Launch plant roll-up and the investor's 180M THB question

Decided (user, October 2026): the plant launches with everything in one
capital round, commissioned in sequence: one Newbilt Duplex system, one
Classic, a Pheenix galvanics line with ZLD water, the Sibert line, a
Sillitoe cutting room, and the modular steam and cooling plant (2 x 500
kg/h boilers, 2 x 250 kW chillers, rooms for four each). No bridge
stampers, no outsourced cutting; cassette and CD-R stay; the second
Duplex and further Classics are growth options, not in the investment.

total-investment.md: new 'Launch plant' roll-up, 4.9M to 8.9M USD,
161M to 292M THB incl. 15 % contingency (midpoint ~227M), with what is
left out (ramp-up reserve ~10-20M THB, CD replication, financing, FX,
archive shelving) and the BOI assumption. The investor's question (180M
THB, maybe +20 % = 216M): fits at the low end only; at the midpoint four
levers that keep every machine (solar via PPA, metrology launch tier,
galvanics near OMS's reference, visitor corridor later) give ~193M, plus
reserve ~203-213M, inside 216M; 180M needs low quotes. The quotes that
decide it: Newbilt (Duplex, Classic), Pheenix galvanics, building with
soil test, metrology. Old full vision and phased entry marked superseded
until the mirrors are re-based.

Utilities CSV: chiller bank two modules (4.9-7.9M THB), boiler note for
B-1 and B-2 at launch, ZLD and DI rows now launch scope (carried with
galvanics); baseline 28.47M-48.73M THB. README project status.
This commit is contained in:
grabowski committed 2026-10-16 14:53:19 +07:00
1 parent 07ef9c0b9a
commit 553b4a93d1
3 files changed
+125 -10

No files matched your search

+9
View File
@@ -67,6 +67,15 @@ steps are open planning items.
investor (October 2026). Post-show follow-ups with Pheenix, Sibert, OMS
and SST are in the
[exhibitor briefing](docs/suppliers/making-vinyl-europe-2026-exhibitors.md#after-the-show).
- The plant now launches with everything in one capital round (October
2026): one Newbilt Duplex system and one Classic, a Pheenix galvanics
line, the Sibert stamper-prep line, a Sillitoe cutting room and the
modular boiler and chiller plant. The investor asked whether it can be
built for 180M THB, possibly 20 % more: on current estimates it costs
~161M to 292M THB (midpoint ~227M), so 216M is a realistic target with
four levers and 180M a low-quote case
([total investment](docs/finance/total-investment.md#launch-plant-october-2026)).
The business plan is being re-based on it.
## Planning Documents
+111 -5
View File
@@ -12,7 +12,111 @@ wherever they appear next to their source document, and converted here at
July 2026; the underlying THB estimates are unchanged, because EUR/THB at
~38 is where it was when they were made.
## Full vision, all blocks
## Launch plant (October 2026)
Decided (user, October 2026): the plant launches **with everything in one
capital round**, commissioned in sequence, with no bridge stampers and no
outsourced cutting:
- one **Newbilt Duplex** system: two HRP 12 semi-automatic presses, an
EX 50 main and an EX 35 colour extruder
([pressing line](../equipment/pressing-line.md));
- one **Newbilt Classic** fully automatic press;
- one **Pheenix Alpha** galvanics line (PASU, PPPU, one PDPU, PMPB) with
zero-discharge water treatment
([galvanics and stamper prep](../equipment/galvanics.md));
- the **Sibert** stamper-prep line (VSF, VSP, VSC);
- a **Sillitoe SDMS** cutting room
([vendor landscape](../suppliers/vendor-landscape.md#mastering-and-cutting-sillitoe-audio-technology-australia));
- the **modular steam and cooling plant**: two 500 kg/h boiler modules and
two 250 kW chiller modules, in a boiler hall and a chiller compound
built for four each ([scale](../scale.md#utility-phasing-backbone-once-modules-with-the-presses)).
