grabowski c50417668b Press fleet: two Newbilt Duplex systems with an extruder per press, plus a Classic
The current plan (user decision, October 2026) replaces the 50/50 target
(two semi-automatic presses and two Pheenix AD12s) with an all-Newbilt
fleet of five presses: two Duplex systems in Newbilt's two-extruder
configuration (two HRP 12 presses, an extruder each, one hydraulic unit)
and one Classic fully automatic press.

- pressing-line.md: new "Current plan" section (fleet table, what it
  means, phasing from the Single 2.1 as the first half of system 1,
  re-quote questions); site requirements per Duplex system.
- scale.md: capacity table and basis (368 to 448 records/h, ~1.06 to 1.5M
  a year on two shifts, same range as before); pressing electrical row;
  steam and cooling flagged, not re-based: five presses draw ~750 to 900
  kg/h of steam and up to ~625 kW of cooling at Newbilt's per-press
  figures, against the 400 kg/h / 250 kW sized for one Duplex.
- total-investment.md: fleet change as an added-scope row (system 2
  ~230k-300k and the Classic ~290k-460k, estimates; -60k / -160k against
  the two blocks it replaces); headline unchanged until the re-base.
- roadmap items 4, 5 and 24, revenue model mature row, crane doc (the
  Classic's weight now decides 5 t or 3.2 t), vendor landscape (AD12 is
  the comparison for the Classic), README.

