The current plan (user decision, October 2026) replaces the 50/50 target (two semi-automatic presses and two Pheenix AD12s) with an all-Newbilt fleet of five presses: two Duplex systems in Newbilt's two-extruder configuration (two HRP 12 presses, an extruder each, one hydraulic unit) and one Classic fully automatic press. - pressing-line.md: new "Current plan" section (fleet table, what it means, phasing from the Single 2.1 as the first half of system 1, re-quote questions); site requirements per Duplex system. - scale.md: capacity table and basis (368 to 448 records/h, ~1.06 to 1.5M a year on two shifts, same range as before); pressing electrical row; steam and cooling flagged, not re-based: five presses draw ~750 to 900 kg/h of steam and up to ~625 kW of cooling at Newbilt's per-press figures, against the 400 kg/h / 250 kW sized for one Duplex. - total-investment.md: fleet change as an added-scope row (system 2 ~230k-300k and the Classic ~290k-460k, estimates; -60k / -160k against the two blocks it replaces); headline unchanged until the re-base. - roadmap items 4, 5 and 24, revenue model mature row, crane doc (the Classic's weight now decides 5 t or 3.2 t), vendor landscape (AD12 is the comparison for the Classic), README. The business plan docx is not regenerated.
264 lines
15 KiB
Markdown
264 lines
15 KiB
Markdown
# CNX Vinyl / Poy Records
|
||
|
||
<img src="docs/brand/poyrecord-logo-1536x1536.png" alt="Poy Records logo" width="160">
|
||
|
||
A vinyl record factory in planning for the Chiang Mai area of northern
|
||
Thailand (site candidates include Lamphun and Lampang provinces and, since
|
||
October 2026, Payap University land in Chiang Mai). This repository is
|
||
the source of truth for the project: planning documents and cost data
|
||
today. As the factory takes shape it will also hold the data and software
|
||
used to run it.
|
||
|
||
## Team
|
||
|
||
- **Simona Meesaiyati**, Project Lead: management and the audio side
|
||
- **Alexander Grabowski**, Technical Consultant: the technical side
|
||
|
||
[buildfor.life](https://buildfor.life) supports the project in a consulting
|
||
capacity.
|
||
|
||
## Vision: Full-Service Production
|
||
|
||
The goal is the complete vinyl production chain under one roof, from audio
|
||
file to delivered record:
|
||
|
||
1. **Mastering**: audio mastering for vinyl
|
||
2. **Lathe cutting**: cutting the master disc
|
||
3. **Silvering**: metallizing the cut master
|
||
4. **Stamper production**: electroforming nickel stampers in-house
|
||
5. **Pressing**: extrusion and pressing of the records, with the labels
|
||
pressed in
|
||
6. **Finishing**: trimming, sleeving, shrink wrapping
|
||
7. **Packaging**: folded paper cartons (jackets and sleeves), produced in
|
||
collaboration with local packaging manufacturers
|
||
8. **Fulfillment**: dropshipping directly to end customers on behalf of
|
||
labels and artists, alongside conventional bulk delivery
|
||
|
||
In-house galvanics (steps 3 and 4) removes the dependency on overseas stamper
|
||
suppliers, a common bottleneck for pressing plants, and shortens turnaround
|
||
for clients. Partnering with local carton manufacturers keeps packaging
|
||
sourcing close to the plant, in line with the local-sourcing preference for
|
||
materials. The pressing line is documented in detail, galvanics and stamper
|
||
prep from vendor datasheets; equipment, partners, and budgets for the other
|
||
steps are open planning items.
|
||
|
||
## Project Status
|
||
|
||
**Planning stage** (as of October 2026).
|
||
|
||
- Industry outreach has been ongoing for several years: equipment vendors,
|
||
material suppliers, and independent consultants.
|
||
- Alexander and Simona attended
|
||
[Making Vinyl Europe 2026](https://makingvinyl.com/) in Haarlem (30
|
||
September to 2 October). Most people they talked to were strongly
|
||
interested in the full-traceability approach, and for Sibert it was a
|
||
reason to engage at all (notes in the
|
||
[exhibitor briefing](docs/suppliers/making-vinyl-europe-2026-exhibitors.md#after-the-show)).
|
||
- Payap University (Chiang Mai) has offered land on lease and wants to
|
||
build joint student programmes with the plant
|
||
([site candidates](docs/site-candidates.md),
|
||
[Payap partnership](docs/payap-partnership.md)).