Cassette and CD-R duplication stay in. The second Duplex system and the
further Classics are growth options with room reserved, not in this
investment. Three presses make roughly 0.7 to 0.95 million records a year
on two shifts (estimate: the [scale](../scale.md) basis gives ~0.71 to
0.97 million, the planning rates of the
[fleet calculator](../fleet-calculator.html) ~0.94 million).
| Block | USD | THB | Basis |
|---|---|---|---|
| Phase 0: BOI consultant, legal and lease work, soil test, re-quotes | 40k – 80k | 1.3M – 2.6M | estimate |
| Newbilt Duplex system (two HRP 12, EX 50 + EX 35, trimmer, label oven, shrink wrapper, grinder, label punch) | 350k – 370k | 11.6M – 12.2M | 2024 quote EUR 200,500 for the Single 2.1 plus the quoted second press and extruder ~USD 115k; expired, re-quote |
| Newbilt Classic | 290k – 460k | 9.6M – 15.2M | placeholder (the old AD12 band per press); **no Newbilt price on file** |
| Pheenix galvanics line (PASU, PPPU, PDPU, PMPB) | 320k – 650k | 10.6M – 21.4M | estimate; **no Pheenix price on file**; OMS's reference prices for a 4-cell wet room (EUR 224k to 311k, ~USD 259k to 359k) sit at the low end |
| Galvanics water: ZLD evaporator and DI water | 97k – 258k | 3.2M – 8.5M | [utilities CSV](utilities-investment.csv) rows, now launch scope |
| Water-treatment building next to galvanics (~12 × 10 m, proposed) | 52k – 87k | 1.7M – 2.9M | estimate at the building rate below |
| Sibert VSF, VSP, VSC | 250k | 8.3M | Sibert's budget confirmation, 5 October 2026; its time, spares, shipping and travel in the freight and working-capital lines |
| Cutting room: Sillitoe SDMS, spare cutterhead and support, mastering console and chain, monitoring, room build-out | 200k – 350k | 6.6M – 11.6M | SDMS list price USD 125k (ex tax and shipping); the rest estimate |
| Metrology and QC stack (XRF, laser confocal, wide-area profiler, inline vision on three presses, audio station) | 350k – 810k | 11.6M – 26.7M | estimate, phaseable ([quality automation](../quality-automation.md)) |
| PVC lab, day-one tier | 55k – 150k | 1.8M – 5.0M | estimate, [quality automation](../quality-automation.md) |
| Utilities, solar, battery, HVAC, clean zones, racking | 863k – 1,477k | 28.5M – 48.7M | [utilities CSV](utilities-investment.csv) baseline re-sized for three presses: chiller bank two modules instead of three |
| Building ~1,500 m² plus civil and site works | 650k – 1,100k | 21.4M – 36.3M | estimate at 12,000 – 20,000 THB/m² plus ~20 % site works; soil is the main variable |
| Overhead crane, runway, frame premium, machine door | 97k – 227k | 3.2M – 7.5M | estimate, [crane, workshop and tours](../crane-workshop-tours.md) |
| Maintenance workshop and machine bay fit-out | 30k – 76k | 1.0M – 2.5M | estimate, same |
| Visitor corridor and accessible entrance | 67k – 148k | 2.2M – 4.9M | estimate, same |
| Utility yard built for four boiler and four chiller modules | 73k – 122k | 2.4M – 4.0M | estimate, [scale](../scale.md#detached-utility-yard-parking-and-what-that-moves) |
| Factory software, ERPNext, artist platform public side | 115k – 310k | 3.8M – 10.2M | estimate: factory software 60k – 170k, ERPNext implementation 15k – 50k ([digital factory](../digital-factory.md#erpnext-the-plants-erp)), artist platform 40k – 90k ([artist platform](../artist-platform.md)) |
| Cassette duplication and CD-R duplication | 55k – 190k | 1.8M – 6.3M | estimate, business plan sections 4.8 and 4.9 |
| Freight, installation, commissioning, training (Pheenix, Sibert, Sillitoe, Newbilt beyond its quoted 5 days) | 150k – 300k | 5.0M – 9.9M | estimate |
| Working capital, PVC stock, spares, lease deposit, first-year rent | 135k – 290k | 4.5M – 9.6M | estimate; land is leased, so no land purchase |
| Subtotal | ~4.24M – 7.71M | ~140M – 254M | |
| Contingency 15 % | ~0.64M – 1.16M | ~21M – 38M | |
| **Total, launch plant** | **~4.9M – 8.9M USD** | **~161M – 292M THB** | midpoint ~6.9M USD, ~227M THB |
Not in the total: a **reserve for the ramp-up** (staff hired before first
revenue, overheads until volume covers them; ~10M to 20M THB, estimate),
CD replication, financing costs, currency moves, and the archive's mobile
shelving (to quote). The blocks are vendor prices without Thai duty or
import VAT, so they assume BOI promotion: without it, ~5 % duty on ~2.3M
USD of imported machinery (~0.11M USD) comes on top, plus ~0.17M USD of
import VAT paid at the border and reclaimed later (estimates).
