grabowski 553b4a93d1 Launch plant roll-up and the investor's 180M THB question
Decided (user, October 2026): the plant launches with everything in one
capital round, commissioned in sequence: one Newbilt Duplex system, one
Classic, a Pheenix galvanics line with ZLD water, the Sibert line, a
Sillitoe cutting room, and the modular steam and cooling plant (2 x 500
kg/h boilers, 2 x 250 kW chillers, rooms for four each). No bridge
stampers, no outsourced cutting; cassette and CD-R stay; the second
Duplex and further Classics are growth options, not in the investment.

total-investment.md: new 'Launch plant' roll-up, 4.9M to 8.9M USD,
161M to 292M THB incl. 15 % contingency (midpoint ~227M), with what is
left out (ramp-up reserve ~10-20M THB, CD replication, financing, FX,
archive shelving) and the BOI assumption. The investor's question (180M
THB, maybe +20 % = 216M): fits at the low end only; at the midpoint four
levers that keep every machine (solar via PPA, metrology launch tier,
galvanics near OMS's reference, visitor corridor later) give ~193M, plus
reserve ~203-213M, inside 216M; 180M needs low quotes. The quotes that
decide it: Newbilt (Duplex, Classic), Pheenix galvanics, building with
soil test, metrology. Old full vision and phased entry marked superseded
until the mirrors are re-based.

Utilities CSV: chiller bank two modules (4.9-7.9M THB), boiler note for
B-1 and B-2 at launch, ZLD and DI rows now launch scope (carried with
galvanics); baseline 28.47M-48.73M THB. README project status.
2026-10-16 14:53:19 +07:00

