grabowski 1f532d0c85 All-equity funding: shareholders fund the whole plant
Deploy test site / deploy (push) Successful in 1m0s
User, 20 Oct 2026: the plan is that the shareholders fund the whole
plant and get shares for that (no bank loan).

- total-investment.md "Two plans": Funding paragraph: Plan B's ~217M
  THB paid in as share capital; the lead investor's 60 % at least ~130M,
  the 40 % at most ~87M (~121M / ~81M before the reserve; Plan A ~109M /
  ~73M); capital registered in full and called in instalments against
  the tranches; BOI's 3:1 met with no debt; nothing pledged.
- boi.md, README Project Status and the share-price bullet follow.
- Business plan A and B: the ask, the decisions, section 12.2 (funding
  bullet replaces the 3:1 equity floor), section 14 and the BOI
  requirements paragraph; "not in this plan" now names bank debt; both
  rebuilt (63 pages, checked).
- share-price.md re-based: 2,170,000 shares of 100 THB, the 40 % ~86.8M
  THB; illustrative calls 25/40/20/15 % against the tranches; premium
  rows on 217M; value per share once running with no debt (adverse 11 to
  42 THB, central 80 to 314, favourable 176 to 688 per 100 THB paid);
  VC method and CAPM recomputed; the calculator's ~22 % IRR is now the
  shareholders' pre-tax return (~18 % after tax, rough); missed-call
  rules (CCC 1120 to 1125); the levered case kept as "if a loan were
  added later".
- Deck: slide 12 (all equity, 60/40 bar ~130M / ~87M, none pledged,
  share capital called in instalments), slide 13 (re-based table, chart,
  premium cards, VC line), slide 17 (co-investor card, calls) and notes
  ("lenders" -> "investors"); both PDFs rebuilt; deck verify clean.
2026-10-20 17:17:18 +07:00
grabowski c8307f9d5e Shareholding: main investor holds at least 60 %, 40 % for sale
User, 20 Oct 2026: the main investor W wants to hold at least 60 % of
the company (the BOI-promoted company), so only 40 % is for sale.

- total-investment.md "Two plans": the 60/40 rule; Ploy Printing's
  stake, founders' shares and any further co-investor come out of the
  40 %; at Plan B's ~54M THB equity floor (3:1) and one share price
  that is at least ~32M / at most ~22M THB (arithmetic only; share
  price, valuation and in-kind shares not agreed).
- README Project Status and boi.md (foreign-ownership privilege) point
  to it.
- Business plan: section 12.2 states the split (A: ~28M / ~18M, B:
  ~32M / ~22M at the equity floor, arithmetic), the co-investment bullet
  and the decisions list name the 40 %; A and B rebuilt (63 pages each,
  TOC and em-dash check clean).
2026-10-20 13:52:33 +07:00
grabowski 995bb4ba60 Plan B chosen; stale mirrors fixed; business plan rebuilt
User, 19 Oct 2026: the main investor wants to go with Plan B; fix the
stale docs the deck build found.

- total-investment.md "Two plans" and README: the main investor wants
  Plan B (~217M THB, labelled ~215M); Plan A stays as the comparison.
- boi.md: duty without BOI on the launch plant's ~2.3M USD of imported
  machinery (~0.11M duty, ~0.17M import VAT), as total-investment states;
  the calculator's ~2.5M includes the water treatment; the old ~2.75M
  was the superseded start fleet.
- roadmap.md item 2: the BOI application stacks automation, R&D and the
  battery if it qualifies; solar lost promotion on 1 July 2025.
- project-timeline.md: October re-read note (launch plant with
  galvanics commissioned first, long lease of raw land, Plan B price;
  calendar not redrawn); galvanics rows no longer "Phase 5".
- revenue-model.md: blended price at 60 % specials ~124 to 174 THB
  (3.76 to 5.27 USD), the Thai gap "three to six times".
- site-candidates.md, scale.md: utility yard with air-cooled chillers,
  no cooling tower; electroplating permission needed from the start.
- Business plan: working capital 4.5M to 9.6M THB (as total-investment);
  A and B docx and PDF rebuilt (63 pages each, TOC checked).
2026-10-20 13:26:28 +07:00
grabowski 984ced2485 Biomass steam in both plans, PV on the factory roof only
Deploy test site / deploy (push) Successful in 49s
User, 17 Oct 2026: "only put solar on the factory, prepare the other
buildings for solar, option a and b should operate on biomass".