The business plan docx is not regenerated.
2026-10-10 16:05:27 +07:00

96 lines
7.7 KiB
Markdown
Raw Blame History

This file contains ambiguous Unicode characters
This file contains Unicode characters that might be confused with other characters. If you think that this is intentional, you can safely ignore this warning. Use the Escape button to reveal them.
# Total Investment: Rough Picture
Everything priced or estimated so far, rolled into one view. Blocks marked
"estimate" have no vendor confirmation; the rest trace to quotes or the
researched ranges in this repo. Treat all figures as budgetary with a wide
margin (plus or minus 30 to 50% on the estimates) until RFQs replace them.
**Currency: USD and THB.** FX at 5 August 2026: **1 USD = 33 THB**.
Vendor quotes issued in another currency are kept in that currency
wherever they appear next to their source document, and converted here at
**1 EUR = 1.155 USD** and **1 GBP = 1.35 USD**. Original figures compiled
July 2026; the underlying THB estimates are unchanged, because EUR/THB at
~38 is where it was when they were made.
## Full vision, all blocks
| Block | USD | THB | Basis |
|---|---|---|---|
| Newbilt semi-auto line, full Duplex | 350k – 370k | 11.5M – 12.2M | 2024 quote EUR 200,500 (~USD 232k) + quoted 2nd press/extruder ~USD 115k; expired, needs re-quote. The fleet has since changed, see the added-scope table |
| 2 automated presses (Pheenix AD12) | 580k – 920k | 19.1M – 30.5M | unverified ~USD 340k/press indicative + delivery and commissioning. Replaced by the Newbilt Classic in the current fleet, see the added-scope table |
| Galvanics line (Digital Matrix or Pheenix Alpha) | 320k – 650k | 10.7M – 21.4M | six-figure-USD turnkey inference from vendor research; the Pheenix range (2024 flyers, [galvanics and stamper prep](../equipment/galvanics.md)) is unpriced too; OMS's reference prices (letter, 9 October 2026) put a complete 4-cell wet room at EUR 224k basic to 311k advanced (~USD 259k to 359k; ~270k to 371k with know-how transfer), installation and water treatment extra: at or below this block's low end, kept until quotes exist |
| Zero-discharge water treatment (ZLD) | 90k – 240k | 3.0M – 8.0M | utilities CSV option row |
| Stamper prep (Sibert VSP, VSF, VSC) | 60k – 170k | 1.9M – 5.7M | estimate kept until the re-base; Sibert has since confirmed USD 250k for the three (its time, spares, shipping and travel extra), the difference is in the table below |
| Mastering and cutting room (Agnew or Sillitoe lathe system, cutter amps, console, room treatment) | 290k – 580k | 9.6M – 19.1M | estimate, bespoke market; the Sillitoe SDMS lists at USD 125k for lathe, head, amplifier and automation (ex tax, shipping), which makes the low end reachable; band kept until both quotes exist |
| Metrology and QC stack (confocal, profiler, XRF, inline vision, audio station) | 350k – 810k | 11.5M – 26.7M | estimate, phaseable |
| Utilities, solar, HVAC, racking baseline | 730k – 1,270k | 24.0M – 41.6M | reviewed [utilities CSV](utilities-investment.csv), THB-native |
| Building ~1,500 m² plus civil works | 650k – 1,100k | 21.4M – 36.2M | estimate at 12,000–20,000 THB/m² Thai industrial construction plus ~20% site works |
| Land 6–8 rai, if purchased | 360k – 970k | 12.0M – 32.0M | estimate at 2–4M THB/rai industrial; leasing cuts this to near zero upfront |
| Traceability and factory software | 60k – 170k | 1.9M – 5.7M | estimate |
| Freight, installation, training (non-Newbilt equipment) | 120k – 230k | 3.8M – 7.6M | estimate |
| Working capital, PVC stock, spares | 120k – 230k | 3.8M – 7.6M | estimate |
| Subtotal | ~4.1M – 7.7M | ~135M – 254M | |
| Contingency 15% | ~0.6M – 1.2M | ~20M – 38M | |
| **Total, full vision** | **~4.7M – 8.9M USD** | **~155M – 294M THB** | |
### Added scope, not yet in the roll-up
Decided, or re-priced by a vendor, after the roll-up above was compiled;
carried here until the next re-base folds them into the blocks (the
building, software and stamper prep lines, and the contingency on top).
| Block | USD | THB | Basis |
|---|---|---|---|
| Overhead crane, runway, frame premium, machine door | 97k – 227k | 3.2M – 7.5M | estimate, [crane, workshop and tours](../crane-workshop-tours.md) |
| Maintenance workshop and machine bay fit-out | 30k – 76k | 1.0M – 2.5M | estimate, same |
| Visitor corridor and accessible entrance | 67k – 148k | 2.2M – 4.9M | estimate, same |
| Artist platform, public side (calculator, campaigns, payments) | 40k – 90k | 1.3M – 3.0M | estimate, [artist platform](../artist-platform.md) |
| PVC material lab, day-one tier (incl. plaque press and sample conditioning) | 55k – 150k | 1.8M – 5.0M | estimate, [quality automation](../quality-automation.md); not costed in the metrology block above. The mature tier (torque rheometer, DSC, FTIR, ~120k – 240k) is deferred, with partner labs in between |
| Stamper prep re-priced: USD 250k for VSP, VSF and VSC against the 60k – 170k block above | +190k (low case) / +80k (high case) | +6.3M / +2.6M | Sibert's budget confirmation, email of 5 October 2026 ([galvanics and stamper prep](../equipment/galvanics.md)); itemised quotation to follow. Its time, spare parts, shipping and travel are extra and fall into the freight/installation and spares blocks above |
| Press fleet changed (October 2026) to two Newbilt Duplex systems with an extruder per press plus one Newbilt Classic, replacing the two blocks above (930k – 1,290k): Duplex system 1 as the first block (350k – 370k), system 2 ~230k – 300k (two press and extruder sets at the quoted ~115k each, plus its hydraulic unit, estimate), the Classic ~290k – 460k (the AD12 band per press as a placeholder; no Newbilt price on file) | −60k (low case) / −160k (high case) | −2.0M / −5.3M | estimate, [pressing line](../equipment/pressing-line.md); the Newbilt re-quote replaces it. The utilities for five presses are not re-sized yet ([scale](../scale.md)) |
| **Added so far** | **~420k – 610k** | **~13.8M – 20.2M** | about 8 to 10% on the full-vision subtotal |
## Phased entry
A credible launch phase is far smaller, roughly **1.7M to 2.9M USD
(~57M to 95M THB)**:
- Newbilt Single system (not Duplex yet)
- Bridge stampers from Stamper Discs, so no galvanics line at launch
- Basic QC (microscope, benchtop PVC lab, sampled listening), full
metrology deferred; the PVC lab's day-one tier is the added-scope row
above
- Leased building instead of purchase, modest first solar array
- Galvanics, the second Duplex system and the Classic, full metrology,
and the biomass boiler follow as revenue-funded or second-round
expansions
The planning already supports this: the Duplex-ready hydraulics, the
bridge-supplier role for Stamper Discs, the staged electric-to-biomass
steam path, and the phaseable metrology stack are all documented for
exactly this reason.
## What moves the number
- **BOI**: machinery duty exemption applies across most of the equipment
blocks, and the solar and automation spend converts into CIT-exemption
headroom; the application precedes every purchase order (see
[boi.md](../boi.md))
- **Buy vs lease** on land and building swings roughly **1.0M to 2.1M
USD (~34M to 69M THB)** of upfront capital, and also moves the launch
date by about three quarters — see
[project-timeline.md](../project-timeline.md)
- **Biggest uncertainty bands**: metrology (partly a choice of ambition),
the mastering/cutting room (bespoke vendor, no public pricing), the
Newbilt Classic (no price on file), and land
- **Currency exposure is real and is not modelled here.** Revenue is
mostly USD/EUR from export customers, the cost base is mostly THB, and
the largest single equipment block is EUR-denominated and unhedged
against an order that will not be placed for roughly a year (see
[project-timeline.md](../project-timeline.md)). A 10% move in EUR/THB
between now and the Newbilt order is worth ~USD 25–35k on that line
alone. Ask for the re-quote to state its currency and validity period.
- Every band narrows only with RFQs; the supplier map in
[equipment-suppliers.md](../suppliers/equipment-suppliers.md) lists who
to ask