### The investor's question: 180M THB, maybe 20 % more (October 2026)
The project's investor asked whether the plant can be built for **180M
THB (~5.45M USD), possibly up to 20 % more (216M THB, ~6.55M USD)**.
| Case | Launch plant | Against 180M | Against 216M |
|---|---|---|---|
| Low end of every block | ~161M THB | fits, ~19M to spare | fits |
| Midpoint | ~227M THB | ~47M over | ~11M over |
| High end of every block | ~292M THB | ~112M over | ~76M over |
**Read honestly: 216M THB is a realistic target for the full equipment
list; 180M THB holds only if the open quotes land low.** At the midpoint
four levers bring the plant inside 216M without dropping any of the
machines decided above (midpoint values with their share of the
contingency, estimates):
| Lever | Saves | Launch plant after it |
|---|---|---|
| Rooftop solar and battery through a solar PPA (the EPC owns and finances the array, the plant buys the power) instead of buying them | ~12.3M THB | ~214M THB |
| Metrology launch tier (XRF, inline vision, audio station), the laser confocal and the wide-area profiler bought from revenue | ~10.1M THB | ~204M THB |
| Pheenix galvanics priced near OMS's reference for a 4-cell wet room | ~6.7M THB | ~198M THB |
| Visitor corridor built later; the plant runs without public tours at first | ~4.1M THB | ~193M THB |
Add the ramp-up reserve of ~10M to 20M THB and that is **~203M to 213M
THB, inside the 216M**. Reaching 180M at the midpoint needs scope cuts on
top: cassette and CD-R later (~4.6M THB) and renting a crane for the
installations while the frame stays crane-ready (~3.7M THB) give ~185M
before the reserve, still above 180M, so 180M is a low-quote outcome, not
a plan.
What decides it: the two largest machine lines have no price at all (the
Classic and the Pheenix galvanics line), and the building depends on the
soil. Four requests settle most of the band: the Newbilt re-quote for the
Duplex and the Classic, a Pheenix quote for the galvanics line, the
building RFQ with a soil test, and distributor quotes for the metrology
stack. Until they are in, quote **~216M THB** to the investor as the
target with the levers above, and 180M as the low-quote case.
## Full vision, all blocks (July 2026, superseded)
The five-press full vision below is superseded by the launch plant above.
It stays until the documents that quote its 4.7M to 8.9M USD total (README,
roadmap, revenue model, business plan) are re-based on the launch plant.
| Block | USD | THB | Basis |
|---|---|---|---|
@@ -54,10 +158,12 @@ building, software and stamper prep lines, and the contingency on top).
