PEA tariff schedule (May 2023 onward, still current) filed under docs/finance/pea/; Ft 0.1623 THB/kWh for Sep-Dec 2026 from the PEA Ft page. The plant falls under Schedule 3.2.2 (Medium General Service, TOU, 22 kV). New section in sustainability.md: blended ~3.81 THB/kWh for two-shift production plus 132.93 THB/kW demand charge; electric steam ~4.7M-5.5M THB/yr at maturity against ~0.35M-0.8M of biomass fuel; self-consumed PV worth ~3.7 THB/kWh (~4.5-7 yr payback); solar thermal not recommended; the battery earns little from TOU arbitrage or peak shaving. biomass.md, scale.md, the utilities CSV note and the README follow.
19 lines
5.6 KiB
CSV
19 lines
5.6 KiB
CSV
category,item,spec_summary,candidate_thai_suppliers,cost_low_thb,cost_high_thb,cost_basis,notes
|
|
steam,Electric/gas once-through boiler package,"~400-500 kg/h at 10 bar / 180 C incl. softener, feed tank, economizer, installed","Miura Thailand (Chachoengsao); Bangkok Industrial Boilers; STE Thailand",2500000,4000000,engineering estimate,"Miura-class modular once-through; BIB budget option ~2.0-3.5M; service is Bangkok-centric, confirm northern dispatch SLA"
|
|
steam,Biomass/wood-fired boiler package (option),"~0.5 t/h solid fuel (wood chips/pellets/rice husk) incl. fuel feed, grate, dust control, softener, installed",Getabec PCL (Thai fabrication and service),4000000,7000000,engineering estimate,"Sustainability path matching Deepgrooves NL precedent; Viessmann has no strong Thai channel; higher capex, lower fuel opex in the North; NOT included in baseline total"
|
|
steam,Steam balance of plant,"Traps, accumulator, condensate return",Forbes Marshall Thailand,0,0,included,"Largely included in boiler package rows; line kept for RFQ completeness"
|
|
compressed_air,Screw compressor skid (oil-injected),"~7.5 kW VSD screw + refrigerated dryer (3 C PDP) + coalescing filters + ~500 L receiver, installed","Atlas Copco Thailand; Kaeser Thailand (SM-T/Aircenter); Ingersoll Rand Thailand",350000,600000,engineering estimate,"14-30 m3/h demand is small (5-10 hp class); oil-injected + filter train meets 5 micron / 3 C spec"
|
|
compressed_air,True oil-free class-0 (option),Same duty in oil-free class-0,"Atlas Copco (ZR/ZT); Kaeser",1200000,1800000,engineering estimate,"Only if air contacts product stream; NOT included in baseline total"
|
|
cooling,Process chiller package 250 kW,"~71 RT air-cooled screw/scroll chiller + pumps + buffer tank + controls, installed, closed loop","Trane Thailand; Carrier Thailand; Daikin Applied Thailand; Hitachi Thailand",2500000,4000000,engineering estimate,"Newbilt spec: 220 l/min peak, 20-25 C supply; chiller is the safe choice for hot-season wet-bulb"
|
|
cooling,Cooling tower + HX loop (alternative),"FRP tower ~250-300 kW reject + plate HX + pumps + tanks + water treatment","Liang Chi Thailand (tower, large service org); Process Cooling Solutions; Tasaki (integrators)",1000000,2000000,engineering estimate,"Cheaper capex but wet-bulb-limited; hybrid tower + trim chiller is the efficiency-optimal design; NOT included in baseline total"
|
|
water,Boiler feedwater duplex softener,~0.5-0.8 m3/h feedwater duty,"Veolia Water Technologies Thailand; Hydrotek; local RO/softener integrators",80000,200000,market estimate,May suffice alone for a small fire-tube boiler
|
|
water,RO skid (option),0.5-1 m3/h low-TDS feed,"Veolia; Hydrotek; local integrators",200000,500000,market estimate,"Only if low-TDS feed needed; NOT included in baseline total"
|
|
water,Closed-loop cooling water treatment,"Side-stream filtration + dosing + conductivity blowdown control",Veolia; Hydrotek; local integrators,150000,400000,engineering estimate,Chemicals are ongoing opex on top
|
|
water,Galvanics ZLD evaporator (future),"Small MVR or low-temp vacuum evaporator for plating rinse, installed","Core unit imported (WTEYA, Greenlan, Fred); Thai integration via Veolia or Hydrotek",3000000,8000000,market estimate,"For the future galvanics line, zero-discharge requirement; NOT included in baseline total"
|
|
storage,Pallet racking and shelving,"100-200 pallet positions selective/heavy-duty (beams sized 1000-1500 kg/pallet, records are dense) + archive and finished-goods shelving, installed","Jenbunjerd; local fabricators (Sahawatthanakit, UPR, SD Shelf); SSI Schaefer (premium)",800000,1500000,published list prices + engineering estimate,"SSI Schaefer premium tier ~1.5-3M for same scope; ~1000-2000 THB per pallet position at local tier"
|
|
hvac,Whole-factory HVAC,"~1500 m2 at 20-26 C, 35-60% RH, ePM1/F7-F9 filtration sized for burning-season PM2.5, ducting and controls","Daikin Thailand; Trane; Mitsubishi Electric; Carrier; filtration: Camfil Thailand, AAF",7500000,15000000,engineering estimate at 5000-10000 THB/m2,"RH low end of 35% is aggressive for tropics and drives desiccant cost; if 45-60% RH acceptable, cost drops materially"
|
|
hvac,Clean-room-grade zone adder,"Cutting room + galvanics clean room, ~2 x 60 m2, ISO 7/8 with HEPA terminals, positive pressure, airlocks","Same HVAC vendors + clean-room contractors; Camfil HEPA",1200000,3400000,engineering estimate at 10000-28000 THB/m2 adder,Applied only to the two tight zones
|
|
solar,PV rooftop EPC (illustrative 300 kWp),"Turnkey C&I rooftop EPC incl. Deye hybrid inverters, at 25000-35000 THB/kWp","Solar Nicolo (Deye tier-1 distributor); Banpu NEXT; SCG Cleanergy; Sermsang; local Chiang Mai installers",7500000,10500000,market rate per kWp; size illustrative,"Final kWp open until site selection; PEA TOU 3.2.2 plus Ft (Sep-Dec 2026): self-consumed PV worth ~3.7 THB/kWh, ~4.5-7 yr payback (sustainability.md, grid tariff)"
|
|
solar,Battery stack 271 kWh (Gobel),"GP-SRA-HV314 HV LiFePO4 rack, 15 x 18 kWh packs, direct from Shenzhen, 50-60 day lead",Gobel Power (no Thai distributor; integration by solar EPC),1400000,2030000,vendor listed price USD 39900-58000 at ~35 THB/USD,"Confirm Deye BMS protocol compatibility and that the EPC warrants a mixed-vendor DC bus; certs (UN38.3/IEC 62619/CE) to be requested"
|
|
total,BASELINE TOTAL,"Electric steam + oil-injected air + chiller + softener + loop treatment + local racking + HVAC + clean zones + 300 kWp solar + 271 kWh BESS",,23980000,41630000,sum of baseline rows,"~630k-1100k EUR at 38 THB/EUR; excludes options rows (biomass premium, oil-free, tower alternative, RO, ZLD evaporator, SSI premium tier); all figures budgetary +/- 30%, get RFQs before BOI/finance filings"
|