Sillitoe Audio Technology (Australia) sells a complete cutting system:
lathe, MMFB feedback cutterhead, cutting amplifier, Space / Time Control
automation with a virtual groove, vacuum and microscope, at a published
USD 125,000 ex tax and shipping. Vendor landscape gets the narrative and
an Agnew-or-Sillitoe comparison; supplier map, total investment basis,
roadmap item 13 and the digital factory's no-telemetry section (STC cue
sheet, Open Groove export, stylus hours) follow.
2026-10-02 17:31:36 +02:00

77 lines
4.8 KiB
Markdown
Raw Blame History

This file contains ambiguous Unicode characters
This file contains Unicode characters that might be confused with other characters. If you think that this is intentional, you can safely ignore this warning. Use the Escape button to reveal them.
# Total Investment: Rough Picture
Everything priced or estimated so far, rolled into one view. Blocks marked
"estimate" have no vendor confirmation; the rest trace to quotes or the
researched ranges in this repo. Treat all figures as budgetary with a wide
margin (plus or minus 30 to 50% on the estimates) until RFQs replace them.
**Currency: USD and THB.** FX at 5 August 2026: **1 USD = 33 THB**.
Vendor quotes issued in another currency are kept in that currency
wherever they appear next to their source document, and converted here at
**1 EUR = 1.155 USD** and **1 GBP = 1.35 USD**. Original figures compiled
July 2026; the underlying THB estimates are unchanged, because EUR/THB at
~38 is where it was when they were made.
## Full vision, all blocks
| Block | USD | THB | Basis |
|---|---|---|---|
| Newbilt semi-auto line, full Duplex | 350k – 370k | 11.5M – 12.2M | 2024 quote EUR 200,500 (~USD 232k) + quoted 2nd press/extruder ~USD 115k; expired, needs re-quote |
| 2 automated presses (Pheenix AD12) | 580k – 920k | 19.1M – 30.5M | unverified ~USD 340k/press indicative + delivery and commissioning |
| Galvanics line (Digital Matrix) | 320k – 650k | 10.7M – 21.4M | six-figure-USD turnkey inference from vendor research |
| Zero-discharge water treatment (ZLD) | 90k – 240k | 3.0M – 8.0M | utilities CSV option row |
| Stamper prep (Sibert VSP, VSF, VSC) | 60k – 170k | 1.9M – 5.7M | estimate, pricing unpublished |
| Mastering and cutting room (Agnew or Sillitoe lathe system, cutter amps, console, room treatment) | 290k – 580k | 9.6M – 19.1M | estimate, bespoke market; the Sillitoe SDMS lists at USD 125k for lathe, head, amplifier and automation (ex tax, shipping), which makes the low end reachable; band kept until both quotes exist |
| Metrology and QC stack (confocal, profiler, XRF, inline vision, audio station) | 350k – 810k | 11.5M – 26.7M | estimate, phaseable |
| Utilities, solar, HVAC, racking baseline | 730k – 1,270k | 24.0M – 41.6M | reviewed [utilities CSV](utilities-investment.csv), THB-native |
| Building ~1,500 m² plus civil works | 650k – 1,100k | 21.4M – 36.2M | estimate at 12,000–20,000 THB/m² Thai industrial construction plus ~20% site works |
| Land 6–8 rai, if purchased | 360k – 970k | 12.0M – 32.0M | estimate at 2–4M THB/rai industrial; leasing cuts this to near zero upfront |
| Traceability and factory software | 60k – 170k | 1.9M – 5.7M | estimate |
| Freight, installation, training (non-Newbilt equipment) | 120k – 230k | 3.8M – 7.6M | estimate |
| Working capital, PVC stock, spares | 120k – 230k | 3.8M – 7.6M | estimate |
| Subtotal | ~4.1M – 7.7M | ~135M – 254M | |
| Contingency 15% | ~0.6M – 1.2M | ~20M – 38M | |
| **Total, full vision** | **~4.7M – 8.9M USD** | **~155M – 294M THB** | |
## Phased entry
A credible launch phase is far smaller, roughly **1.7M to 2.9M USD
(~57M to 95M THB)**:
- Newbilt Single system (not Duplex yet)
- Bridge stampers from Stamper Discs, so no galvanics line at launch
- Basic QC (microscope, benchtop PVC lab, sampled listening), full
metrology deferred
- Leased building instead of purchase, modest first solar array
- Galvanics, automated presses, full metrology, and the biomass boiler
follow as revenue-funded or second-round expansions
The planning already supports this: the Duplex-ready hydraulics, the
bridge-supplier role for Stamper Discs, the staged electric-to-biomass
steam path, and the phaseable metrology stack are all documented for
exactly this reason.
## What moves the number
- **BOI**: machinery duty exemption applies across most of the equipment
blocks, and the solar and automation spend converts into CIT-exemption
headroom; the application precedes every purchase order (see
[boi.md](../boi.md))
- **Buy vs lease** on land and building swings roughly **1.0M to 2.1M
USD (~34M to 69M THB)** of upfront capital, and also moves the launch
date by about three quarters — see
[project-timeline.md](../project-timeline.md)
- **Biggest uncertainty bands**: metrology (partly a choice of ambition),
the mastering/cutting room (bespoke vendor, no public pricing), the
automated presses (single unverified price point), and land
- **Currency exposure is real and is not modelled here.** Revenue is
mostly USD/EUR from export customers, the cost base is mostly THB, and
the largest single equipment block is EUR-denominated and unhedged
against an order that will not be placed for roughly a year (see
[project-timeline.md](../project-timeline.md)). A 10% move in EUR/THB
between now and the Newbilt order is worth ~USD 25–35k on that line
alone. Ask for the re-quote to state its currency and validity period.
- Every band narrows only with RFQs; the supplier map in
[equipment-suppliers.md](../suppliers/equipment-suppliers.md) lists who
to ask