| Archive mobile shelving for the father and mother archive (October 2026) | to quote | to quote | not in the sum: A-Z Solutions publishes no prices; quote it and a Thai supplier ([facility security](../facility-security.md#archive-room-mobile-shelving)) |
| **Added so far** | **~678k – 1,027k** | **~22.3M – 33.9M** | about 13 to 17% on the full-vision subtotal |
## Phased entry
## Phased entry (superseded October 2026)
A credible launch phase is far smaller, roughly **1.7M to 2.9M USD
(~57M to 95M THB)**:
Superseded by the launch plant above, which launches with galvanics, the
cutting room and three presses. The earlier phased entry, kept for
reference: a launch phase of roughly **1.7M to 2.9M USD (~57M to 95M
THB)**:
- Newbilt Single system (not Duplex yet)
- Bridge stampers from Stamper Discs, so no galvanics line at launch
@@ -85,7 +191,7 @@ exactly this reason.
start fleet (estimate)
- **Buy vs lease** on land and building swings roughly **1.0M to 2.1M
USD (~34M to 69M THB)** of upfront capital, and also moves the launch
date by about three quarters — see
date by about three quarters; see
[project-timeline.md](../project-timeline.md)
- **Biggest uncertainty bands**: metrology (partly a choice of ambition),
the mastering/cutting room (bespoke vendor, no public pricing), the
+5 -5
View File
@@ -1,18 +1,18 @@
category,item,spec_summary,candidate_thai_suppliers,cost_low_thb,cost_high_thb,cost_basis,notes
steam,Electric/gas once-through boiler bank,"2 x 500 kg/h modules at 10.5 bar / 180 C, lead/lag, shared feed tank, feed pumps, economizer, installed",Miura Thailand (Chachoengsao); Bangkok Industrial Boilers; STE Thailand,4500000,7000000,engineering estimate,"Five-press fleet 750-900 kg/h (steam-cooling.html); B-1 with the launch press, B-2 with Duplex 2; a third module for N+1 is an RFQ option; Miura-class modular once-through; service is Bangkok-centric, confirm northern dispatch SLA"
steam,Electric/gas once-through boiler bank,"2 x 500 kg/h modules at 10.5 bar / 180 C, lead/lag, shared feed tank, feed pumps, economizer, installed",Miura Thailand (Chachoengsao); Bangkok Industrial Boilers; STE Thailand,4500000,7000000,engineering estimate,"Launch plant (October 2026): one Duplex system and one Classic, 450-540 kg/h at Newbilt's 150-180 kg/h per press, so B-1 and B-2 both at launch; the boiler hall is built for four modules (scale.md utility phasing); a third module for N+1 is an RFQ option; Miura-class modular once-through; service is Bangkok-centric, confirm northern dispatch SLA"
steam,Biomass/wood-fired boiler package (option),"~1 t/h solid fuel (wood chips/pellets/rice husk) incl. fuel feed, grate, dust control, softener, installed",Getabec PCL (Thai fabrication and service),6000000,10000000,engineering estimate,"Sized for the five-press fleet (was ~0.5 t/h for one Duplex); sustainability path matching Deepgrooves NL precedent; higher capex, lower fuel opex in the North; NOT included in baseline total"
steam,Steam balance of plant,"Traps, accumulator, condensate return",Forbes Marshall Thailand,0,0,included,Largely included in boiler package rows; line kept for RFQ completeness
compressed_air,Screw compressor skid (oil-injected),"~7.5 kW VSD screw + refrigerated dryer (3 C PDP) + coalescing filters + ~500 L receiver, installed",Atlas Copco Thailand; Kaeser Thailand (SM-T/Aircenter); Ingersoll Rand Thailand,350000,600000,engineering estimate,14-30 m3/h demand is small (5-10 hp class); oil-injected + filter train meets 5 micron / 3 C spec
compressed_air,True oil-free class-0 (option),Same duty in oil-free class-0,Atlas Copco (ZR/ZT); Kaeser,1200000,1800000,engineering estimate,Only if air contacts product stream; NOT included in baseline total
