Launch plant roll-up and the investor's 180M THB question
Decided (user, October 2026): the plant launches with everything in one capital round, commissioned in sequence: one Newbilt Duplex system, one Classic, a Pheenix galvanics line with ZLD water, the Sibert line, a Sillitoe cutting room, and the modular steam and cooling plant (2 x 500 kg/h boilers, 2 x 250 kW chillers, rooms for four each). No bridge stampers, no outsourced cutting; cassette and CD-R stay; the second Duplex and further Classics are growth options, not in the investment. total-investment.md: new 'Launch plant' roll-up, 4.9M to 8.9M USD, 161M to 292M THB incl. 15 % contingency (midpoint ~227M), with what is left out (ramp-up reserve ~10-20M THB, CD replication, financing, FX, archive shelving) and the BOI assumption. The investor's question (180M THB, maybe +20 % = 216M): fits at the low end only; at the midpoint four levers that keep every machine (solar via PPA, metrology launch tier, galvanics near OMS's reference, visitor corridor later) give ~193M, plus reserve ~203-213M, inside 216M; 180M needs low quotes. The quotes that decide it: Newbilt (Duplex, Classic), Pheenix galvanics, building with soil test, metrology. Old full vision and phased entry marked superseded until the mirrors are re-based. Utilities CSV: chiller bank two modules (4.9-7.9M THB), boiler note for B-1 and B-2 at launch, ZLD and DI rows now launch scope (carried with galvanics); baseline 28.47M-48.73M THB. README project status.
This commit is contained in:
1 parent
07ef9c0b9a
commit
553b4a93d1
3 files changed
+125
-10
No files matched your search
@@ -12,7 +12,111 @@ wherever they appear next to their source document, and converted here at
|
||||
July 2026; the underlying THB estimates are unchanged, because EUR/THB at
|
||||
~38 is where it was when they were made.
|
||||
|
||||
## Full vision, all blocks
|
||||
## Launch plant (October 2026)
|
||||
|
||||
Decided (user, October 2026): the plant launches **with everything in one
|
||||
capital round**, commissioned in sequence, with no bridge stampers and no
|
||||
outsourced cutting:
|
||||
|
||||
- one **Newbilt Duplex** system: two HRP 12 semi-automatic presses, an
|
||||
EX 50 main and an EX 35 colour extruder
|
||||
([pressing line](../equipment/pressing-line.md));
|
||||
- one **Newbilt Classic** fully automatic press;
|
||||
- one **Pheenix Alpha** galvanics line (PASU, PPPU, one PDPU, PMPB) with
|
||||
zero-discharge water treatment
|
||||
([galvanics and stamper prep](../equipment/galvanics.md));
|
||||
- the **Sibert** stamper-prep line (VSF, VSP, VSC);
|
||||
- a **Sillitoe SDMS** cutting room
|
||||
([vendor landscape](../suppliers/vendor-landscape.md#mastering-and-cutting-sillitoe-audio-technology-australia));
|
||||
- the **modular steam and cooling plant**: two 500 kg/h boiler modules and
|
||||
two 250 kW chiller modules, in a boiler hall and a chiller compound
|
||||
built for four each ([scale](../scale.md#utility-phasing-backbone-once-modules-with-the-presses)).
|
||||
|
||||
Cassette and CD-R duplication stay in. The second Duplex system and the
|
||||
further Classics are growth options with room reserved, not in this
|
||||
investment. Three presses make roughly 0.7 to 0.95 million records a year
|
||||
on two shifts (estimate: the [scale](../scale.md) basis gives ~0.71 to
|
||||
0.97 million, the planning rates of the
|
||||
[fleet calculator](../fleet-calculator.html) ~0.94 million).
