Biomass: reported northern fuel prices (October 2026)
No public price index exists; DEDE lists buyers, not prices. Reported market prices: fresh chips 1,350-1,800 THB/t (LH Bank, Mar 2026), rubberwood firewood >1 THB/kg farm gate (OIE RIU 2026, doubled since late 2025), corn residue 2 THB/kg (Sunsweet, Mae Chaem), rice husk ~1.5 THB/kg, pellets 3,000-5,000 THB/t. Planning price 1.35-2 THB/kg delivered, so the mature fuel bill is ~0.6M-1.2M THB/yr (was 0.35M-0.8M): still a quarter to a tenth of electric steam. Prices follow diesel; Ratch Pathana's Pa Sak (Lamphun) buying centre is the local price-setter. Sources filed under docs/finance/biomass/; sustainability.md and README follow.
This commit is contained in:
1 parent
9640a4f075
commit
47e5f9e458
5 files changed
+79
-18
No files matched your search
@@ -90,15 +90,15 @@ The detail lives in dedicated documents:
|
|||||||
the full needs list per production step with supplier tables and contacts
|
the full needs list per production step with supplier tables and contacts
|
||||||
- [Sustainability](docs/sustainability.md): the solar installation (Deye
|
- [Sustainability](docs/sustainability.md): the solar installation (Deye
|
||||||
inverters, 271 kWh Gobel Power battery stack), the PEA grid tariff and
|
inverters, 271 kWh Gobel Power battery stack), the PEA grid tariff and
|
||||||
what it decides (biomass steam at about a tenth of the cost of electric,
|
what it decides (biomass steam at a quarter to a tenth of the cost of
|
||||||
PV rather than solar thermal), the zero contaminated water commitment,
|
electric, PV rather than solar thermal), the zero contaminated water commitment,
|
||||||
and the materials strategy
|
and the materials strategy
|
||||||
- [Worker safety](docs/worker-safety.md): safety training, galvanics clean
|
- [Worker safety](docs/worker-safety.md): safety training, galvanics clean
|
||||||
rooms and decontamination, PPE
|
rooms and decontamination, PPE
|
||||||
- [Biomass fuel strategy](docs/biomass.md): the 60 rai own-grown coppice
|
- [Biomass fuel strategy](docs/biomass.md): the 60 rai own-grown coppice
|
||||||
idea (with the forestry-classification check that comes first), northern
|
idea (with the forestry-classification check that comes first), northern
|
||||||
agricultural waste as the main supply, and the staged electric-to-biomass
|
agricultural waste as the main supply, reported northern fuel prices
|
||||||
path
|
(October 2026) and who sets them, and the staged electric-to-biomass path
|
||||||
- [BOI investment promotion](docs/boi.md): the promotion strategy (Group B
|
- [BOI investment promotion](docs/boi.md): the promotion strategy (Group B
|
||||||
base activity plus solar, automation, and R&D measures for the tax value),
|
base activity plus solar, automation, and R&D measures for the tax value),
|
||||||
requirements, Northern-region angle, and why BOI approval precedes
|
requirements, Northern-region angle, and why BOI approval precedes
|
||||||
@@ -208,7 +208,8 @@ docs/
|
|||||||
│ └── pressing-line.md Press fleet strategy and equipment plan
|
│ └── pressing-line.md Press fleet strategy and equipment plan
|
||||||
├── finance/ Project cost overviews, revenue model,
|
├── finance/ Project cost overviews, revenue model,
|
||||||
│ construction RFQ, PEA electricity tariff
|
│ construction RFQ, PEA electricity tariff
|
||||||
│ schedule (pea/)
|
│ schedule (pea/), biomass fuel market
|
||||||
|
│ reports (biomass/)
|
||||||
├── suppliers/ Supplier contacts, vendor landscape, supplier map
|
├── suppliers/ Supplier contacts, vendor landscape, supplier map
|
||||||
├── artist-platform.md Upload, price calculator, fan-funded pressing
|
├── artist-platform.md Upload, price calculator, fan-funded pressing
|
||||||
├── biomass.md Biomass fuel strategy and the 60 rai coppice idea
|
├── biomass.md Biomass fuel strategy and the 60 rai coppice idea
|
||||||
|
|||||||
+64
-5
@@ -18,6 +18,9 @@ recovery architecture trimming the load and realistic duty cycles:
|
|||||||
efficiency and ~4 kWh/kg air-dry wood)
|
efficiency and ~4 kWh/kg air-dry wood)
|
||||||
- Early operations (one press line, single shift): roughly a quarter of
|
- Early operations (one press line, single shift): roughly a quarter of
|
||||||
that, **~90 to 100 t/yr**
|
that, **~90 to 100 t/yr**
|
||||||
|
- Bought as fresh wood chips (~45 % moisture, ~2.6 kWh/kg) the same heat
|
||||||
|
is **~540 to 620 t/yr**, which is what the fuel store and the monsoon
|
||||||
|
stock have to be sized for (estimate)
|
||||||
|
|
||||||
## The 60 rai: own-grown fuelwood
|
## The 60 rai: own-grown fuelwood
|
||||||
|
|
||||||
@@ -32,7 +35,9 @@ about **80 to 135 t/yr**:
|
|||||||
|
|
||||||
That makes the land a meaningful supplement and a strong brand story
|
That makes the land a meaningful supplement and a strong brand story
|
||||||
("records pressed with steam from our own trees"), not a complete fuel
|
("records pressed with steam from our own trees"), not a complete fuel
|
||||||
supply.