cooling,Process chiller bank 3 x 250 kW,"3 x ~71 RT air-cooled screw/scroll chillers rated at 40 C ambient + primary pumps + plate HX + warm and cold tanks + VFD supply pumps + controls, installed",Trane Thailand; Carrier Thailand; Daikin Applied Thailand; Hitachi Thailand,6500000,10500000,engineering estimate,"Five-press fleet up to ~650 kW and 305-540 l/min (Newbilt site requirements, 20-25 C supply); one module per press stage; 3 x 350 kW for N+1 as the alternative (steam-cooling.html)"
cooling,Process chiller bank 2 x 250 kW,"2 x ~71 RT air-cooled screw/scroll chillers rated at 40 C ambient (CH-1, CH-2) + primary pumps + plate HX + warm and cold tanks + VFD supply pumps + controls, backbone (HX frame, tanks, pumps, mains) sized for four modules, installed",Trane Thailand; Carrier Thailand; Daikin Applied Thailand; Hitachi Thailand,4900000,7900000,engineering estimate,"Launch plant (October 2026): Duplex system ~261 kW hot-afternoon peak (scale.md) plus the Classic up to ~125 kW (Newbilt per press), ~390 kW against 500 kW installed; was 3 x 250 kW at 6.5-10.5M for five presses, less one module at ~1.6-2.6M THB (estimate); CH-3 and CH-4 come with the growth options; 3 x 350 kW frame pads stay the alternative (steam-cooling.html)"
cooling,Cooling tower + HX loop (alternative),Dry cooler or FRP tower ~650-750 kW reject + plate HX + pumps + tanks + water treatment,"Liang Chi Thailand (tower, large service org); Process Cooling Solutions; Tasaki (integrators)",2000000,3500000,engineering estimate,Cheaper capex but wet-bulb-limited; hybrid tower + trim chiller is the efficiency-optimal design; NOT included in baseline total
water,Boiler feedwater duplex softener,~1.0-1.2 m3/h feedwater duty (five-press boiler bank),Veolia Water Technologies Thailand; Hydrotek; local RO/softener integrators,120000,300000,market estimate,May suffice alone for a small fire-tube boiler
water,RO skid (option),0.5-1 m3/h low-TDS feed,Veolia; Hydrotek; local integrators,200000,500000,market estimate,Only if low-TDS feed needed; NOT included in baseline total
water,RO skid (option),0.5-1 m3/h low-TDS feed,Veolia; Hydrotek; local integrators,200000,500000,market estimate,"Launch scope since October 2026 as the DI water supply for the galvanics PMPB (with polishing); carried in the galvanics water block of total-investment.md, so NOT included in this baseline total"
water,Closed-loop cooling water treatment,Side-stream filtration + dosing + conductivity blowdown control,Veolia; Hydrotek; local integrators,200000,500000,engineering estimate,"Sized for the five-press loop with its open return tank (Newbilt press outlets are open, max. 2 bar); chemicals are ongoing opex on top"
water,Galvanics ZLD evaporator (future),"Small MVR or low-temp vacuum evaporator for plating rinse, installed","Core unit imported (WTEYA, Greenlan, Fred); Thai integration via Veolia or Hydrotek",3000000,8000000,market estimate,"For the future galvanics line, zero-discharge requirement; NOT included in baseline total"
water,Galvanics ZLD evaporator,"Small MVR or low-temp vacuum evaporator for plating rinse, installed","Core unit imported (WTEYA, Greenlan, Fred); Thai integration via Veolia or Hydrotek",3000000,8000000,market estimate,"Launch scope since October 2026 (galvanics in-house from the start); carried as its own block in total-investment.md, so NOT included in this baseline total"
