The current plan (user decision, October 2026) replaces the 50/50 target (two semi-automatic presses and two Pheenix AD12s) with an all-Newbilt fleet of five presses: two Duplex systems in Newbilt's two-extruder configuration (two HRP 12 presses, an extruder each, one hydraulic unit) and one Classic fully automatic press. - pressing-line.md: new "Current plan" section (fleet table, what it means, phasing from the Single 2.1 as the first half of system 1, re-quote questions); site requirements per Duplex system. - scale.md: capacity table and basis (368 to 448 records/h, ~1.06 to 1.5M a year on two shifts, same range as before); pressing electrical row; steam and cooling flagged, not re-based: five presses draw ~750 to 900 kg/h of steam and up to ~625 kW of cooling at Newbilt's per-press figures, against the 400 kg/h / 250 kW sized for one Duplex. - total-investment.md: fleet change as an added-scope row (system 2 ~230k-300k and the Classic ~290k-460k, estimates; -60k / -160k against the two blocks it replaces); headline unchanged until the re-base. - roadmap items 4, 5 and 24, revenue model mature row, crane doc (the Classic's weight now decides 5 t or 3.2 t), vendor landscape (AD12 is the comparison for the Classic), README. The business plan docx is not regenerated.
253 lines
13 KiB
Markdown
253 lines
13 KiB
Markdown
# Project Scale: Rough Numbers
|
||
|
||
One-page sizing of the whole project. Everything here is a planning
|
||
estimate derived from the session's vendor data and standard ratios;
|
||
figures marked "estimate" have no vendor confirmation yet. Update this
|
||
page as real quotes and the site decision land.
|
||
|
||
## Production capacity
|
||
|
||
| Phase | Fleet | Rough output |
|
||
|---|---|---|
|
||
| Launch | 1 semi-auto press (Newbilt Single, the first half of Duplex system 1), 1 shift | ~90,000 to 135,000 records/yr |
|
||
| Duplex | 2 semi-auto presses (Duplex system 1, an extruder per press), 1 to 2 shifts | ~175,000 to 540,000 records/yr |
|
||
| Mature | 4 semi-auto (two Duplex systems, an extruder per press) + 1 automated (Newbilt Classic), 2 shifts | ~1.0 to 1.5 million records/yr |
|
||
|
||
Basis: the current fleet plan of October 2026
|
||
([pressing line](equipment/pressing-line.md)). The automated Classic
|
||
~128 records/hour (28 s cycle, vendor flyer); semi-automatic throughput is
|
||
unpublished, assumed 60 to 80 records/hour per press with operator
|
||
handling (estimate); 16 h/day, 300 days/yr, with realistic overall
|
||
effectiveness of 60 to 70% applied: 368 to 448 records/hour, ~1.06 to 1.5
|
||
million a year. The theoretical ceiling of the mature fleet at 100% uptime
|
||
is roughly 1.8 to 2.2 million records per year. (The earlier 50/50 fleet,
|
||
two semi-automatic presses and two Pheenix AD12s, landed in the same
|
||
range.)
|
||
|
||
**The 60–70% effectiveness assumption is worth challenging, but not yet
|
||
changing.** Newbilt publishes ≥95% yield and ≥95% uptime for the Classic
|
||
12" automatic at a 28 s cycle (~128 records/h), and quotes ~30 s average
|
||
for the Duplex. Three reasons not to adjust anything on that basis:
|
||
|
||
- **Machine uptime is not plant OEE.** A vendor uptime figure excludes
|
||
stamper and mould changes, label reels, colour changeovers, PVC lot
|
||
changes, first-article QC and breaks — precisely the losses that
|
||
dominate a short-run boutique plant. They are different quantities.
|
||
- It would apply only to the **automated press** (the Classic). The
|
||
60–80/h semi-auto figure already embeds operator handling, so applying
|
||
an uplift to that half would double-count.
|
||
- 0.95 × 0.95 is 0.90 before any performance factor; reaching 80% OEE
|
||
needs a performance factor near 0.89, which nobody has estimated.
|
||
|
||
Ask both press vendors for the **basis** of their uptime and yield
|
||
figures — measured over what period, at what run length, counting which
|
||
stoppages — as part of the re-quote. It is a free question. If the
|
||
figures survive scrutiny they would argue for a higher OEE on the
|
||
automated fleet only, and the same logic would apply to any competitor
|
||
running the same machine.
