Files
cnx_vinyl/docs/finance/total-investment.md
T
grabowski 81f3279efd
Deploy test site / deploy (push) Successful in 45s
Add Pheenix galvanics flyers and Sibert stamper prep specs
docs/equipment/pheenix-alpha/: the four Pheenix Alpha electroforming flyers
(2024: PASU silvering, PPPU pre-plating, PDPU dual-cell plating, PMPB
passivation bench), renamed from their download hashes.
docs/equipment/sibert/: the VSP, VSF and VSC technical specifications
(2021), plus Sibert's 2008-09 optical-disc SPS literature and the 2008
Blu-ray stamper characteristics paper in sps-optical-disc-2009/. Two
byte-identical duplicates in the download were dropped.

New docs/equipment/galvanics.md, the metal-path counterpart to
pressing-line.md: datasheet tables for both ranges and what they change.
Pheenix is a second turnkey galvanics vendor next to Digital Matrix and
can quote lacquer-to-record as one vendor; neither range includes water
treatment. Utilities from the sheets (~27 kVA connected per line, DI water,
12-20 C cooling water, extraction sizes), ~5.6 m2 of footprint, and a cell
count estimate (one PDPU at the low end, two at the high end). The Sibert
machines are single-phase, 200/250/600 kg on castors, centre manually and
list no data interface; the VSC locates on the punched hole; the finisher's
water carries nickel. Weights, cycle times, prices and mould fit are listed
as quote questions.

Backlinks and small updates: README (bullet, layout tree, vendor list),
roadmap items 6 and 23, vendor landscape, supplier map, exhibitor briefing
(on-file notes, Sibert three-phase question answered), digital factory
(Pheenix PLC data, Sibert data question, RFQ clause 5), quality automation
(hardness on the centre slug, BD paper as the acceptance-spec model),
sustainability (finisher water), total investment block label (numbers
unchanged), scale (galvanics feeder note), crane weight table, process
flow, pressing-line stamper-fit question, plant page detail lines.
2026-10-03 21:05:00 +02:00