storage,Pallet racking and shelving,"100-200 pallet positions selective/heavy-duty (beams sized 1000-1500 kg/pallet, records are dense) + archive and finished-goods shelving, installed","Jenbunjerd; LPI Rack Range (Thailand), Bangkok/Samut Prakan, racking and office mobile shelving; local fabricators (Sahawatthanakit, UPR, SD Shelf); SSI Schaefer (premium)",800000,1500000,published list prices + engineering estimate,SSI Schaefer premium tier ~1.5-3M for same scope; ~1000-2000 THB per pallet position at local tier
hvac,Whole-factory HVAC,"~1500 m2 at 20-26 C, 35-60% RH, ePM1/F7-F9 filtration sized for burning-season PM2.5, ducting and controls","Daikin Thailand; Trane; Mitsubishi Electric; Carrier; filtration: Camfil Thailand, AAF",7500000,15000000,engineering estimate at 5000-10000 THB/m2,"RH low end of 35% is aggressive for tropics and drives desiccant cost; if 45-60% RH acceptable, cost drops materially"
hvac,Clean-room-grade zone adder,"Cutting room + galvanics clean room, ~2 x 60 m2, ISO 7/8 with HEPA terminals, positive pressure, airlocks",Same HVAC vendors + clean-room contractors; Camfil HEPA,1200000,3400000,engineering estimate at 10000-28000 THB/m2 adder,Applied only to the two tight zones
solar,PV rooftop EPC (illustrative 300 kWp),"Turnkey C&I rooftop EPC incl. Deye hybrid inverters, at 25000-35000 THB/kWp",Solar Nicolo (Deye tier-1 distributor); Banpu NEXT; SCG Cleanergy; Sermsang; local Chiang Mai installers,7500000,10500000,market rate per kWp; size illustrative,"Final kWp open until site selection; PEA TOU 3.2.2 plus Ft (Sep-Dec 2026): self-consumed PV worth ~3.7 THB/kWh, ~4.5-7 yr payback (sustainability.md, grid tariff)"
solar,Battery stack 271 kWh (Gobel),"GP-SRA-HV314 HV LiFePO4 rack, 15 x 18 kWh packs, direct from Shenzhen, 50-60 day lead",Gobel Power (no Thai distributor; integration by solar EPC),1400000,2030000,vendor listed price USD 39900-58000 at ~35 THB/USD,Confirm Deye BMS protocol compatibility and that the EPC warrants a mixed-vendor DC bus; certs (UN38.3/IEC 62619/CE) to be requested
total,BASELINE TOTAL,Electric steam bank + oil-injected air + chiller bank + softener + loop treatment + local racking + HVAC + clean zones + 300 kWp solar + 271 kWh BESS,,30070000,51330000,sum of baseline rows,"Five-press fleet (October 2026; was 23.98M-41.63M THB for one Duplex); ~790k-1350k EUR at 38 THB/EUR; excludes options rows (biomass premium, oil-free, tower alternative, RO, ZLD evaporator, SSI premium tier); all figures budgetary +/- 30%, get RFQs before BOI/finance filings"
total,BASELINE TOTAL,Electric steam bank (2 modules) + oil-injected air + chiller bank (2 modules) + softener + loop treatment + local racking + HVAC + clean zones + 300 kWp solar + 271 kWh BESS,,28470000,48730000,sum of baseline rows,"Launch plant, one Duplex system and one Classic (October 2026; was 30.07M-51.33M THB for five presses, 23.98M-41.63M for one Duplex); ~750k-1280k EUR at 38 THB/EUR; excludes options rows and the galvanics water rows (ZLD, DI), which total-investment.md carries with galvanics; all figures budgetary +/- 30%, get RFQs before BOI"
1 category item spec_summary candidate_thai_suppliers cost_low_thb cost_high_thb cost_basis notes
2 steam Electric/gas once-through boiler bank 2 x 500 kg/h modules at 10.5 bar / 180 C, lead/lag, shared feed tank, feed pumps, economizer, installed Miura Thailand (Chachoengsao); Bangkok Industrial Boilers; STE Thailand 4500000 7000000 engineering estimate Five-press fleet 750-900 kg/h (steam-cooling.html); B-1 with the launch press, B-2 with Duplex 2; a third module for N+1 is an RFQ option; Miura-class modular once-through; service is Bangkok-centric, confirm northern dispatch SLA Launch plant (October 2026): one Duplex system and one Classic, 450-540 kg/h at Newbilt's 150-180 kg/h per press, so B-1 and B-2 both at launch; the boiler hall is built for four modules (scale.md utility phasing); a third module for N+1 is an RFQ option; Miura-class modular once-through; service is Bangkok-centric, confirm northern dispatch SLA