|
||
|
||
## Building
|
||
|
||
| Zone | Rough area |
|
||
|---|---|
|
||
| Semi-auto press hall (Newbilt Duplex spec) | ~200 m² |
|
||
| Automated press zone | ~100 to 150 m² |
|
||
| Galvanics clean room + water treatment + chemical storage | ~80 to 150 m² |
|
||
| Mastering and cutting room | ~40 to 60 m² |
|
||
| Stamper prep | ~30 m² |
|
||
| Packaging + finished goods warehouse | ~300 to 500 m² |
|
||
| Utility rooms (boiler, compressor, chiller, electrical) | ~100 to 150 m² |
|
||
| Offices, QC/listening, archive, IT, entrance | ~150 to 200 m² |
|
||
| Maintenance workshop and machine bay (crane-served) | ~100 to 150 m² |
|
||
| Visitor corridor (glazed, ground level) | ~110 to 130 m² |
|
||
| Circulation, walls, misc | ~150 to 250 m² |
|
||
| **Total under roof** | **~1,400 to 2,000 m²** |
|
||
|
||
The HVAC budget in the utilities CSV already assumes ~1,500 m² conditioned.
|
||
Single story throughout: all heavy equipment needs ground-slab floor
|
||
loading (multiple tons per m²).
|
||
|
||
The workshop and the visitor corridor were added in October 2026, together
|
||
with an overhead crane over the production compartment; what they need and
|
||
what they change in the shell is in
|
||
[crane, workshop and tours](crane-workshop-tours.md). They add ~210 to
|
||
280 m² to a program that already filled the 60 × 25 m footprint, which
|
||
settles the open question below in favour of growing the program into the
|
||
floor the utility yard frees: at the lower half of the table everything
|
||
fits; at the upper half, finished goods move to the phase 2 building.
|
||
|
||
### Detached utility yard, parking, and what that moves
|
||
|
||
The massing model puts the boiler and chiller in a **detached utility yard**
|
||
alongside the main building rather than inside it, which is what the boiler's
|
||
own-room requirement in [facility security](facility-security.md) and biomass
|
||
fuel delivery both push toward:
|
||
|
||
| | Area | Height |
|
||
|---|---|---|
|
||
| Boiler hall | 66 m² | 6.0 m |
|
||
| Biomass fuel store | 42 m² | 5.0 m |
|
||
| Chiller room | 60 m² | 5.0 m |
|
||
| Cooling tower (outdoor pad) | 10 m² | 3.5 m |
|
||
| Flue stack | - | 14 m |
|
||
|
||
Boiler plus chiller at 126 m² lands inside the 100 to 150 m² the zone table
|
||
allows, but moving them out of the main shed frees that floor for
|
||
production, so either the main building shrinks by ~126 m² or the program
|
||
grows into it. Decide which before the building is priced.
|
||
|
||
Staff parking is roofed, in the front yard clear of the loading route:
|
||
**10 car bays** (27.7 × 7.0 m canopy, 195 m²) and **~30 scooter spaces**
|
||
(13.7 × 5.5 m, 76 m²), carrying a further **~40 kWp** of PV on their
|
||
canopies — dimensions per the modelled layout in the
|
||
[construction RFQ](finance/phase1-construction-rfq.md). At 4.1 m and 3.5 m
|
||
they sit below the main building's 7.0 m low eave, so they cannot shade it.
|
||
|
||
### Expansion headroom: a second building
|
||
|
||
Tested against the candidate Mueang Chi parcel, in the massing model at
|
||
`factory_building_rough.FCStd`. The whole zone table above fits inside one
|
||
60 × 25 m building, so a second one is expansion **beyond** the current
|
||
program — doubling pressing capacity, or moving finished goods out to free
|
||
production floor — not a gap in it.
|
||
|
||
| | Phase 1 | Phase 2 | Total |
|
||
|---|---|---|---|
|
||
| Footprint | 60 × 25 m — 1,500 m² | 45 × 38 m — 1,710 m² | 3,210 m² |
|
||
| Roof PV | ~247 kWp | ~251 kWp | **~498 kWp** |
|
||
| Tightest boundary clearance | 15.7 m | 3.0 m | |
|
||
|
||
- **45 × 38 m is the sweet spot.** The plot narrows going south, so past
|
||
~45 m of length the width falls away faster than length adds: 40 m gives
|
||
1,607 m², 45 m gives 1,723 m², 50 m drops to 1,558 m², and beyond 65 m
|
||
nothing useful fits.