91 lines
5.8 KiB
Markdown
Raw Blame History

This file contains ambiguous Unicode characters
This file contains Unicode characters that might be confused with other characters. If you think that this is intentional, you can safely ignore this warning. Use the Escape button to reveal them.
# Total Investment: Rough Picture
Everything priced or estimated so far, rolled into one view. Blocks marked
"estimate" have no vendor confirmation; the rest trace to quotes or the
researched ranges in this repo. Treat all figures as budgetary with a wide
margin (plus or minus 30 to 50% on the estimates) until RFQs replace them.
**Currency: USD and THB.** FX at 5 August 2026: **1 USD = 33 THB**.
Vendor quotes issued in another currency are kept in that currency
wherever they appear next to their source document, and converted here at
**1 EUR = 1.155 USD** and **1 GBP = 1.35 USD**. Original figures compiled
July 2026; the underlying THB estimates are unchanged, because EUR/THB at
~38 is where it was when they were made.
## Full vision, all blocks
| Block | USD | THB | Basis |
|---|---|---|---|
| Newbilt semi-auto line, full Duplex | 350k – 370k | 11.5M – 12.2M | 2024 quote EUR 200,500 (~USD 232k) + quoted 2nd press/extruder ~USD 115k; expired, needs re-quote |
| 2 automated presses (Pheenix AD12) | 580k – 920k | 19.1M – 30.5M | unverified ~USD 340k/press indicative + delivery and commissioning |
| Galvanics line (Digital Matrix or Pheenix Alpha) | 320k – 650k | 10.7M – 21.4M | six-figure-USD turnkey inference from vendor research; the Pheenix range (2024 flyers, [galvanics and stamper prep](../equipment/galvanics.md)) is unpriced too |
| Zero-discharge water treatment (ZLD) | 90k – 240k | 3.0M – 8.0M | utilities CSV option row |
| Stamper prep (Sibert VSP, VSF, VSC) | 60k – 170k | 1.9M – 5.7M | estimate, pricing unpublished (2021 specifications on file) |
| Mastering and cutting room (Agnew or Sillitoe lathe system, cutter amps, console, room treatment) | 290k – 580k | 9.6M – 19.1M | estimate, bespoke market; the Sillitoe SDMS lists at USD 125k for lathe, head, amplifier and automation (ex tax, shipping), which makes the low end reachable; band kept until both quotes exist |
| Metrology and QC stack (confocal, profiler, XRF, inline vision, audio station) | 350k – 810k | 11.5M – 26.7M | estimate, phaseable |
| Utilities, solar, HVAC, racking baseline | 730k – 1,270k | 24.0M – 41.6M | reviewed [utilities CSV](utilities-investment.csv), THB-native |
| Building ~1,500 m² plus civil works | 650k – 1,100k | 21.4M – 36.2M | estimate at 12,000–20,000 THB/m² Thai industrial construction plus ~20% site works |
| Land 6–8 rai, if purchased | 360k – 970k | 12.0M – 32.0M | estimate at 2–4M THB/rai industrial; leasing cuts this to near zero upfront |
| Traceability and factory software | 60k – 170k | 1.9M – 5.7M | estimate |
| Freight, installation, training (non-Newbilt equipment) | 120k – 230k | 3.8M – 7.6M | estimate |
| Working capital, PVC stock, spares | 120k – 230k | 3.8M – 7.6M | estimate |
| Subtotal | ~4.1M – 7.7M | ~135M – 254M | |
| Contingency 15% | ~0.6M – 1.2M | ~20M – 38M | |
| **Total, full vision** | **~4.7M – 8.9M USD** | **~155M – 294M THB** | |
### Added scope, not yet in the roll-up
Decided after the roll-up above was compiled; carried here as estimates
until the next re-base folds them into the blocks (the building and
software lines, and the contingency on top).
| Block | USD | THB | Basis |
|---|---|---|---|
| Overhead crane, runway, frame premium, machine door | 97k – 227k | 3.2M – 7.5M | estimate, [crane, workshop and tours](../crane-workshop-tours.md) |
| Maintenance workshop and machine bay fit-out | 30k – 76k | 1.0M – 2.5M | estimate, same |
| Visitor corridor and accessible entrance | 67k – 148k | 2.2M – 4.9M | estimate, same |
| Artist platform, public side (calculator, campaigns, payments) | 40k – 90k | 1.3M – 3.0M | estimate, [artist platform](../artist-platform.md) |
| **Added so far** | **~235k – 540k** | **~7.7M – 17.9M** | about 6 to 7% on the full-vision subtotal |
## Phased entry
A credible launch phase is far smaller, roughly **1.7M to 2.9M USD
(~57M to 95M THB)**:
- Newbilt Single system (not Duplex yet)
- Bridge stampers from Stamper Discs, so no galvanics line at launch
- Basic QC (microscope, benchtop PVC lab, sampled listening), full
metrology deferred
- Leased building instead of purchase, modest first solar array
- Galvanics, automated presses, full metrology, and the biomass boiler
follow as revenue-funded or second-round expansions
The planning already supports this: the Duplex-ready hydraulics, the
bridge-supplier role for Stamper Discs, the staged electric-to-biomass
steam path, and the phaseable metrology stack are all documented for
exactly this reason.
## What moves the number
- **BOI**: machinery duty exemption applies across most of the equipment
blocks, and the solar and automation spend converts into CIT-exemption
headroom; the application precedes every purchase order (see
[boi.md](../boi.md))
- **Buy vs lease** on land and building swings roughly **1.0M to 2.1M
USD (~34M to 69M THB)** of upfront capital, and also moves the launch
date by about three quarters — see
[project-timeline.md](../project-timeline.md)
- **Biggest uncertainty bands**: metrology (partly a choice of ambition),
the mastering/cutting room (bespoke vendor, no public pricing), the
automated presses (single unverified price point), and land
- **Currency exposure is real and is not modelled here.** Revenue is
mostly USD/EUR from export customers, the cost base is mostly THB, and
the largest single equipment block is EUR-denominated and unhedged
against an order that will not be placed for roughly a year (see
[project-timeline.md](../project-timeline.md)). A 10% move in EUR/THB
between now and the Newbilt order is worth ~USD 25–35k on that line
alone. Ask for the re-quote to state its currency and validity period.
- Every band narrows only with RFQs; the supplier map in
[equipment-suppliers.md](../suppliers/equipment-suppliers.md) lists who
to ask