3 steam Biomass/wood-fired boiler package (option) ~1 t/h solid fuel (wood chips/pellets/rice husk) incl. fuel feed, grate, dust control, softener, installed Getabec PCL (Thai fabrication and service) 6000000 10000000 engineering estimate Sized for the five-press fleet (was ~0.5 t/h for one Duplex); sustainability path matching Deepgrooves NL precedent; higher capex, lower fuel opex in the North; NOT included in baseline total
4 steam Steam balance of plant Traps, accumulator, condensate return Forbes Marshall Thailand 0 0 included Largely included in boiler package rows; line kept for RFQ completeness
5 compressed_air Screw compressor skid (oil-injected) ~7.5 kW VSD screw + refrigerated dryer (3 C PDP) + coalescing filters + ~500 L receiver, installed Atlas Copco Thailand; Kaeser Thailand (SM-T/Aircenter); Ingersoll Rand Thailand 350000 600000 engineering estimate 14-30 m3/h demand is small (5-10 hp class); oil-injected + filter train meets 5 micron / 3 C spec
6 compressed_air True oil-free class-0 (option) Same duty in oil-free class-0 Atlas Copco (ZR/ZT); Kaeser 1200000 1800000 engineering estimate Only if air contacts product stream; NOT included in baseline total
7 cooling Process chiller bank 3 x 250 kW Process chiller bank 2 x 250 kW 3 x ~71 RT air-cooled screw/scroll chillers rated at 40 C ambient + primary pumps + plate HX + warm and cold tanks + VFD supply pumps + controls, installed 2 x ~71 RT air-cooled screw/scroll chillers rated at 40 C ambient (CH-1, CH-2) + primary pumps + plate HX + warm and cold tanks + VFD supply pumps + controls, backbone (HX frame, tanks, pumps, mains) sized for four modules, installed Trane Thailand; Carrier Thailand; Daikin Applied Thailand; Hitachi Thailand 6500000 4900000 10500000 7900000 engineering estimate Five-press fleet up to ~650 kW and 305-540 l/min (Newbilt site requirements, 20-25 C supply); one module per press stage; 3 x 350 kW for N+1 as the alternative (steam-cooling.html) Launch plant (October 2026): Duplex system ~261 kW hot-afternoon peak (scale.md) plus the Classic up to ~125 kW (Newbilt per press), ~390 kW against 500 kW installed; was 3 x 250 kW at 6.5-10.5M for five presses, less one module at ~1.6-2.6M THB (estimate); CH-3 and CH-4 come with the growth options; 3 x 350 kW frame pads stay the alternative (steam-cooling.html)
8 cooling Cooling tower + HX loop (alternative) Dry cooler or FRP tower ~650-750 kW reject + plate HX + pumps + tanks + water treatment Liang Chi Thailand (tower, large service org); Process Cooling Solutions; Tasaki (integrators) 2000000 3500000 engineering estimate Cheaper capex but wet-bulb-limited; hybrid tower + trim chiller is the efficiency-optimal design; NOT included in baseline total
9 water Boiler feedwater duplex softener ~1.0-1.2 m3/h feedwater duty (five-press boiler bank) Veolia Water Technologies Thailand; Hydrotek; local RO/softener integrators 120000 300000 market estimate May suffice alone for a small fire-tube boiler
10 water RO skid (option) 0.5-1 m3/h low-TDS feed Veolia; Hydrotek; local integrators 200000 500000 market estimate Only if low-TDS feed needed; NOT included in baseline total Launch scope since October 2026 as the DI water supply for the galvanics PMPB (with polishing); carried in the galvanics water block of total-investment.md, so NOT included in this baseline total
11 water Closed-loop cooling water treatment Side-stream filtration + dosing + conductivity blowdown control Veolia; Hydrotek; local integrators 200000 500000 engineering estimate Sized for the five-press loop with its open return tank (Newbilt press outlets are open, max. 2 bar); chemicals are ongoing opex on top
