Decided (user, October 2026): the plant launches with everything in one capital round, commissioned in sequence: one Newbilt Duplex system, one Classic, a Pheenix galvanics line with ZLD water, the Sibert line, a Sillitoe cutting room, and the modular steam and cooling plant (2 x 500 kg/h boilers, 2 x 250 kW chillers, rooms for four each). No bridge stampers, no outsourced cutting; cassette and CD-R stay; the second Duplex and further Classics are growth options, not in the investment. total-investment.md: new 'Launch plant' roll-up, 4.9M to 8.9M USD, 161M to 292M THB incl. 15 % contingency (midpoint ~227M), with what is left out (ramp-up reserve ~10-20M THB, CD replication, financing, FX, archive shelving) and the BOI assumption. The investor's question (180M THB, maybe +20 % = 216M): fits at the low end only; at the midpoint four levers that keep every machine (solar via PPA, metrology launch tier, galvanics near OMS's reference, visitor corridor later) give ~193M, plus reserve ~203-213M, inside 216M; 180M needs low quotes. The quotes that decide it: Newbilt (Duplex, Classic), Pheenix galvanics, building with soil test, metrology. Old full vision and phased entry marked superseded until the mirrors are re-based. Utilities CSV: chiller bank two modules (4.9-7.9M THB), boiler note for B-1 and B-2 at launch, ZLD and DI rows now launch scope (carried with galvanics); baseline 28.47M-48.73M THB. README project status.
18 KiB
Total Investment: Rough Picture
Everything priced or estimated so far, rolled into one view. Blocks marked "estimate" have no vendor confirmation; the rest trace to quotes or the researched ranges in this repo. Treat all figures as budgetary with a wide margin (plus or minus 30 to 50% on the estimates) until RFQs replace them.
Currency: USD and THB. FX at 5 August 2026: 1 USD = 33 THB. Vendor quotes issued in another currency are kept in that currency wherever they appear next to their source document, and converted here at 1 EUR = 1.155 USD and 1 GBP = 1.35 USD. Original figures compiled July 2026; the underlying THB estimates are unchanged, because EUR/THB at ~38 is where it was when they were made.
Launch plant (October 2026)
Decided (user, October 2026): the plant launches with everything in one capital round, commissioned in sequence, with no bridge stampers and no outsourced cutting:
- one Newbilt Duplex system: two HRP 12 semi-automatic presses, an EX 50 main and an EX 35 colour extruder (pressing line);
- one Newbilt Classic fully automatic press;
- one Pheenix Alpha galvanics line (PASU, PPPU, one PDPU, PMPB) with zero-discharge water treatment (galvanics and stamper prep);
- the Sibert stamper-prep line (VSF, VSP, VSC);
- a Sillitoe SDMS cutting room (vendor landscape);
- the modular steam and cooling plant: two 500 kg/h boiler modules and two 250 kW chiller modules, in a boiler hall and a chiller compound built for four each (scale).
Cassette and CD-R duplication stay in. The second Duplex system and the further Classics are growth options with room reserved, not in this investment. Three presses make roughly 0.7 to 0.95 million records a year on two shifts (estimate: the scale basis gives ~0.71 to 0.97 million, the planning rates of the fleet calculator ~0.94 million).
| Block | USD | THB | Basis |
|---|---|---|---|
| Phase 0: BOI consultant, legal and lease work, soil test, re-quotes | 40k – 80k | 1.3M – 2.6M | estimate |
| Newbilt Duplex system (two HRP 12, EX 50 + EX 35, trimmer, label oven, shrink wrapper, grinder, label punch) | 350k – 370k | 11.6M – 12.2M | 2024 quote EUR 200,500 for the Single 2.1 plus the quoted second press and extruder ~USD 115k; expired, re-quote |
| Newbilt Classic | 290k – 460k | 9.6M – 15.2M | placeholder (the old AD12 band per press); no Newbilt price on file |
| Pheenix galvanics line (PASU, PPPU, PDPU, PMPB) | 320k – 650k | 10.6M – 21.4M | estimate; no Pheenix price on file; OMS's reference prices for a 4-cell wet room (EUR 224k to 311k, ~USD 259k to 359k) sit at the low end |
| Galvanics water: ZLD evaporator and DI water | 97k – 258k | 3.2M – 8.5M | utilities CSV rows, now launch scope |
| Water-treatment building next to galvanics (~12 × 10 m, proposed) | 52k – 87k | 1.7M – 2.9M | estimate at the building rate below |
| Sibert VSF, VSP, VSC | 250k | 8.3M | Sibert's budget confirmation, 5 October 2026; its time, spares, shipping and travel in the freight and working-capital lines |