|
||
- **A 20 m yard** between the buildings covers fire separation and shared
|
||
loading off the phase 1 circulation road.
|
||
- **Roof form: two-bay sawtooth, shaded rows deliberately left empty.**
|
||
A single 38 m monopitch would be the best solar answer — 28 panel rows,
|
||
none shaded, ~17% more yield than what is drawn, but it needs a **13.7 m**
|
||
high wall. The sawtooth holds the high side to **10.35 m**, at a cost: each
|
||
bay falls toward ESE onto the next bay's 3.35 m riser, so the bottom rows
|
||
sit in shadow (the lowest is blocked below a 53° sun profile angle). Those
|
||
two rows on the first bay are left empty rather than populated, which
|
||
trades ~8% of the roof's yield for clean strings, no mismatch losses, and
|
||
a maintenance walkway. Building height won this trade; revisit it if
|
||
cladding a 13.7 m wall turns out cheaper than the lost generation.
|
||
A 7° single pitch (11.7 m high side) sits between the two if wanted.
|
||
- **Coverage stays comfortable**: 3,210 m² is 39% of the deed area (34% of
|
||
the mapped extent), well under the 50 to 60% typically allowed.
|
||
- **The two roofs together clear 500 kWp**, which removes the need for the
|
||
ground-mount solar assumed further down this page.
|
||
|
||
Two caveats. Phase 2's tightest corner sits **3.0 m** from the boundary and
|
||
must be checked against the local ผังเมือง setback rule before it is taken as
|
||
real. And the plot's zoning for factory use is still unverified — that gates
|
||
phase 1 every bit as much as phase 2.
|
||
|
||
## Land: factory plot
|
||
|
||
Industrial plots typically allow 50 to 60% building coverage, and the site
|
||
needs truck access and turning, parking, the outdoor cooling tower, the
|
||
separated BESS enclosure, possible ground-mount solar, and expansion room.
|
||
|
||
- Minimum workable: **~4 rai** (6,400 m²)
|
||
- Comfortable with expansion and ground-mount solar: **~6 to 8 rai**
|
||
(9,600 to 12,800 m²)
|
||
|
||
Separate asset: the **60 rai** forestry-classified parcel for coppice
|
||
fuelwood (see [biomass](biomass.md)), pending its title check. It is a fuel
|
||
plantation, not a factory site candidate unless the classification allows
|
||
conversion, which forestry land generally does not.
|
||
|
||
## Electrical scale
|
||
|
||
| Load | Rough figure |
|
||
|---|---|
|
||
| Pressing machinery (two Duplex systems + the Classic) | ~90 to 120 kW installed (estimate: 32 kVA per Duplex system by Newbilt's requirements; the second extruders and the Classic not yet published) |
|
||
| Process chiller (250 kW cooling) | ~80 to 125 kW electrical |
|
||
| Whole-factory HVAC | ~100 to 200 kW peak (estimate) |
|
||
| Electric steam boiler (if chosen over biomass/LPG) | ~300 kW |
|
||
| Compressed air, lighting, IT, misc | ~30 to 50 kW |
|
||
| **Plant peak demand** | **~300 to 450 kW without electric boiler; ~600 to 750 kW with it** |
|
||
|
||
Grid connection: a medium-voltage connection with a transformer in the
|
||
**500 to 1,000 kVA** class from PEA, sized by the boiler decision.
|
||
|
||
**Not yet re-based for the five-press fleet** (October 2026). The chiller
|
||
and peak rows above are sized for one Duplex's ~250 kW of cooling; at
|
||
Newbilt's up to 125 kW of cooling per press, five presses need up to ~625
|
||
kW, so the chiller's electrical draw and the plant peak rise accordingly.
|
||
Re-size with the Newbilt re-quote figures, together with the steam below
|
||
([pressing line](equipment/pressing-line.md)).