- Steam: two 500 kg/h biomass modules (Getabec class, 6M to 10M THB) plus
  a fuel store and handling block (1M to 2M, estimate) in both plans; the
  electric bank becomes the alternative. ~0.67M THB of fuel a year against
  ~4.9M for electric steam; grid demand ~264 kW instead of ~980 kW.
- Solar: ~520 kWp on the factory roof (the biomass-case optimum is ~500 to
  550 kWp, hourly sketch in sustainability.md "PV size with biomass
  steam"); office roof and parking canopies built PV-ready (~120 kWp
  later). ~87 % used on site, ~61 % of the plant's electricity.
- Calculator: biomass default, bFuel row, pvKWp 520, pvSelf 87, iso fills
  the factory roof first and shows the other roofs as PV-ready.
- Numbers: launch plant ~168M / 232M / 296M with contingency; Plan A
  ~182M (~2M above 180M: the Chinese-route lever priced only electric
  boilers; a Chinese biomass quote is the way back), Plan B ~217M (label
  ~215M), ~35M more. Calculator EBITDA A 2.17M, B 2.23M USD.
- CSV, total-investment, revenue-model, sustainability, scale, biomass,
  site-candidates, boi, steam-cooling, construction RFQ (canopies
  PV-ready), README, roadmap; business plan draft 0.3 rebuilt (A and B
  63 pages) with new renders.
2026-10-17 20:24:55 +07:00
grabowski 9ff5feef11 Solar on every roof, BOI solar correction, open source section
Deploy test site / deploy (push) Successful in 54s
Solar (user, 17 Oct 2026: "use as much roof space as possible")
- PV on every roof and canopy: ~640 kWp on the Payap scenario plot
  (factory roof ~523, canopies ~54, flat office roof ~65 kWp around the
  AC units); ~300 kWp on the Mueang Chi hall. Calculator: pvKWp 640,
  new pvSelf 85 % (zero export, hourly sketch), PV cost per kWp times the
  array, office-roof PV in the iso view, roofs drawn full.
- 12.8M to 16.6M THB at 20 to 26 THB/W; CSV baseline 34.37M to 56.34M;
  launch plant ~168M / 231M / 294M THB with contingency; Plan B ~216M
  (label ~215M), ~39M above Plan A; Plan A unchanged (it leases the
  array), its solar lever ~17.5M. PV payback ~4.2 to 5.9 years.
- Permits (rooftop solar no factory licence since 28 Dec 2024, ERC
  exemption under 1,000 kVA, PEA zero export) and PPA discounts sourced
  in sustainability.md.

BOI correction
- Announcement 3/2568 (in force 1 July 2025) ended BOI promotion for
  solar installations; only the battery may qualify (12M THB per MW cap).
  Removed the "BOI solar measure" from boi.md, total-investment,
  revenue-model, sustainability, site-candidates and both plan versions;
  Plan B's case for owning the array is the PPA bill it avoids
  (~0.07M USD a year).

Open source (user, 17 Oct 2026)
- digital-factory.md "Open source throughout, and working with other
  plants": everything we run and build is open source on NixOS, our code
  published (licence to decide), vendor firmware the stated exception;
  later the stack and factory-automation services for other pressing
  plants, not in the revenue.
- Business plan section 5.6 plus an executive-summary bullet, reading
  guide and not-modelled mentions; draft 0.3 rebuilt (A 60, B 61 pages),
  renders re-made with the roofs full.
2026-10-17 17:22:57 +07:00
grabowski 8032e0ea47 BOI: machinery import duty and import VAT, PVC duty relief
Deploy test site / deploy (push) Successful in 35s
User, October 2026: take the BOI duty-free import and VAT exemption into
consideration.

- boi.md: import VAT goes with the BOI duty exemption (Revenue Department
  answer on the BOI OSOS FAQ, checked October 2026); what it is worth:
  ~2.75M USD of imported machinery at the start fleet (block midpoints)
  would otherwise carry ~5 % duty (Thai MFN averages 4.1 % on HS 8477,
  0 to 10 % across HS 84; estimate until the HS codes are set), ~0.14M
  USD, and 7 % import VAT, ~0.2M paid at the border and recovered later
  as input tax, mostly as a refund claim since exports are zero-rated.
- total-investment.md: the blocks are vendor prices without duty or
  import VAT, so the headline already assumes promotion.
- Fleet calculator: BOI promoted / not promoted switch and export share.
  Not promoted adds the machinery duty to capex and depreciation, shows the
  import VAT as cash at the border, and charges duty on imported PVC
  compound; promoted exempts both, with no compound duty on exported
  records and 90 % off for domestic sales (sections 36(1) and 30). A note
  under the KPIs shows what promotion saves either way. Defaults: payback
  3.1 years with BOI, 3.2 without; adverse case operating result -31k
  with BOI, -68k without. CIT and BOI CIT exemptions still not modelled.
2026-10-10 20:29:32 +07:00
grabowski ffbc46782a Add the Payap University partnership: joint student programmes
Payap also wants to work closely with the project on new student
programmes: audio engineering (mastering, lathe cutting), IT, business
administration and more.

New docs/payap-partnership.md: why it fits (mastering/cutting engineers
are the hardest hires; Payap has music, IT, business, communication arts,
an English-language International College and pharmacy labs; the plant has
a lathe, production data and a real factory application), programme areas
mapped to the docs they draw on, and what it changes: a reason to bring
the cutting room (roadmap item 27) forward, a cutting engineer before the
students, lacquer and stylus cost of teaching, pre-release security for
customer audio, student access and safety, IT work on staging only, the
link to the Payap land, BOI R&D merit. Suggested form: MOU, internships,
short certificate courses first, degree tracks later; what to settle in
writing and questions for the next meeting.

Links from README (bullet, layout), site-candidates, roadmap item 27, the
supplier map's open training item and the BOI open items.
2026-10-03 21:36:17 +02:00
grabowski b2ab630231 Add BOI investment promotion strategy
Group B base activity (plastics) with non-tax package and machinery duty
exemption; CIT value engineered via solar/BESS, smart-and-sustainable
automation, and R&D merit measures; NEC/Lamphun regional angle; BOI
approval sequenced ahead of incorporation and machinery orders