Press fleet: two Newbilt Duplex systems with an extruder per press, plus a Classic
The current plan (user decision, October 2026) replaces the 50/50 target (two semi-automatic presses and two Pheenix AD12s) with an all-Newbilt fleet of five presses: two Duplex systems in Newbilt's two-extruder configuration (two HRP 12 presses, an extruder each, one hydraulic unit) and one Classic fully automatic press. - pressing-line.md: new "Current plan" section (fleet table, what it means, phasing from the Single 2.1 as the first half of system 1, re-quote questions); site requirements per Duplex system. - scale.md: capacity table and basis (368 to 448 records/h, ~1.06 to 1.5M a year on two shifts, same range as before); pressing electrical row; steam and cooling flagged, not re-based: five presses draw ~750 to 900 kg/h of steam and up to ~625 kW of cooling at Newbilt's per-press figures, against the 400 kg/h / 250 kW sized for one Duplex. - total-investment.md: fleet change as an added-scope row (system 2 ~230k-300k and the Classic ~290k-460k, estimates; -60k / -160k against the two blocks it replaces); headline unchanged until the re-base. - roadmap items 4, 5 and 24, revenue model mature row, crane doc (the Classic's weight now decides 5 t or 3.2 t), vendor landscape (AD12 is the comparison for the Classic), README. The business plan docx is not regenerated.
This commit is contained in:
1 parent
f1334f4756
commit
c50417668b
8 files changed
+128
-48
No files matched your search
+9
-5
@@ -40,12 +40,15 @@ These three run in parallel and gate everything downstream:
|
||||
|
||||
## Phase 1: Quotes and site (parallel with the BOI decision window)
|
||||
|
||||
4. **Newbilt re-quote** (2024 offer expired), with PLC/data access as a
|
||||
4. **Newbilt re-quote** (2024 offer expired) for the current fleet: the
|
||||
two-extruder Duplex as the Single 2.1 upgrade and as a second system,
|
||||
the Classic automatic press, and a central hydraulic supply option
|
||||
([pressing line](equipment/pressing-line.md)), with PLC/data access as a
|
||||
stated purchasing requirement per the
|
||||
[traceability spec](traceability.md)
|
||||
5. **Pheenix Alpha**: current metric datasheet and quotes for the AD12 and
|
||||
AD12 Manual, evaluating the single-vendor option against Newbilt for
|
||||
the semi-auto half. After Haarlem the CEO offered a Teams call,
|
||||
5. **Pheenix Alpha**: the AD12 left the current fleet plan in October
|
||||
2026 (an all-Newbilt fleet); Pheenix stays the comparison for the
|
||||
Classic and a galvanics candidate (item 6). After Haarlem the CEO offered a Teams call,
|
||||
reference clients and a factory visit near Stockholm; the call follows
|
||||
once our questions are ready, and the next Europe trip is planned
|
||||
for February 2027 ([exhibitor briefing](suppliers/making-vinyl-europe-2026-exhibitors.md#after-the-show))
|
||||
@@ -140,7 +143,8 @@ These three run in parallel and gate everything downstream:
|
||||
before every manufacturing step is in place
|
||||
([exhibitor briefing](suppliers/making-vinyl-europe-2026-exhibitors.md#after-the-show));
|
||||
supplier advice to weigh against the market evidence, not a decision
|
||||
24. Automated press line (the 50/50 fleet target)
|
||||
24. Second Duplex system and the Newbilt Classic automatic press, which
|
||||
complete the five-press fleet ([pressing line](equipment/pressing-line.md))
|
||||
25. Full metrology stack and the sampled audio QC station
|
||||
26. Biomass boiler, fed by the by-then-mature coppice plus regional fuel
|
||||
27. Mastering and cutting room (can move earlier if title-services demand
|
||||
|
||||