|
||
- A collaboration with [ResurRec](https://www.resurrec.com/) is under
|
||
discussion.
|
||
- Back from Haarlem, the team is preparing a meeting with the project's
|
||
investor (October 2026). Post-show follow-ups with Pheenix, Sibert, OMS
|
||
and SST are in the
|
||
[exhibitor briefing](docs/suppliers/making-vinyl-europe-2026-exhibitors.md#after-the-show).
|
||
|
||
## Planning Documents
|
||
|
||
The detail lives in dedicated documents:
|
||
|
||
- [Roadmap](docs/roadmap.md): next steps in dependency order, from the
|
||
three current gates (market validation, BOI, land title check) through
|
||
quotes, commitment, build, launch, and expansion
|
||
- [Pressing line equipment plan](docs/equipment/pressing-line.md): the
|
||
current all-Newbilt fleet (two Duplex systems with an extruder per press,
|
||
plus one Classic automatic press), the 2024 Newbilt quote (~USD 232k,
|
||
expired), the 2026 product flyers, and site requirements
|
||
- [Galvanics and stamper prep equipment plan](docs/equipment/galvanics.md):
|
||
the metal path from lacquer to press-ready stamper, from vendor
|
||
datasheets: Pheenix Alpha's electroforming range as a second turnkey
|
||
vendor next to Digital Matrix, OMS as a third named by Sibert (reference
|
||
prices for a 4-cell wet room, EUR 224k to 311k), Sibert's
|
||
VSP/VSF/VSC stamper prep line (USD 250k budget for the three confirmed),
|
||
the utilities they need, a first cell-count estimate, and Sibert's
|
||
optical-disc reference material
|
||
- [Vendor landscape](docs/suppliers/vendor-landscape.md): researched
|
||
candidates for mastering and cutting (Agnew Analog, and the Sillitoe
|
||
SDMS with integrated cutting automation at a published USD 125k),
|
||
galvanics equipment
|
||
(Plating Power / Digital Matrix, Pheenix Alpha, Optical Media Services),
|
||
used lathes and cutting-room contacts (via OMS),
|
||
stamper preparation
|
||
(Sibert), bridge stamper service (Stamper Discs), and automated presses
|
||
(Pheenix Alpha, the comparison for the Classic)
|
||
- [Equipment needs and supplier map](docs/suppliers/equipment-suppliers.md):
|
||
the full needs list per production step with supplier tables and contacts
|
||
- [Sustainability](docs/sustainability.md): the solar installation (Deye
|
||
inverters, 271 kWh Gobel Power battery stack), the PEA grid tariff and
|
||
what it decides (biomass steam at a quarter to a tenth of the cost of
|
||
electric, PV rather than solar thermal), the zero contaminated water commitment,
|
||
and the materials strategy
|
||
- [Worker safety](docs/worker-safety.md): safety training, galvanics clean
|
||
rooms and decontamination, PPE
|
||
- [Biomass fuel strategy](docs/biomass.md): the 60 rai own-grown coppice
|
||
idea (with the forestry-classification check that comes first), northern
|
||
agricultural waste as the main supply, reported northern fuel prices
|
||
(October 2026) and who sets them, and the staged electric-to-biomass path
|
||
- [BOI investment promotion](docs/boi.md): the promotion strategy (Group B
|
||
base activity plus solar, automation, and R&D measures for the tax value),
|
||
requirements, Northern-region angle, and why BOI approval precedes
|
||
machinery orders
|
||
- [Facility security and site systems](docs/facility-security.md): access
|
||
control, CCTV, whole-factory HVAC (temperature, humidity, PM), archive and
|
||
audio protection, fire and life safety, plant monitoring, Thai compliance
|
||
anchors
|
||
- [Overhead crane, workshop and visitor corridor](docs/crane-workshop-tours.md):
|
||
a 5 t crane over the whole production floor to move machines in and
|
||
out, a crane-served maintenance workshop and machine bay at the ramp
|
||
end, and a glazed ground-level corridor for guided tours without noise,
|
||
dust or plating chemistry; what each changes in the building and what
|
||
it costs
|
||
- [Production hall layout sketch](docs/production-hall-layout-sketch.png):
|
||
a rough BIM sketch in FreeCAD (`docs/production-hall-layout-sketch.FCStd`)
|
||
of the 60 x 25 m phase 1 hall: zones in process order along the visitor
|
||
corridor, the crane zone, room-in-room boxes and the main equipment; every
|
||
position is an estimate
