# Total Investment: Rough Picture Everything priced or estimated so far, rolled into one view. Blocks marked "estimate" have no vendor confirmation; the rest trace to quotes or the researched ranges in this repo. Treat all figures as budgetary with a wide margin (plus or minus 30 to 50% on the estimates) until RFQs replace them. **Currency: USD and THB.** FX at 5 August 2026: **1 USD = 33 THB**. Vendor quotes issued in another currency are kept in that currency wherever they appear next to their source document, and converted here at **1 EUR = 1.155 USD** and **1 GBP = 1.35 USD**. Original figures compiled July 2026; the underlying THB estimates are unchanged, because EUR/THB at ~38 is where it was when they were made. ## Full vision, all blocks | Block | USD | THB | Basis | |---|---|---|---| | Newbilt semi-auto line, full Duplex | 350k – 370k | 11.5M – 12.2M | 2024 quote EUR 200,500 (~USD 232k) + quoted 2nd press/extruder ~USD 115k; expired, needs re-quote | | 2 automated presses (Pheenix AD12) | 580k – 920k | 19.1M – 30.5M | unverified ~USD 340k/press indicative + delivery and commissioning | | Galvanics line (Digital Matrix or Pheenix Alpha) | 320k – 650k | 10.7M – 21.4M | six-figure-USD turnkey inference from vendor research; the Pheenix range (2024 flyers, [galvanics and stamper prep](../equipment/galvanics.md)) is unpriced too | | Zero-discharge water treatment (ZLD) | 90k – 240k | 3.0M – 8.0M | utilities CSV option row | | Stamper prep (Sibert VSP, VSF, VSC) | 60k – 170k | 1.9M – 5.7M | estimate, pricing unpublished (2021 specifications on file) | | Mastering and cutting room (Agnew or Sillitoe lathe system, cutter amps, console, room treatment) | 290k – 580k | 9.6M – 19.1M | estimate, bespoke market; the Sillitoe SDMS lists at USD 125k for lathe, head, amplifier and automation (ex tax, shipping), which makes the low end reachable; band kept until both quotes exist | | Metrology and QC stack (confocal, profiler, XRF, inline vision, audio station) | 350k – 810k | 11.5M – 26.7M | estimate, phaseable | | Utilities, solar, HVAC, racking baseline | 730k – 1,270k | 24.0M – 41.6M | reviewed [utilities CSV](utilities-investment.csv), THB-native | | Building ~1,500 m² plus civil works | 650k – 1,100k | 21.4M – 36.2M | estimate at 12,000–20,000 THB/m² Thai industrial construction plus ~20% site works | | Land 6–8 rai, if purchased | 360k – 970k | 12.0M – 32.0M | estimate at 2–4M THB/rai industrial; leasing cuts this to near zero upfront | | Traceability and factory software | 60k – 170k | 1.9M – 5.7M | estimate | | Freight, installation, training (non-Newbilt equipment) | 120k – 230k | 3.8M – 7.6M | estimate | | Working capital, PVC stock, spares | 120k – 230k | 3.8M – 7.6M | estimate | | Subtotal | ~4.1M – 7.7M | ~135M – 254M | | | Contingency 15% | ~0.6M – 1.2M | ~20M – 38M | | | **Total, full vision** | **~4.7M – 8.9M USD** | **~155M – 294M THB** | | ### Added scope, not yet in the roll-up Decided after the roll-up above was compiled; carried here as estimates until the next re-base folds them into the blocks (the building and software lines, and the contingency on top). | Block | USD | THB | Basis | |---|---|---|---| | Overhead crane, runway, frame premium, machine door | 97k – 227k | 3.2M – 7.5M | estimate, [crane, workshop and tours](../crane-workshop-tours.md) | | Maintenance workshop and machine bay fit-out | 30k – 76k | 1.0M – 2.5M | estimate, same | | Visitor corridor and accessible entrance | 67k – 148k | 2.2M – 4.9M | estimate, same | | Artist platform, public side (calculator, campaigns, payments) | 40k – 90k | 1.3M – 3.0M | estimate, [artist platform](../artist-platform.md) | | **Added so far** | **~235k – 540k** | **~7.7M – 17.9M** | about 6 to 7% on the full-vision subtotal | ## Phased entry A credible launch phase is far smaller, roughly **1.7M to 2.9M USD (~57M to 95M THB)**: - Newbilt Single system (not Duplex yet) - Bridge stampers from Stamper Discs, so no galvanics line at launch - Basic QC (microscope, benchtop PVC lab, sampled listening), full metrology deferred - Leased building instead of purchase, modest first solar array - Galvanics, automated presses, full metrology, and the biomass boiler follow as revenue-funded or second-round expansions The planning already supports this: the Duplex-ready hydraulics, the bridge-supplier role for Stamper Discs, the staged electric-to-biomass steam path, and the phaseable metrology stack are all documented for exactly this reason. ## What moves the number - **BOI**: machinery duty exemption applies across most of the equipment blocks, and the solar and automation spend converts into CIT-exemption headroom; the application precedes every purchase order (see [boi.md](../boi.md)) - **Buy vs lease** on land and building swings roughly **1.0M to 2.1M USD (~34M to 69M THB)** of upfront capital, and also moves the launch date by about three quarters — see [project-timeline.md](../project-timeline.md) - **Biggest uncertainty bands**: metrology (partly a choice of ambition), the mastering/cutting room (bespoke vendor, no public pricing), the automated presses (single unverified price point), and land - **Currency exposure is real and is not modelled here.** Revenue is mostly USD/EUR from export customers, the cost base is mostly THB, and the largest single equipment block is EUR-denominated and unhedged against an order that will not be placed for roughly a year (see [project-timeline.md](../project-timeline.md)). A 10% move in EUR/THB between now and the Newbilt order is worth ~USD 25–35k on that line alone. Ask for the re-quote to state its currency and validity period. - Every band narrows only with RFQs; the supplier map in [equipment-suppliers.md](../suppliers/equipment-suppliers.md) lists who to ask