|
||||
|
||||
| Block | USD | THB | Basis |
|
||||
|---|---|---|---|
|
||||
| Phase 0: BOI consultant, legal and lease work, soil test, re-quotes | 40k – 80k | 1.3M – 2.6M | estimate |
|
||||
| Newbilt Duplex system (two HRP 12, EX 50 + EX 35, trimmer, label oven, shrink wrapper, grinder, label punch) | 350k – 370k | 11.6M – 12.2M | 2024 quote EUR 200,500 for the Single 2.1 plus the quoted second press and extruder ~USD 115k; expired, re-quote |
|
||||
| Newbilt Classic | 290k – 460k | 9.6M – 15.2M | placeholder (the old AD12 band per press); **no Newbilt price on file** |
|
||||
| Pheenix galvanics line (PASU, PPPU, PDPU, PMPB) | 320k – 650k | 10.6M – 21.4M | estimate; **no Pheenix price on file**; OMS's reference prices for a 4-cell wet room (EUR 224k to 311k, ~USD 259k to 359k) sit at the low end |
|
||||
| Galvanics water: ZLD evaporator and DI water | 97k – 258k | 3.2M – 8.5M | [utilities CSV](utilities-investment.csv) rows, now launch scope |
|
||||
| Water-treatment building next to galvanics (~12 × 10 m, proposed) | 52k – 87k | 1.7M – 2.9M | estimate at the building rate below |
|
||||
| Sibert VSF, VSP, VSC | 250k | 8.3M | Sibert's budget confirmation, 5 October 2026; its time, spares, shipping and travel in the freight and working-capital lines |
|
||||
| Cutting room: Sillitoe SDMS, spare cutterhead and support, mastering console and chain, monitoring, room build-out | 200k – 350k | 6.6M – 11.6M | SDMS list price USD 125k (ex tax and shipping); the rest estimate |
|
||||
| Metrology and QC stack (XRF, laser confocal, wide-area profiler, inline vision on three presses, audio station) | 350k – 810k | 11.6M – 26.7M | estimate, phaseable ([quality automation](../quality-automation.md)) |
|
||||
| PVC lab, day-one tier | 55k – 150k | 1.8M – 5.0M | estimate, [quality automation](../quality-automation.md) |
|
||||
| Utilities, solar, battery, HVAC, clean zones, racking | 863k – 1,477k | 28.5M – 48.7M | [utilities CSV](utilities-investment.csv) baseline re-sized for three presses: chiller bank two modules instead of three |
|
||||
| Building ~1,500 m² plus civil and site works | 650k – 1,100k | 21.4M – 36.3M | estimate at 12,000 – 20,000 THB/m² plus ~20 % site works; soil is the main variable |
|
||||
| Overhead crane, runway, frame premium, machine door | 97k – 227k | 3.2M – 7.5M | estimate, [crane, workshop and tours](../crane-workshop-tours.md) |
|
||||
| Maintenance workshop and machine bay fit-out | 30k – 76k | 1.0M – 2.5M | estimate, same |
|
||||
| Visitor corridor and accessible entrance | 67k – 148k | 2.2M – 4.9M | estimate, same |
|
||||
| Utility yard built for four boiler and four chiller modules | 73k – 122k | 2.4M – 4.0M | estimate, [scale](../scale.md#detached-utility-yard-parking-and-what-that-moves) |
|
||||
| Factory software, ERPNext, artist platform public side | 115k – 310k | 3.8M – 10.2M | estimate: factory software 60k – 170k, ERPNext implementation 15k – 50k ([digital factory](../digital-factory.md#erpnext-the-plants-erp)), artist platform 40k – 90k ([artist platform](../artist-platform.md)) |
|
||||
| Cassette duplication and CD-R duplication | 55k – 190k | 1.8M – 6.3M | estimate, business plan sections 4.8 and 4.9 |
|
||||
| Freight, installation, commissioning, training (Pheenix, Sibert, Sillitoe, Newbilt beyond its quoted 5 days) | 150k – 300k | 5.0M – 9.9M | estimate |
|
||||
| Working capital, PVC stock, spares, lease deposit, first-year rent | 135k – 290k | 4.5M – 9.6M | estimate; land is leased, so no land purchase |
|
||||
| Subtotal | ~4.24M – 7.71M | ~140M – 254M | |
|
||||
| Contingency 15 % | ~0.64M – 1.16M | ~21M – 38M | |
|
||||
| **Total, launch plant** | **~4.9M – 8.9M USD** | **~161M – 292M THB** | midpoint ~6.9M USD, ~227M THB |
|
||||
|
||||
Not in the total: a **reserve for the ramp-up** (staff hired before first
|
||||
revenue, overheads until volume covers them; ~10M to 20M THB, estimate),
|
||||
CD replication, financing costs, currency moves, and the archive's mobile
|
||||
shelving (to quote). The blocks are vendor prices without Thai duty or
|
||||
import VAT, so they assume BOI promotion: without it, ~5 % duty on ~2.3M
|
||||
USD of imported machinery (~0.11M USD) comes on top, plus ~0.17M USD of
|
||||
import VAT paid at the border and reclaimed later (estimates).
|
||||
|
||||
### The investor's question: 180M THB, maybe 20 % more (October 2026)
|
||||
|
||||
The project's investor asked whether the plant can be built for **180M
|
||||
THB (~5.45M USD), possibly up to 20 % more (216M THB, ~6.55M USD)**.