| Cutting room: Sillitoe SDMS, spare cutterhead and support, mastering console and chain, monitoring, room build-out | 200k – 350k | 6.6M – 11.6M | SDMS list price USD 125k (ex tax and shipping); the rest estimate |
| Metrology and QC stack (XRF, laser confocal, wide-area profiler, inline vision on three presses, audio station) | 350k – 810k | 11.6M – 26.7M | estimate, phaseable (quality automation) |
| PVC lab, day-one tier | 55k – 150k | 1.8M – 5.0M | estimate, quality automation |
| Utilities, solar, battery, HVAC, clean zones, racking | 863k – 1,477k | 28.5M – 48.7M | utilities CSV baseline re-sized for three presses: chiller bank two modules instead of three |
| Building ~1,500 m² plus civil and site works | 650k – 1,100k | 21.4M – 36.3M | estimate at 12,000 – 20,000 THB/m² plus ~20 % site works; soil is the main variable |
| Overhead crane, runway, frame premium, machine door | 97k – 227k | 3.2M – 7.5M | estimate, crane, workshop and tours |
| Maintenance workshop and machine bay fit-out | 30k – 76k | 1.0M – 2.5M | estimate, same |
| Visitor corridor and accessible entrance | 67k – 148k | 2.2M – 4.9M | estimate, same |
| Utility yard built for four boiler and four chiller modules | 73k – 122k | 2.4M – 4.0M | estimate, scale |
| Factory software, ERPNext, artist platform public side | 115k – 310k | 3.8M – 10.2M | estimate: factory software 60k – 170k, ERPNext implementation 15k – 50k (digital factory), artist platform 40k – 90k (artist platform) |
| Cassette duplication and CD-R duplication | 55k – 190k | 1.8M – 6.3M | estimate, business plan sections 4.8 and 4.9 |
| Freight, installation, commissioning, training (Pheenix, Sibert, Sillitoe, Newbilt beyond its quoted 5 days) | 150k – 300k | 5.0M – 9.9M | estimate |
| Working capital, PVC stock, spares, lease deposit, first-year rent | 135k – 290k | 4.5M – 9.6M | estimate; land is leased, so no land purchase |
| Subtotal | ~4.24M – 7.71M | ~140M – 254M | |
| Contingency 15 % | ~0.64M – 1.16M | ~21M – 38M | |
| Total, launch plant | ~4.9M – 8.9M USD | ~161M – 292M THB | midpoint ~6.9M USD, ~227M THB |
Not in the total: a reserve for the ramp-up (staff hired before first revenue, overheads until volume covers them; ~10M to 20M THB, estimate), CD replication, financing costs, currency moves, and the archive's mobile shelving (to quote). The blocks are vendor prices without Thai duty or import VAT, so they assume BOI promotion: without it, ~5 % duty on ~2.3M USD of imported machinery (~0.11M USD) comes on top, plus ~0.17M USD of import VAT paid at the border and reclaimed later (estimates).
The investor's question: 180M THB, maybe 20 % more (October 2026)
The project's investor asked whether the plant can be built for 180M THB (~5.45M USD), possibly up to 20 % more (216M THB, ~6.55M USD).
| Case | Launch plant | Against 180M | Against 216M |
|---|---|---|---|
| Low end of every block | ~161M THB | fits, ~19M to spare | fits |
| Midpoint | ~227M THB | ~47M over | ~11M over |
| High end of every block | ~292M THB | ~112M over | ~76M over |
Read honestly: 216M THB is a realistic target for the full equipment list; 180M THB holds only if the open quotes land low. At the midpoint four levers bring the plant inside 216M without dropping any of the machines decided above (midpoint values with their share of the contingency, estimates):
| Lever | Saves | Launch plant after it |
|---|---|---|
| Rooftop solar and battery through a solar PPA (the EPC owns and finances the array, the plant buys the power) instead of buying them | ~12.3M THB | ~214M THB |
| Metrology launch tier (XRF, inline vision, audio station), the laser confocal and the wide-area profiler bought from revenue | ~10.1M THB | ~204M THB |
| Pheenix galvanics priced near OMS's reference for a 4-cell wet room | ~6.7M THB | ~198M THB |
| Visitor corridor built later; the plant runs without public tours at first | ~4.1M THB | ~193M THB |
Add the ramp-up reserve of ~10M to 20M THB and that is ~203M to 213M THB, inside the 216M. Reaching 180M at the midpoint needs scope cuts on top: cassette and CD-R later (~4.6M THB) and renting a crane for the installations while the frame stays crane-ready (~3.7M THB) give ~185M before the reserve, still above 180M, so 180M is a low-quote outcome, not a plan.
