost. The previous figures quoted 0.6-1.2M and hid this entirely.
  Utilisation and price realisation decide solvency, not just upside.
- The favourable case is not credible and that is a finding about the
  cost table rather than the business: 69% EBITDA margin against
  industry norms of 15-25%, and 47% even at the centre. The direct cost
  table counts only per-record consumables and direct payroll. Named
  what is missing (indirect labour, scrap above the reject allowance,
  water and effluent, inbound freight, inventory carrying, sales
  commission) and marked the adverse column as the honest one until
  those lines exist.
- Payback restated per scenario: never / 2.3-4.4 yr / 1.0-1.8 yr. The
  old "5 to 8 years" came from the pre-correction margin.
- FX sensitivity and the utilisation bullet updated to match.

The table is a sensitivity, not a forecast, and now says so.
2026-08-06 12:52:14 +07:00
grabowski 4deaa2c57c Correct errors found by review; hedge unmarked inferences
A four-agent review audited arithmetic, cross-document consistency,
epistemic honesty and style. It found substantially more than the
manual pass in the previous commit. Errors that changed conclusions,
not decimals:

Arithmetic
- production-timeline: the headline lead times did not reconcile with
  the stage table on the same page. Launch is 22-49 days (was 21-39),
  mature 11.5-22 (was 14-20), repress 6.5-11.5. Including gates,
  launch is 6-17 weeks, not 8-14.
- Consequence: at 17 weeks the launch configuration is at parity with
  EU/US plants, not ahead of them. The page now compares quote to
  quote rather than a stage sum to a quoted lead time, and says so.
- The galvanics turnaround saving is 1.5-5 weeks, not 3-5.
- scale.md Duplex capacity 300-600k/yr did not reproduce from its own
  stated basis; corrected to 175-540k. production-timeline disagreed
  with scale.md on the same fleet; both now agree.
- "300 units is under an hour of pressing" was out by an order of
  magnitude on the semi-auto line: 5-8 hours.
- project-timeline carried two totals for the same quantity. Now
  27-33 months throughout, with the Gantt's two ordering breaks fixed.
- scale.md: 300 kWp covers 28-45% of consumption, not 20-35%; roof PV
  stated as both 150-200 and 247 kWp for the same roof; parking canopy
  dimensions and PV disagreed with the RFQ.
- RFQ: fire tank stated 200 m3 where both its geometry (254 m3) and
  its own mass (250 t) say 250. Drainage now gives total sealed area
  66%, not the 46% paving figure, since that is what attenuation needs.
- Galvanics payback used only the top of the saving range: 1-5 years,
  not 1-4.

Inference marked as inference
- The 22,000 THB stamper figure is an invoice RESIDUAL. It carries
  lacquer cutting, test pressings, setup and margin, so it is an upper
  bound on the stamper component, not a measurement. Everything derived
  from it now says so, and a line-itemised invoice is the top question.
- The saving was also benchmarked against the wrong supplier: CNX buys
  from Stamper Discs, not a Thai reseller. Stated as 175-665 USD until
  that quote exists.
- The stamper-bottleneck hypothesis now names its alternatives. Jacket
  print runs would produce the same symptom and would constrain CNX
  equally, which would remove the competitive read entirely.
- Competitor capacity relabelled as nameplate times an assumed OEE,
  with the assumed shift pattern stated; all rows on one 300-day basis.
- The fixed/variable decomposition keeps the shape and drops the point
  estimates: the solve point inside the flat 1000-3000 tier is
  arbitrary and moves the fixed component by nearly half.
- "Nobody in Thailand plates" reduced to "we have found no evidence",
  with a desk check named as the action.
- Cut the USD 450-700k valuation of a competitor's presses entirely.
  It extrapolated a semi-auto quote onto a different machine, ignored
  the used market, and supported no decision.
- The collaboration payback divided capex by revenue where the same
  page uses contribution elsewhere: 5-10 years, not 1-3.

Missing caveats added
- No financing is committed or modelled anywhere in this repo;
  project-timeline previously asserted money was not a constraint.
- Leasing cannot pull the launch forward on its own, since the press
  chain governs and construction has float against it.
- The whole competitive analysis is one buyer, one plant, one
  afternoon, and the primary evidence is not archived in the repo.
- ResurRec is a competitor and may decline to buy from a new entrant.
2026-08-06 12:35:37 +07:00
grabowski 20c8d283d5 Rebase costs on USD/THB; add timelines and first market data
Currency
- Base currency moves from EUR to USD and THB throughout. Rates at
  5 Aug 2026: 1 USD = 33 THB, 1 EUR = 1.155 USD, 1 GBP = 1.35 USD.
  EUR/THB lands at ~38, so existing THB research needed no change.
- Vendor quotes keep their original currency with a USD/THB equivalent
  alongside, so they stay checkable against the source PDFs.
- Full vision ~4.7-8.9M USD; phased entry ~1.7-2.9M USD.