|
||
|
||
Tariff: PEA Schedule 3.2.2, Medium General Service on time of use at
|
||
22 kV (the flat rate is closed to new customers): 132.93 THB/kW demand
|
||
charge on the peak-hour maximum, 4.1839 THB/kWh peak (09:00 to 22:00 on
|
||
weekdays) and 2.6037 THB/kWh off-peak, plus Ft (0.1623 THB/kWh for
|
||
September to December 2026) and VAT. Two-shift production lands at a
|
||
blended ~3.81 THB/kWh before the demand charge, roughly 4.3M to 6.4M THB a
|
||
year without electric steam (estimate); the deposit for the connection is
|
||
400 THB per kVA. Detail and what it decides for steam, PV and the battery
|
||
in [sustainability](sustainability.md#grid-tariff-pea-and-what-it-decides).
|
||
|
||
Galvanics (Phase 5) is not in the table yet. By the Pheenix Alpha and
|
||
Sibert datasheets, one electroforming line plus the stamper prep machines
|
||
is ~30 kVA connected, two three-phase plating units and the rest
|
||
single-phase (see [galvanics and stamper prep](equipment/galvanics.md)):
|
||
small against the connection, but its own feeder and meter.
|
||
|
||
## Solar and storage
|
||
|
||
- The phase 1 roof carries **~247 kWp** (425 modules on the 1,523 m²
|
||
roof plane, per the [construction RFQ](finance/phase1-construction-rfq.md)).
|
||
This supersedes the older rule of thumb of 150 to 200 kWp on a
|
||
~1,500 m² building, which the massing model has overtaken
|
||
- Northern Thailand yield ~1,400 to 1,500 kWh/kWp/yr, so 300 kWp produces
|
||
roughly **420 to 450 MWh/yr**
|
||
- Plant consumption at mature two-shift operation: roughly **1,000 to
|
||
1,500 MWh/yr** without electric steam, up to **~2,500 MWh/yr** with it
|
||
(estimate), so 300 kWp covers roughly **28 to 45%** of consumption
|
||
without electric steam, falling to **~17%** with it; a bigger array
|
||
shifts that up
|
||
- Battery: **271 kWh** Gobel stack (ride-through, roughly
|
||
two to three hours of the chiller's electrical draw; peak shaving earns
|
||
little under PEA's time-of-use tariff, see
|
||
[sustainability](sustainability.md#grid-tariff-pea-and-what-it-decides))
|
||
|
||
## Steam and fuel
|
||
|
||
- Boiler: **400 kg/h at 10 bar / 180 °C** (~300 kW thermal), sized for
|
||
one Duplex. The current five-press fleet draws **~750 to 900 kg/h** at
|
||
Newbilt's 150 to 180 kg/h per press: not yet re-based, and the fuel
|
||
figures below scale with it
|
||
- If biomass: **~350 to 400 t/yr** air-dry wood at mature operation, of
|
||
which the 60 rai coppice could supply **~80 to 135 t/yr**
|
||
- If LPG: **~2.5 to 5 t** bulk tank on site (no gas pipeline in the North)
|
||
|
||
## People
|
||
|
||
Rough mature-operation headcount (estimate): 4 to 6 press/finishing
|
||
operators per shift, 2 to 3 galvanics, 1 to 2 mastering/cutting engineers,
|
||
1 to 2 QC, 2 maintenance, 3 to 5 admin/sales/logistics. Roughly **15 to 25
|
||
people** across shifts at maturity, fewer than half that at launch. For
|
||
galvanics, OMS's rule of thumb (one person runs about 20 stampers a day,
|
||
two from about 30) against the 8 to 20 parts a day at full capacity
|
||
points to one operator per shift
|
||
([galvanics and stamper prep](equipment/galvanics.md)).
|
||
|
||
## Money (cross-references)
|
||
|
||
Figures in USD and THB at 1 USD = 33 THB (5 August 2026); vendor quotes
|
||
keep their original currency alongside.
|
||
|
||
- Newbilt semi-auto line: **~USD 232k (~7.7M THB)**, from the June 2024
|
||
quote of EUR 200,500 — expired, in
|
||
[pressing-line](equipment/pressing-line.md)
|
||
- Thai-sourced utilities, HVAC, racking, solar, BESS baseline: **~24M to
|
||
42M THB (~USD 730k to 1.27M)**, detail in the
|
||
[utilities CSV](finance/utilities-investment.csv)
|
||
- Not yet priced: the second Duplex system and the Newbilt Classic
|
||
(estimates in [total investment](finance/total-investment.md)),
|
||
galvanics line, mastering/cutting room, metrology, building
|
||
construction/fit-out, land
|