What decides it: the two largest machine lines have no price at all (the Classic and the Pheenix galvanics line), and the building depends on the soil. Four requests settle most of the band: the Newbilt re-quote for the Duplex and the Classic, a Pheenix quote for the galvanics line, the building RFQ with a soil test, and distributor quotes for the metrology stack. Until they are in, quote ~216M THB to the investor as the target with the levers above, and 180M as the low-quote case.
Full vision, all blocks (July 2026, superseded)
The five-press full vision below is superseded by the launch plant above. It stays until the documents that quote its 4.7M to 8.9M USD total (README, roadmap, revenue model, business plan) are re-based on the launch plant.
| Block | USD | THB | Basis |
|---|---|---|---|
| Newbilt semi-auto line, full Duplex | 350k – 370k | 11.5M – 12.2M | 2024 quote EUR 200,500 (~USD 232k) + quoted 2nd press/extruder ~USD 115k; expired, needs re-quote. The fleet has since changed, see the added-scope table |
| 2 automated presses (Pheenix AD12) | 580k – 920k | 19.1M – 30.5M | unverified ~USD 340k/press indicative + delivery and commissioning. Replaced by the Newbilt Classic in the current fleet, see the added-scope table |
| Galvanics line (Digital Matrix or Pheenix Alpha) | 320k – 650k | 10.7M – 21.4M | six-figure-USD turnkey inference from vendor research; the Pheenix range (2024 flyers, galvanics and stamper prep) is unpriced too; OMS's reference prices (letter, 9 October 2026) put a complete 4-cell wet room at EUR 224k basic to 311k advanced (~USD 259k to 359k; ~270k to 371k with know-how transfer), installation and water treatment extra: at or below this block's low end, kept until quotes exist |
| Zero-discharge water treatment (ZLD) | 90k – 240k | 3.0M – 8.0M | utilities CSV option row |
| Stamper prep (Sibert VSP, VSF, VSC) | 60k – 170k | 1.9M – 5.7M | estimate kept until the re-base; Sibert has since confirmed USD 250k for the three (its time, spares, shipping and travel extra), the difference is in the table below |
| Mastering and cutting room (Agnew or Sillitoe lathe system, cutter amps, console, room treatment) | 290k – 580k | 9.6M – 19.1M | estimate, bespoke market; the Sillitoe SDMS lists at USD 125k for lathe, head, amplifier and automation (ex tax, shipping), which makes the low end reachable; band kept until both quotes exist |
| Metrology and QC stack (confocal, profiler, XRF, inline vision, audio station) | 350k – 810k | 11.5M – 26.7M | estimate, phaseable |
| Utilities, solar, HVAC, racking baseline | 730k – 1,270k | 24.0M – 41.6M | reviewed utilities CSV, THB-native; sized for one Duplex, the five-press re-size is in the table below |
| Building ~1,500 m² plus civil works | 650k – 1,100k | 21.4M – 36.2M | estimate at 12,000–20,000 THB/m² Thai industrial construction plus ~20% site works |
| Land 6–8 rai, if purchased | 360k – 970k | 12.0M – 32.0M | estimate at 2–4M THB/rai industrial; leasing cuts this to near zero upfront |
| Traceability and factory software | 60k – 170k | 1.9M – 5.7M | estimate |
| Freight, installation, training (non-Newbilt equipment) | 120k – 230k | 3.8M – 7.6M | estimate |
| Working capital, PVC stock, spares | 120k – 230k | 3.8M – 7.6M | estimate |
| Subtotal | ~4.1M – 7.7M | ~135M – 254M | |
| Contingency 15% | ~0.6M – 1.2M | ~20M – 38M | |
| Total, full vision | ~4.7M – 8.9M USD | ~155M – 294M THB |
Added scope, not yet in the roll-up
Decided, or re-priced by a vendor, after the roll-up above was compiled; carried here until the next re-base folds them into the blocks (the building, software and stamper prep lines, and the contingency on top).