New documents
- production-timeline.md: order turnaround stage by stage. Launch
  8-14 weeks, mature 5-10, repress 2-3. Quantifies the in-house
  galvanics turnaround claim the repo had asserted without a number,
  and flags artwork as an unmodelled fourth approval gate.
- project-timeline.md: calendar to first paying release, ~Q4 2028.
  Critical path is BOI certificate to press order to build to
  commissioning. Two findings: Newbilt build time is absent from the
  repo yet carries ~40% of the schedule, and the BOI rule may be
  over-serialised since duty exemption attaches at importation rather
  than at contract signature.

First market data (ResurRec, Bangkok)
- Invoice-derived prices, a factory tour, and a confirmed fleet of one
  Newbilt Classic 12" automatic plus one semi-automatic.
- Price ladder recorded at 300/500/1000-3000/3000+ units. Decomposes
  to roughly 34-50k THB fixed per title and 535-780 THB variable per
  unit, which is 4-7x the price this model assumes.
- The incumbent presses 230-350k records/yr but buys every stamper as
  an import. That single constraint plausibly explains their 150-unit
  floor, their flat discount ladder and their large-run lead time, and
  it is what an in-house galvanics line attacks. Logged as an open
  question on whether galvanics should move from phase 5 to phase 1.
- Inferences are marked as inferences; the whole set is one buyer and
  one plant, and the model is deliberately left unrebased until a
  second data point exists.

Corrections
- Gross margin arithmetic did not follow from its own inputs. Restated
  as ~1.95 USD at the midpoint with the 0.75-3.15 spread shown; the
  previous "40 to 55%" was not supported.
- Direct cost low total 1.50 to 1.45 USD; contingency THB high 40M
  to 38M.
- README indexes the construction RFQ, which was missing.
2026-08-06 12:22:40 +07:00
grabowski 9d5d695855 Add parametric BIM model; rework site works, envelope and phase 2
The parametric model (docs/cnx_vinyl_parametric.FCStd) is now tracked. It
is the spreadsheet-driven Arch/BIM rebuild that supersedes the hard-coded
massing in factory_building_rough.FCStd, which is kept because the current
renders still come from it.

Site works. The two gates are consolidated into a single 10.0 m bi-parting
opening, with the wall plugged where the second one stood. The guard house
sits beside it clear of the entry corridor, and was raised out of the
ground - it had been modelled sunk half a storey. The fire water tank moved
to the north-west corner of the plot, taking utility-yard clearance from
5.6 m to 18.6 m; the fire pump house follows it. The site is now paved
continuously from the frontage through to phase 2: 4,387 m², split 1,608
heavy-duty and 2,779 general so the two can be priced apart.

Phase 1 envelope. The walls stopped flat at 8.2 m while the roof rose to
12.6 m, leaving the entire high-side wall and both gable triangles open -
about 366 m². Walls now follow the roof underside exactly. The rebuild also
starts the sandwich panel on top of the masonry dado, clearing a 31.9 m³
overlap that had been double-counting 425 m² of envelope. A vehicle ramp
(10.5 m at 1:10) and three stair flights are added, since with FFL at
+1.2 m the building had no means of access at grade.

Phase 2. Built from the design already documented in scale.md: 45 x 38 m,
two-bay sawtooth at 10.35/7.0 m with a 3.35 m glazed riser, bays falling
ESE. A three-storey office cube - canteen, office, office plus sleeping -
stands at the yard end of the west tooth, 1.65 m proud of the ridge. Its
walls and the hall walls are Arch Walls, and the yard glazing is Arch
Windows, so both carry IFC types and cut their own openings.

RFQ updated against the model throughout, with a new section on where
mineral-wool core is required instead of PIR, for compartmentation and for
acoustics.
2026-08-05 16:38:24 +07:00
grabowski bbeaed7e87 Add loading dock, second gate, and phase 1 construction RFQ
Site model: two sealed dock positions on the north gable (depressed
12 m pit + 12 m ramp cut into ground and paving), water treatment
moved clear of the cooling tower, second car/staff gate on the NE
edge with access road to parking, guard house relocated between the
gates, perimeter wall rebuilt continuous on its 0.4 m inset line,
leftover door recesses filled on both envelopes, loading-apron
marking removed. Renders re-exported.

Docs: phase 1 contractor pricing request (PEB spec, PIR envelope,
dock, site works, exclusions, soil caveats).
2026-07-30 18:11:30 +07:00
grabowski ed987b4375 Fix render camera orientation so world up is up in frame
setViewDirection leaves camera roll unconstrained, so the aerials came
out with a tilted horizon. The camera orientation is now built explicitly
with world +Z projected as the frame up-vector.