|
||
- [Process logging and traceability](docs/traceability.md): end-to-end
|
||
per-order traceability for customers, batch genealogy from audio file to
|
||
shipment, and the requirements this sets for the factory software
|
||
- [Digital factory systems plan](docs/digital-factory.md): every system
|
||
that has to exist for environment, machine, QC and genealogy data to land
|
||
in one database keyed to one record identity: the plant as one more site
|
||
in B4L's existing NixOS fleet (the cnx-network clan: mesh, DNS, fleet
|
||
monitoring, site gateway module, public proxy), what changes in that
|
||
repo, VLAN zoning, Telegraf/MQTT acquisition source by source, QC
|
||
instrument integration, the factory application, alerting, backup,
|
||
security, the data clauses for every RFQ, build order and rough cost
|
||
- [Quality automation](docs/quality-automation.md): stamper metrology
|
||
(Keyence-class confocal, profiler, XRF), layered pressed-record QC (100%
|
||
optical inspection, per-cycle press telemetry, sampled automated audio
|
||
comparison), and how it feeds traceability
|
||
- [Process flow](docs/process-flow.md): the whole chain from audio file to
|
||
delivered record as a chart and stage table, with every check and the
|
||
three artist approval gates (printable diagram alongside)
|
||
- [Artist platform](docs/artist-platform.md): upload a master and
|
||
artwork, get a transparent itemised offer from the price calculator
|
||
(for artists, labels and any other customer), and optionally launch a
|
||
fan-funded campaign that the plant presses and ships to each fan once
|
||
enough have pre-ordered, with refunds if not
|
||
- [Plant operation page](docs/plant-operation.html): a single static page
|
||
animating the mature plant as a simulated SCADA overview at real cycle
|
||
times: the Newbilt Duplex and two Classic presses, the Pheenix Alpha
|
||
electroforming line and Sibert stamper prep, from PVC intake and the
|
||
material lab through pressing, inspection, packaging and fulfillment,
|
||
with the three artist gates, the mother archive, utilities and energy;
|
||
1× is real time, up to 3600× (a day in 24 s); every station is
|
||
clickable and names the source of its figures; on phones and tablets
|
||
held sideways it pinch-zooms and opens station details in a side sheet
|
||
- [Test site](site/README.md): `site/` builds https://cnxvinyl.lol/, the
|
||
internal test site with demo pages from `docs/` (the plant operation
|
||
page first) and any static site we want to share by link; Gitea Actions
|
||
deploys it to the buildfor.life web server on every push that touches it
|
||
- [Production timeline](docs/production-timeline.md): how long an order
|
||
takes stage by stage, launch vs mature configuration, the repress fast
|
||
path, and what lead time can honestly be quoted to a customer
|
||
- [Project timeline](docs/project-timeline.md): the calendar from today to
|
||
first paying release, the BOI-to-machinery critical path, and where the
|
||
float actually sits
|
||
- [Site candidates](docs/site-candidates.md): the land options side by
|
||
side (the Mueang Chi lease, the Northern Region Industrial Estate, and
|
||
Payap University's offer of land next to a pharmaceutical facility under
|
||
construction) and what has to be checked before any of them is chosen
|
||
- [Payap University partnership](docs/payap-partnership.md): joint student
|
||
programmes in audio engineering (mastering, lathe cutting), IT and
|
||
business built around the plant, what they change in the plan (cutting
|
||
room earlier, pre-release security, student access) and what to agree
|
||
- [Project scale](docs/scale.md): rough numbers for everything on one page:
|
||
output capacity, building area, land, electrical demand, solar and
|
||
storage, steam and fuel, headcount, and money cross-references
|
||
- [Total investment](docs/finance/total-investment.md): the full-vision
|
||
roll-up (~4.7M to 8.9M USD) and the ~1.7M to 2.9M USD phased entry, with
|
||
the basis of every block
|
||
- [Phase 1 construction RFQ](docs/finance/phase1-construction-rfq.md):
|
||
the spec sheet for asking a contractor to price the phase 1 buildings
|