12 water Galvanics ZLD evaporator (future) Galvanics ZLD evaporator Small MVR or low-temp vacuum evaporator for plating rinse, installed Core unit imported (WTEYA, Greenlan, Fred); Thai integration via Veolia or Hydrotek 3000000 8000000 market estimate For the future galvanics line, zero-discharge requirement; NOT included in baseline total Launch scope since October 2026 (galvanics in-house from the start); carried as its own block in total-investment.md, so NOT included in this baseline total
13 storage Pallet racking and shelving 100-200 pallet positions selective/heavy-duty (beams sized 1000-1500 kg/pallet, records are dense) + archive and finished-goods shelving, installed Jenbunjerd; LPI Rack Range (Thailand), Bangkok/Samut Prakan, racking and office mobile shelving; local fabricators (Sahawatthanakit, UPR, SD Shelf); SSI Schaefer (premium) 800000 1500000 published list prices + engineering estimate SSI Schaefer premium tier ~1.5-3M for same scope; ~1000-2000 THB per pallet position at local tier
14 hvac Whole-factory HVAC ~1500 m2 at 20-26 C, 35-60% RH, ePM1/F7-F9 filtration sized for burning-season PM2.5, ducting and controls Daikin Thailand; Trane; Mitsubishi Electric; Carrier; filtration: Camfil Thailand, AAF 7500000 15000000 engineering estimate at 5000-10000 THB/m2 RH low end of 35% is aggressive for tropics and drives desiccant cost; if 45-60% RH acceptable, cost drops materially
15 hvac Clean-room-grade zone adder Cutting room + galvanics clean room, ~2 x 60 m2, ISO 7/8 with HEPA terminals, positive pressure, airlocks Same HVAC vendors + clean-room contractors; Camfil HEPA 1200000 3400000 engineering estimate at 10000-28000 THB/m2 adder Applied only to the two tight zones
16 solar PV rooftop EPC (illustrative 300 kWp) Turnkey C&I rooftop EPC incl. Deye hybrid inverters, at 25000-35000 THB/kWp Solar Nicolo (Deye tier-1 distributor); Banpu NEXT; SCG Cleanergy; Sermsang; local Chiang Mai installers 7500000 10500000 market rate per kWp; size illustrative Final kWp open until site selection; PEA TOU 3.2.2 plus Ft (Sep-Dec 2026): self-consumed PV worth ~3.7 THB/kWh, ~4.5-7 yr payback (sustainability.md, grid tariff)
17 solar Battery stack 271 kWh (Gobel) GP-SRA-HV314 HV LiFePO4 rack, 15 x 18 kWh packs, direct from Shenzhen, 50-60 day lead Gobel Power (no Thai distributor; integration by solar EPC) 1400000 2030000 vendor listed price USD 39900-58000 at ~35 THB/USD Confirm Deye BMS protocol compatibility and that the EPC warrants a mixed-vendor DC bus; certs (UN38.3/IEC 62619/CE) to be requested
18 total BASELINE TOTAL Electric steam bank + oil-injected air + chiller bank + softener + loop treatment + local racking + HVAC + clean zones + 300 kWp solar + 271 kWh BESS Electric steam bank (2 modules) + oil-injected air + chiller bank (2 modules) + softener + loop treatment + local racking + HVAC + clean zones + 300 kWp solar + 271 kWh BESS 30070000 28470000 51330000 48730000 sum of baseline rows Five-press fleet (October 2026; was 23.98M-41.63M THB for one Duplex); ~790k-1350k EUR at 38 THB/EUR; excludes options rows (biomass premium, oil-free, tower alternative, RO, ZLD evaporator, SSI premium tier); all figures budgetary +/- 30%, get RFQs before BOI/finance filings Launch plant, one Duplex system and one Classic (October 2026; was 30.07M-51.33M THB for five presses, 23.98M-41.63M for one Duplex); ~750k-1280k EUR at 38 THB/EUR; excludes options rows and the galvanics water rows (ZLD, DI), which total-investment.md carries with galvanics; all figures budgetary +/- 30%, get RFQs before BOI