Two FreeCAD quirks had to be worked around. setCameraOrientation() goes
through an animated setter (UseAnimation defaults on), so saveImage fired
mid-transition and the roll drifted; setting the Coin camera node
directly avoids the animation entirely. The first call after a standard
view also needs a second application to take, so each render now verifies
up.z equals cos(elevation) before saving and retries if not.

Also tightened framing 20%, since fitAll was zooming out to include the
road strip that runs well past the parcel.
2026-07-30 01:12:28 +07:00
grabowski 9aff3a5c24 Replace renders with a top-visible set only
The first pass included two orthographic elevations and a low approach
view, which read the site edge-on and showed no roof. Dropped those.

The set is now six views that all look down: a straight-down site plan,
four aerials at 45 degrees from each corner, and one 35 degree hero shot.
2026-07-30 00:58:09 +07:00
grabowski e2ad342a1a Export site renders; pin the freecad-mcp MCP server
Nine 2400px views of the site model in docs/renders: an isometric, a
site plan, dimetric and trimetric, four aerial obliques from each corner,
a low approach view from the road, and two orthographic elevations.

Also hardens the freecad MCP entry added in the previous commit. It ran
"uvx freecad-mcp" unpinned, which resolves and executes whatever version
is current at every launch. Now pinned to 0.1.20 and marked optional, in
line with the ruv-swarm and flow-nexus entries alongside it.
2026-07-30 00:54:20 +07:00
grabowski c4d0e08c9f Add site massing model for the Mueang Chi candidate parcel
Models the plot and everything on it in FreeCAD, and writes up the
decisions the modelling forced.

Parcel geometry is traced from the DOL LandsMaps cadastral polygon and
reconciled against that portal's own measured edge lengths (40.86 + 26.61
/ 166.81 / 42.48 + 14.94 / 152.46 m), which the trace reproduces to within
about 1% with 1.67 m of closure error over a 444 m perimeter. Note the
mapped extent comes out near 9,570 sqm against a deed area of 8,266 sqm,
a ~16% gap that needs a surveyor before any offer.

On the site: 60x25 m production building on a 10 degree monopitch, a
45x38 m phase-2 building, roof and carport PV, fire and raw water tanks,
a detached boiler/chiller utility yard, perimeter wall and gate, guard
house, roofed staff parking, and the loading and fire-access roads.

Docs:
- scale.md: expansion headroom for a second building, and the detached
  utility yard, which frees ~126 sqm inside the main shed
- sustainability.md: roof orientation study (rotating the building for
  solar gains under 1 point and costs 4 m of clearance, so it stays
  aligned to the plot), and a new water supply section
- facility-security.md: fire water supply behind the existing
  suppression design

