grabowski 89da2af9c3 Add total investment roll-up: 4M-7.7M EUR full vision, 1.5M-2.5M EUR phased entry
All sums and conversions reviewer-recomputed; every block carries its
basis (quote, researched range, or marked estimate)
2026-07-17 17:46:27 +07:00
grabowski c95874ce6f Add project scale summary: capacity, building, land, electrical, solar, headcount
All derived figures reviewer-recomputed; BESS runtime corrected to the
chiller's electrical draw (2-3 h, not 1 h of thermal rating)
2026-07-17 17:37:20 +07:00
grabowski 50a75c1fa4 Add biomass fuel strategy: 60 rai coppice idea and northern fuel market
Own land yields ~80-135 t/yr vs ~350-400 t/yr mature demand; forestry
classification check gates everything; staged electric-first path with
coppice planted now for the expansion-phase biomass boiler
2026-07-17 17:16:06 +07:00
grabowski b2ab630231 Add BOI investment promotion strategy
Group B base activity (plastics) with non-tax package and machinery duty
exemption; CIT value engineered via solar/BESS, smart-and-sustainable
automation, and R&D merit measures; NEC/Lamphun regional angle; BOI
approval sequenced ahead of incorporation and machinery orders
2026-07-17 15:54:53 +07:00
grabowski 11b7df3be4 Add end-to-end process flow document and diagram; floor loading criterion
- docs/process-flow.md: mermaid chart plus stage table of every check and
  the three artist approval gates, from audio intake to fulfillment
- docs/process-flow.drawio with PNG and PDF exports
- pressing-line.md: floor must carry multiple tons per m2 in machine areas
- README: process-flow entry in document index and layout tree
2026-07-17 15:48:48 +07:00
grabowski 808e3e34b8 Add quality automation spec: stamper metrology and layered record QC
- Keyence-class instrument stack for father/mother/stamper analysis
  (VK-X confocal sampled zones, VR-6000 wide-area, XRF thickness) with
  genealogy integration via middleware
- Three-layer pressed-record QC: 100% inline optical inspection,
  per-cycle press telemetry, sampled automated audio comparison
- Honest limits documented: no turnkey products exist for the optical
  and audio layers; 100% audio QC impossible at press speed
2026-07-17 13:56:45 +07:00
grabowski 0b79c4fb73 Add whole-factory HVAC requirement and process traceability spec
- facility-security.md: continuous temperature/humidity/PM control, zoned
  filtration, burning-season PM2.5 design point, HVAC in PV/battery sizing
- traceability.md: end-to-end per-order customer traceability, batch
  genealogy, log-at-source principles, machine data access as a
  procurement requirement
2026-07-17 13:05:46 +07:00
grabowski 0a4f47a5cc Split README into topic documents
- README reduced to overview with linked document index
- docs/equipment/pressing-line.md: fleet strategy, Newbilt plan, site reqs
- docs/suppliers/vendor-landscape.md: researched vendor narratives
- docs/sustainability.md: solar, zero-discharge water, materials
- docs/worker-safety.md: training, clean rooms, PPE
- docs/facility-security.md: access control, CCTV, archive/audio protection,
  fire and life safety, plant monitoring, Thai compliance anchors
2026-07-17 12:51:04 +07:00
grabowski 6281c5b223 Add solar hardware plan: Deye hybrid inverters + Gobel Power 271 kWh BESS
Includes open engineering checks: battery rack voltage vs Deye model
window, Gobel safety certifications, and peak-shaving-scale framing
2026-07-17 12:41:52 +07:00
grabowski 4c44b39e0c Add vendor landscape to README and equipment supplier map
- README: vendor sections for Agnew Analog (lathe), Plating Power/Digital
  Matrix (galvanics), Sibert (stamper prep), Stamper Discs (bridge stamper
  service), Pheenix Alpha (automated presses)
- docs/suppliers/equipment-suppliers.md: full needs list and supplier map
  across all nine areas of the production chain
2026-07-17 12:22:04 +07:00
grabowski d9970d335f Update README: remove em dashes, add packaging/dropshipping, 50/50 press fleet strategy 2026-07-17 11:58:13 +07:00
grabowski d1bffb217e Rename B4L to buildfor.life 2026-07-17 11:53:22 +07:00
grabowski abfa6f1ee1 Correct project attribution: add team section, B4L is consulting support 2026-07-17 11:53:06 +07:00
grabowski 08a1607e22 Add README: project vision, equipment plan, sustainability and safety commitments 2026-07-17 11:51:11 +07:00