6.8 KiB

1categoryitemspec_summarycandidate_thai_supplierscost_low_thbcost_high_thbcost_basisnotes
2steamElectric/gas once-through boiler bank2 x 500 kg/h modules at 10.5 bar / 180 C, lead/lag, shared feed tank, feed pumps, economizer, installedMiura Thailand (Chachoengsao); Bangkok Industrial Boilers; STE Thailand45000007000000engineering estimateLaunch plant (October 2026): one Duplex system and one Classic, 450-540 kg/h at Newbilt's 150-180 kg/h per press, so B-1 and B-2 both at launch; the boiler hall is built for four modules (scale.md utility phasing); a third module for N+1 is an RFQ option; Miura-class modular once-through; service is Bangkok-centric, confirm northern dispatch SLA
3steamBiomass/wood-fired boiler package (option)~1 t/h solid fuel (wood chips/pellets/rice husk) incl. fuel feed, grate, dust control, softener, installedGetabec PCL (Thai fabrication and service)600000010000000engineering estimateSized for the five-press fleet (was ~0.5 t/h for one Duplex); sustainability path matching Deepgrooves NL precedent; higher capex, lower fuel opex in the North; NOT included in baseline total
4steamSteam balance of plantTraps, accumulator, condensate returnForbes Marshall Thailand00includedLargely included in boiler package rows; line kept for RFQ completeness
5compressed_airScrew compressor skid (oil-injected)~7.5 kW VSD screw + refrigerated dryer (3 C PDP) + coalescing filters + ~500 L receiver, installedAtlas Copco Thailand; Kaeser Thailand (SM-T/Aircenter); Ingersoll Rand Thailand350000600000engineering estimate14-30 m3/h demand is small (5-10 hp class); oil-injected + filter train meets 5 micron / 3 C spec
6compressed_airTrue oil-free class-0 (option)Same duty in oil-free class-0Atlas Copco (ZR/ZT); Kaeser12000001800000engineering estimateOnly if air contacts product stream; NOT included in baseline total
7coolingProcess chiller bank 2 x 250 kW2 x ~71 RT air-cooled screw/scroll chillers rated at 40 C ambient (CH-1, CH-2) + primary pumps + plate HX + warm and cold tanks + VFD supply pumps + controls, backbone (HX frame, tanks, pumps, mains) sized for four modules, installedTrane Thailand; Carrier Thailand; Daikin Applied Thailand; Hitachi Thailand49000007900000engineering estimateLaunch plant (October 2026): Duplex system ~261 kW hot-afternoon peak (scale.md) plus the Classic up to ~125 kW (Newbilt per press), ~390 kW against 500 kW installed; was 3 x 250 kW at 6.5-10.5M for five presses, less one module at ~1.6-2.6M THB (estimate); CH-3 and CH-4 come with the growth options; 3 x 350 kW frame pads stay the alternative (steam-cooling.html)
8coolingCooling tower + HX loop (alternative)Dry cooler or FRP tower ~650-750 kW reject + plate HX + pumps + tanks + water treatmentLiang Chi Thailand (tower, large service org); Process Cooling Solutions; Tasaki (integrators)20000003500000engineering estimateCheaper capex but wet-bulb-limited; hybrid tower + trim chiller is the efficiency-optimal design; NOT included in baseline total
9waterBoiler feedwater duplex softener~1.0-1.2 m3/h feedwater duty (five-press boiler bank)Veolia Water Technologies Thailand; Hydrotek; local RO/softener integrators120000300000market estimateMay suffice alone for a small fire-tube boiler
10waterRO skid (option)0.5-1 m3/h low-TDS feedVeolia; Hydrotek; local integrators200000500000market estimateLaunch scope since October 2026 as the DI water supply for the galvanics PMPB (with polishing); carried in the galvanics water block of total-investment.md, so NOT included in this baseline total
11waterClosed-loop cooling water treatmentSide-stream filtration + dosing + conductivity blowdown controlVeolia; Hydrotek; local integrators200000500000engineering estimateSized for the five-press loop with its open return tank (Newbilt press outlets are open, max. 2 bar); chemicals are ongoing opex on top
12waterGalvanics ZLD evaporatorSmall MVR or low-temp vacuum evaporator for plating rinse, installedCore unit imported (WTEYA, Greenlan, Fred); Thai integration via Veolia or Hydrotek30000008000000market estimateLaunch scope since October 2026 (galvanics in-house from the start); carried as its own block in total-investment.md, so NOT included in this baseline total
13storagePallet racking and shelving100-200 pallet positions selective/heavy-duty (beams sized 1000-1500 kg/pallet, records are dense) + archive and finished-goods shelving, installedJenbunjerd; LPI Rack Range (Thailand), Bangkok/Samut Prakan, racking and office mobile shelving; local fabricators (Sahawatthanakit, UPR, SD Shelf); SSI Schaefer (premium)8000001500000published list prices + engineering estimateSSI Schaefer premium tier ~1.5-3M for same scope; ~1000-2000 THB per pallet position at local tier
14hvacWhole-factory HVAC~1500 m2 at 20-26 C, 35-60% RH, ePM1/F7-F9 filtration sized for burning-season PM2.5, ducting and controlsDaikin Thailand; Trane; Mitsubishi Electric; Carrier; filtration: Camfil Thailand, AAF750000015000000engineering estimate at 5000-10000 THB/m2RH low end of 35% is aggressive for tropics and drives desiccant cost; if 45-60% RH acceptable, cost drops materially
15hvacClean-room-grade zone adderCutting room + galvanics clean room, ~2 x 60 m2, ISO 7/8 with HEPA terminals, positive pressure, airlocksSame HVAC vendors + clean-room contractors; Camfil HEPA12000003400000engineering estimate at 10000-28000 THB/m2 adderApplied only to the two tight zones
16solarPV rooftop EPC (illustrative 300 kWp)Turnkey C&I rooftop EPC incl. Deye hybrid inverters, at 25000-35000 THB/kWpSolar Nicolo (Deye tier-1 distributor); Banpu NEXT; SCG Cleanergy; Sermsang; local Chiang Mai installers750000010500000market rate per kWp; size illustrativeFinal kWp open until site selection; PEA TOU 3.2.2 plus Ft (Sep-Dec 2026): self-consumed PV worth ~3.7 THB/kWh, ~4.5-7 yr payback (sustainability.md, grid tariff)
17solarBattery stack 271 kWh (Gobel)GP-SRA-HV314 HV LiFePO4 rack, 15 x 18 kWh packs, direct from Shenzhen, 50-60 day leadGobel Power (no Thai distributor; integration by solar EPC)14000002030000vendor listed price USD 39900-58000 at ~35 THB/USDConfirm Deye BMS protocol compatibility and that the EPC warrants a mixed-vendor DC bus; certs (UN38.3/IEC 62619/CE) to be requested
18totalBASELINE TOTALElectric steam bank (2 modules) + oil-injected air + chiller bank (2 modules) + softener + loop treatment + local racking + HVAC + clean zones + 300 kWp solar + 271 kWh BESS2847000048730000sum of baseline rowsLaunch plant, one Duplex system and one Classic (October 2026; was 30.07M-51.33M THB for five presses, 23.98M-41.63M for one Duplex); ~750k-1280k EUR at 38 THB/EUR; excludes options rows and the galvanics water rows (ZLD, DI), which total-investment.md carries with galvanics; all figures budgetary +/- 30%, get RFQs before BOI