Figures marked as estimates are planning-grade, not engineering
calculations; the PV module spec is a generic placeholder, and zoning for
factory use on this plot is still unverified.
2026-07-29 23:00:09 +07:00
grabowski c138177f67 Add project roadmap: 27 steps in dependency order across six phases
Three current gates (market validation, BOI, land title check) through
quotes, commitment, build, launch, and revenue-gated expansion; import
window correctly attributed to certificate issuance
2026-07-17 18:02:18 +07:00
grabowski 195dbff1f4 Add revenue model: 3.2M-5.9M EUR/yr at full capacity, per-record economics
Blended pressing price, direct cost breakdown, margin, EBITDA and payback
bands; all arithmetic reviewer-recomputed; adverse payback corner stated
honestly alongside mid assumptions
2026-07-17 17:56:23 +07:00
grabowski 89da2af9c3 Add total investment roll-up: 4M-7.7M EUR full vision, 1.5M-2.5M EUR phased entry
All sums and conversions reviewer-recomputed; every block carries its
basis (quote, researched range, or marked estimate)
2026-07-17 17:46:27 +07:00
grabowski c95874ce6f Add project scale summary: capacity, building, land, electrical, solar, headcount
All derived figures reviewer-recomputed; BESS runtime corrected to the
chiller's electrical draw (2-3 h, not 1 h of thermal rating)
2026-07-17 17:37:20 +07:00
grabowski 50a75c1fa4 Add biomass fuel strategy: 60 rai coppice idea and northern fuel market
Own land yields ~80-135 t/yr vs ~350-400 t/yr mature demand; forestry
classification check gates everything; staged electric-first path with
coppice planted now for the expansion-phase biomass boiler
2026-07-17 17:16:06 +07:00
grabowski 5184014a2d Add energy efficiency architecture: heat recovery before generation
Press cooling return (60 C) feeds heat pump into boiler feedwater; waste
heat runs label oven and HVAC dehumid reheat; solar thermal preheat;
steam accumulator; boiler does only the final lift. Heat pumps for the
final 180 C steam and ground-source in tropical Thailand both ruled out
with reasoning; northern Thailand LPG tank context documented
2026-07-17 17:09:35 +07:00
grabowski 6648eb00b2 Add Thai utilities investment CSV with supplier candidates and budgetary ranges
Steam, compressed air, cooling, water treatment, racking, HVAC, solar EPC
and BESS; baseline total 23.98M-41.63M THB, options priced separately;
all figures budgetary +/- 30%, basis marked per row
2026-07-17 16:39:46 +07:00
grabowski b2ab630231 Add BOI investment promotion strategy
Group B base activity (plastics) with non-tax package and machinery duty
exemption; CIT value engineered via solar/BESS, smart-and-sustainable
automation, and R&D merit measures; NEC/Lamphun regional angle; BOI
approval sequenced ahead of incorporation and machinery orders
2026-07-17 15:54:53 +07:00
grabowski 11b7df3be4 Add end-to-end process flow document and diagram; floor loading criterion
- docs/process-flow.md: mermaid chart plus stage table of every check and
  the three artist approval gates, from audio intake to fulfillment
- docs/process-flow.drawio with PNG and PDF exports
- pressing-line.md: floor must carry multiple tons per m2 in machine areas
- README: process-flow entry in document index and layout tree
2026-07-17 15:48:48 +07:00
grabowski c07c554169 Add marking method per material: cold scribe on lacquers, laser on nickel, none on PVC
Laser marking excluded on lacquers (nitrocellulose flammability) and on
pressed records (HCl fumes from PVC), per the safety commitments
2026-07-17 15:28:24 +07:00
grabowski c5ec01369b Add stamper part marking and orientation fiducials; label alignment noted as deprioritized option 2026-07-17 15:26:34 +07:00
grabowski d194ebdc30 Add tiered PVC lab checks: per-lot benchtop, in-house workhorses, external qualification panel 2026-07-17 15:23:36 +07:00
grabowski 5b6beba305 Soften packaging assembly-check claim per review 2026-07-17 15:17:11 +07:00
grabowski d85e8fec8d Add raw PVC per-lot and packaging QC gates to quality automation spec 2026-07-17 15:16:33 +07:00
grabowski 808e3e34b8 Add quality automation spec: stamper metrology and layered record QC
- Keyence-class instrument stack for father/mother/stamper analysis
  (VK-X confocal sampled zones, VR-6000 wide-area, XRF thickness) with
  genealogy integration via middleware
- Three-layer pressed-record QC: 100% inline optical inspection,
  per-cycle press telemetry, sampled automated audio comparison
- Honest limits documented: no turnkey products exist for the optical
  and audio layers; 100% audio QC impossible at press speed
2026-07-17 13:56:45 +07:00
grabowski 6c1b1e7bbd Add factory layout concept diagram and fix fire-suppression section structure
- docs/facility-layout.drawio: zoned floor concept (production, galvanics,
  utilities, logistics, support) with material and stamper flow arrows
- PNG and PDF exports alongside the source
- facility-security.md: suppression subsection no longer splits the fire
  safety bullet list; clean agent wording updated to FK-5-1-12
2026-07-17 13:41:23 +07:00
grabowski 0b79c4fb73 Add whole-factory HVAC requirement and process traceability spec
- facility-security.md: continuous temperature/humidity/PM control, zoned
  filtration, burning-season PM2.5 design point, HVAC in PV/battery sizing
- traceability.md: end-to-end per-order customer traceability, batch
  genealogy, log-at-source principles, machine data access as a
  procurement requirement
2026-07-17 13:05:46 +07:00
grabowski 0a4f47a5cc Split README into topic documents
- README reduced to overview with linked document index
- docs/equipment/pressing-line.md: fleet strategy, Newbilt plan, site reqs
- docs/suppliers/vendor-landscape.md: researched vendor narratives
- docs/sustainability.md: solar, zero-discharge water, materials
- docs/worker-safety.md: training, clean rooms, PPE
- docs/facility-security.md: access control, CCTV, archive/audio protection,
  fire and life safety, plant monitoring, Thai compliance anchors
2026-07-17 12:51:04 +07:00
grabowski 6281c5b223 Add solar hardware plan: Deye hybrid inverters + Gobel Power 271 kWh BESS
Includes open engineering checks: battery rack voltage vs Deye model
window, Gobel safety certifications, and peak-shaving-scale framing
2026-07-17 12:41:52 +07:00
grabowski 4c44b39e0c Add vendor landscape to README and equipment supplier map
- README: vendor sections for Agnew Analog (lathe), Plating Power/Digital
  Matrix (galvanics), Sibert (stamper prep), Stamper Discs (bridge stamper
  service), Pheenix Alpha (automated presses)
- docs/suppliers/equipment-suppliers.md: full needs list and supplier map
  across all nine areas of the production chain
2026-07-17 12:22:04 +07:00