||
and site works, with quantities taken from the parametric BIM model
|
||
- [Revenue model](docs/finance/revenue-model.md): rough full-capacity
|
||
revenue (~3.7M to 6.8M USD/yr), direct cost and margin per record, and
|
||
the levers and caveats behind the numbers
|
||
- [Business plan](docs/business-plan/CNX-Vinyl-Business-Plan.docx): the
|
||
investor-facing roll-up of everything above, built from
|
||
`docs/business-plan/build/` (run `python build_plan.py` to regenerate
|
||
after the numbers move). Draft 0.1 carries the land-lease decision, the
|
||
cassette and CD scope, and Ploy Printing as packaging partner and
|
||
intended co-investor
|
||
|
||
## Repository Layout
|
||
|
||
```
|
||
docs/
|
||
├── brand/ Poy Records logo (1536 px PNG)
|
||
├── business-plan/
|
||
│ ├── CNX-Vinyl-Business-Plan.docx Investor business plan (generated)
|
||
│ └── build/ Python source of the plan; regenerate with
|
||
│ build_plan.py
|
||
├── consulting/ Consultancy proposals and overviews
|
||
├── equipment/
|
||
│ ├── newbilt/ Offers, site requirements, process schematic,
|
||
│ │ service rates, 2026 product flyers (vendor PDFs)
|
||
│ ├── oms/ OMS introduction letter: wet-room units, reference
|
||
│ │ prices, capacities, lathe contacts (vendor docx)
|
||
│ ├── pheenix-alpha/ Electroforming range flyers (vendor PDFs)
|
||
│ ├── sibert/ Stamper prep specifications and line-up drawing
|
||
│ │ (2021 issues in specs-2021/), 2008-09
|
||
│ │ optical-disc literature (vendor PDFs)
|
||
│ ├── galvanics.md Electroforming and stamper prep equipment plan
|
||
│ └── pressing-line.md Press fleet strategy and equipment plan
|
||
├── finance/ Project cost overviews, revenue model,
|
||
│ construction RFQ, PEA electricity tariff
|
||
│ schedule (pea/), biomass fuel market
|
||
│ reports (biomass/)
|
||
├── suppliers/ Supplier contacts, vendor landscape, supplier map
|
||
├── artist-platform.md Upload, price calculator, fan-funded pressing
|
||
├── biomass.md Biomass fuel strategy and the 60 rai coppice idea
|
||
├── boi.md BOI promotion strategy and requirements
|
||
├── crane-workshop-tours.md Overhead crane, workshop, visitor corridor
|
||
├── digital-factory.md Data platform, NixOS/Clan fleet, acquisition, app
|
||
├── facility-security.md Security, HVAC, fire and life safety, compliance
|
||
├── payap-partnership.md Joint student programmes with Payap University
|
||
├── plant-operation.html Animated plant overview (simulated SCADA)
|
||
├── process-flow.md Audio file to delivered record, with all checks
|
||
├── production-hall-layout-sketch.FCStd Rough BIM layout sketch of the hall
|
||
├── production-hall-layout-sketch.png Top view of the sketch
|
||
├── production-timeline.md Order turnaround, stage by stage
|
||
├── project-timeline.md Calendar to first paying release, critical path
|
||
├── quality-automation.md Stamper metrology and layered record QC
|
||
├── roadmap.md Next steps in dependency order
|
||
├── scale.md Rough project sizing on one page
|
||
├── site-candidates.md Land options and the checks before choosing
|
||
├── sustainability.md Energy, water, materials commitments
|
||
├── traceability.md Process logging and per-order traceability
|
||
└── worker-safety.md Training, clean rooms, PPE
|
||
site/ Internal test site https://cnxvinyl.lol/
|
||
├── public/ Served as is: landing page, static sites
|
||
├── build.sh Builds site/dist: public/ plus demo pages from docs/
|
||
├── Caddyfile Virtual host for the web server (applied by hand)
|
||
└── README.md Build, deploy and one-time setup
|
||
.gitea/workflows/
|
||
└── deploy-site.yml Builds site/ and deploys it on push to master
|
||
```
|
||
|
||
Vendor PDFs and spreadsheets are primary sources and reflect the state of
|
||
negotiations at their file dates. Treat prices and lead times as snapshots,
|
||
not commitments.
|
||
|
||
## What This Repo Will Grow to Hold
|
||
|
||
- Accumulate planning and vendor documents as decisions firm up, including
|
||
the mastering, cutting, and galvanics chain
|
||
- Add structured data (inventory, orders, production batches) once operations
|
||
begin
|
||
- Host the software/tooling built to run the factory (tracking, ERP-style
|
||
workflows)
|