| Block | USD | THB | Basis |
|---|---|---|---|
| Overhead crane, runway, frame premium, machine door | 97k – 227k | 3.2M – 7.5M | estimate, crane, workshop and tours |
| Maintenance workshop and machine bay fit-out | 30k – 76k | 1.0M – 2.5M | estimate, same |
| Visitor corridor and accessible entrance | 67k – 148k | 2.2M – 4.9M | estimate, same |
| Artist platform, public side (calculator, campaigns, payments) | 40k – 90k | 1.3M – 3.0M | estimate, artist platform |
| PVC material lab, day-one tier (incl. plaque press and sample conditioning) | 55k – 150k | 1.8M – 5.0M | estimate, quality automation; not costed in the metrology block above. The mature tier (torque rheometer, DSC, FTIR, ~120k – 240k) is deferred, with partner labs in between |
| Stamper prep re-priced: USD 250k for VSP, VSF and VSC against the 60k – 170k block above | +190k (low case) / +80k (high case) | +6.3M / +2.6M | Sibert's budget confirmation, email of 5 October 2026 (galvanics and stamper prep); itemised quotation to follow. Its time, spare parts, shipping and travel are extra and fall into the freight/installation and spares blocks above |
| Press fleet changed (October 2026) to two Newbilt Duplex systems (two presses each, EX 50 main extruder and EX 35 colour extruder) plus one Newbilt Classic, replacing the two blocks above (930k – 1,290k): Duplex system 1 as the first block (350k – 370k; the quote's second-extruder option becomes the EX 35), system 2 ~230k – 300k (two presses at the quoted ~115k per press and extruder set as the yardstick, plus hydraulic unit and EX 35, estimate; no EX 35 price on file), the Classic ~290k – 460k (the AD12 band per press as a placeholder; no Newbilt price on file) | −60k (low case) / −160k (high case) | −2.0M / −5.3M | estimate, pressing line; the Newbilt re-quote replaces it. The utilities for five presses are re-sized in the row below |
| Utilities re-sized for the five-press fleet (October 2026): boiler bank 2 × 500 kg/h, chiller bank 3 × 250 kW with plate heat exchanger and tanks, larger softener and loop treatment (steam and cooling) | +185k (low case) / +294k (high case) | +6.1M / +9.7M | estimate, utilities CSV re-based from 24.0M – 41.6M to 30.1M – 51.3M THB |
| Utility yard built for four boiler and four chiller modules (October 2026): yard ~379 m² against 178 m² (scale) | 73k – 122k | 2.4M – 4.0M | estimate: the building rate above on the ~200 m² the yard grows by; the open chiller compound costs less than a building, so this is the cautious end. The valved branches and feeders for the empty positions are not priced yet |
ERPNext for the whole plant (October 2026): configuration with Thai tax, integration with every tool, Nix packaging; vinyl-erp server |
to quote | to quote | not in the sum: 3.5 to 6 person-months in-house or a partner quote (Ecosoft), plus 2k to 4k USD hardware (digital factory); no licence fee |
| Archive mobile shelving for the father and mother archive (October 2026) | to quote | to quote | not in the sum: A-Z Solutions publishes no prices; quote it and a Thai supplier (facility security) |
| Added so far | ~678k – 1,027k | ~22.3M – 33.9M | about 13 to 17% on the full-vision subtotal |
Phased entry (superseded October 2026)
Superseded by the launch plant above, which launches with galvanics, the cutting room and three presses. The earlier phased entry, kept for reference: a launch phase of roughly 1.7M to 2.9M USD (~57M to 95M THB):
- Newbilt Single system (not Duplex yet)
- Bridge stampers from Stamper Discs, so no galvanics line at launch
- Basic QC (microscope, benchtop PVC lab, sampled listening), full metrology deferred; the PVC lab's day-one tier is the added-scope row above
- Leased building instead of purchase, modest first solar array
- Galvanics, the second Duplex system and the Classic, full metrology, and the biomass boiler follow as revenue-funded or second-round expansions
The planning already supports this: the Duplex-ready hydraulics, the bridge-supplier role for Stamper Discs, the staged electric-to-biomass steam path, and the phaseable metrology stack are all documented for exactly this reason.
What moves the number
- BOI: machinery duty exemption applies across most of the equipment blocks, and the solar and automation spend converts into CIT-exemption headroom; the application precedes every purchase order (see boi.md). The blocks are vendor prices without Thai duty or import VAT, so the headline assumes promotion: without it, ~0.14M USD of duty and ~0.2M USD of import VAT (reclaimable later) come on top at the start fleet (estimate)
- Buy vs lease on land and building swings roughly 1.0M to 2.1M USD (~34M to 69M THB) of upfront capital, and also moves the launch date by about three quarters; see project-timeline.md
- Biggest uncertainty bands: metrology (partly a choice of ambition), the mastering/cutting room (bespoke vendor, no public pricing), the Newbilt Classic (no price on file), and land
- Currency exposure is real and is not modelled here. Revenue is mostly USD/EUR from export customers, the cost base is mostly THB, and the largest single equipment block is EUR-denominated and unhedged against an order that will not be placed for roughly a year (see project-timeline.md). A 10% move in EUR/THB between now and the Newbilt order is worth ~USD 25–35k on that line alone. Ask for the re-quote to state its currency and validity period.
- Every band narrows only with RFQs; the supplier map in equipment-suppliers.md lists who to ask