|
||||
|
||||
| Case | Launch plant | Against 180M | Against 216M |
|
||||
|---|---|---|---|
|
||||
| Low end of every block | ~161M THB | fits, ~19M to spare | fits |
|
||||
| Midpoint | ~227M THB | ~47M over | ~11M over |
|
||||
| High end of every block | ~292M THB | ~112M over | ~76M over |
|
||||
|
||||
**Read honestly: 216M THB is a realistic target for the full equipment
|
||||
list; 180M THB holds only if the open quotes land low.** At the midpoint
|
||||
four levers bring the plant inside 216M without dropping any of the
|
||||
machines decided above (midpoint values with their share of the
|
||||
contingency, estimates):
|
||||
|
||||
| Lever | Saves | Launch plant after it |
|
||||
|---|---|---|
|
||||
| Rooftop solar and battery through a solar PPA (the EPC owns and finances the array, the plant buys the power) instead of buying them | ~12.3M THB | ~214M THB |
|
||||
| Metrology launch tier (XRF, inline vision, audio station), the laser confocal and the wide-area profiler bought from revenue | ~10.1M THB | ~204M THB |
|
||||
| Pheenix galvanics priced near OMS's reference for a 4-cell wet room | ~6.7M THB | ~198M THB |
|
||||
| Visitor corridor built later; the plant runs without public tours at first | ~4.1M THB | ~193M THB |
|
||||
|
||||
Add the ramp-up reserve of ~10M to 20M THB and that is **~203M to 213M
|
||||
THB, inside the 216M**. Reaching 180M at the midpoint needs scope cuts on
|
||||
top: cassette and CD-R later (~4.6M THB) and renting a crane for the
|
||||
installations while the frame stays crane-ready (~3.7M THB) give ~185M
|
||||
before the reserve, still above 180M, so 180M is a low-quote outcome, not
|
||||
a plan.
|
||||
|
||||
What decides it: the two largest machine lines have no price at all (the
|
||||
Classic and the Pheenix galvanics line), and the building depends on the
|
||||
soil. Four requests settle most of the band: the Newbilt re-quote for the
|
||||
Duplex and the Classic, a Pheenix quote for the galvanics line, the
|
||||
building RFQ with a soil test, and distributor quotes for the metrology
|
||||
stack. Until they are in, quote **~216M THB** to the investor as the
|
||||
target with the levers above, and 180M as the low-quote case.
|
||||
|
||||
## Full vision, all blocks (July 2026, superseded)
|
||||
|
||||
The five-press full vision below is superseded by the launch plant above.
|
||||
It stays until the documents that quote its 4.7M to 8.9M USD total (README,
|
||||
roadmap, revenue model, business plan) are re-based on the launch plant.
|
||||
|
||||
| Block | USD | THB | Basis |
|
||||
|---|---|---|---|
|
||||
@@ -54,10 +158,12 @@ building, software and stamper prep lines, and the contingency on top).
|
||||
| Archive mobile shelving for the father and mother archive (October 2026) | to quote | to quote | not in the sum: A-Z Solutions publishes no prices; quote it and a Thai supplier ([facility security](../facility-security.md#archive-room-mobile-shelving)) |
|
||||
| **Added so far** | **~678k – 1,027k** | **~22.3M – 33.9M** | about 13 to 17% on the full-vision subtotal |
|
||||
|
||||
## Phased entry
|
||||
## Phased entry (superseded October 2026)
|
||||
|
||||
A credible launch phase is far smaller, roughly **1.7M to 2.9M USD
|
||||
(~57M to 95M THB)**:
|
||||
Superseded by the launch plant above, which launches with galvanics, the
|
||||
cutting room and three presses. The earlier phased entry, kept for
|
||||
reference: a launch phase of roughly **1.7M to 2.9M USD (~57M to 95M
|
||||
THB)**:
|
||||
|
||||
- Newbilt Single system (not Duplex yet)
|
||||
- Bridge stampers from Stamper Discs, so no galvanics line at launch
|
||||
@@ -85,7 +191,7 @@ exactly this reason.
|
||||
start fleet (estimate)
|
||||
- **Buy vs lease** on land and building swings roughly **1.0M to 2.1M
|
||||
USD (~34M to 69M THB)** of upfront capital, and also moves the launch
|
||||
date by about three quarters — see
|
||||
date by about three quarters; see
|
||||
[project-timeline.md](../project-timeline.md)
|
||||
- **Biggest uncertainty bands**: metrology (partly a choice of ambition),
|
||||
the mastering/cutting room (bespoke vendor, no public pricing), the
|
||||
|
||||