|
supply. At the market prices below, 80 to 135 t of air-dry wood is worth
|
||||||
|
only ~0.1M to 0.25M THB a year (estimate): the land's value is supply
|
||||||
|
security and the story, not the fuel bill.
|
||||||
|
|
||||||
### The classification check comes first
|
### The classification check comes first
|
||||||
|
|
||||||
@@ -62,6 +67,60 @@ The region fills the remainder easily and cheaply:
|
|||||||
- Buying from local farmers also strengthens the local-sourcing story that
|
- Buying from local farmers also strengthens the local-sourcing story that
|
||||||
already runs through packaging and PVC
|
already runs through packaging and PVC
|
||||||
|
|
||||||
|
## Fuel prices (market check, October 2026)
|
||||||
|
|
||||||
|
There is no public price index for biomass fuel in northern Thailand. DEDE
|
||||||
|
publishes lists of buyers and sellers (February 2026: 42 registered buyers
|
||||||
|
wanting 2.09M t a year), not prices, so the figures below are reported
|
||||||
|
market prices from bank research, a government industry unit and the
|
||||||
|
press, all checked 7 October 2026. None is a quote to this plant.
|
||||||
|
|
||||||
|
| Fuel | Reported price | Source | Heat cost (estimate) |
|
||||||
|
|---|---|---|---|
|
||||||
|
| Wood chips, fresh (45 to 50 % moisture) | 1,350 to 1,800 THB/t delivered | [LH Bank Research, wood pellet outlook](finance/biomass/LHBank_Wood_Pellets_Industry_Outlook_2026-03.pdf), 9 March 2026: 1,700 to 1,800 THB per fresh tonne for export; a power-plant chip quota in Nakhon Ratchasima at 1,350 THB/t, at most 45 % moisture (undated trader post) | ~0.65 to 0.85 THB/kWh |
|
||||||
|
| Firewood and rubberwood offcuts, air-dry | over 1 THB/kg at the farm gate, up from 0.55 to 0.70 before late 2025 | [OIE Rubber Intelligence Unit](https://rubber.oie.go.th/Article.aspx?id=66365), 2026; southern rubber belt, so chipping and haulage to Lamphun come on top | ~0.3 to 0.5 THB/kWh before chipping and haulage |
|
||||||
|
| Corn cobs and stalk residue | 2 THB/kg, bought from farmers in Mae Chaem (Chiang Mai) | Sunsweet's "no burning, we buy" programme, [Prachachat](https://www.prachachat.net/economic/local-economy/news-1498508), February 2024; an incentive price set to stop field burning | ~0.6 THB/kWh |
|
||||||
|
| Rice husk | ~1.5 THB/kg at past demand peaks | [FTI renewable energy group](https://re-fti.org/%E0%B9%84%E0%B8%9F%E0%B8%9F%E0%B9%89%E0%B8%B2%E0%B8%8A%E0%B8%B5%E0%B8%A7%E0%B8%A1%E0%B8%A7%E0%B8%A5%E0%B8%A3%E0%B8%B0%E0%B8%AA%E0%B9%88%E0%B8%B3%E0%B8%A3%E0%B8%B2%E0%B8%84%E0%B8%B2%E0%B9%81%E0%B8%81%E0%B8%A5%E0%B8%9A%E0%B8%9E%E0%B8%B8%E0%B9%88%E0%B8%87/) (undated); power plants compete for it and northern milling volumes are small | ~0.5 THB/kWh |
|
||||||
|
| Wood pellets, domestic | 3,000 to 5,000 THB/t | LH Bank Research, March 2026; export FOB averaged 4,482 THB/t in 2025 | ~0.75 to 1.25 THB/kWh |
|
||||||
|
|
||||||
|
Heat cost assumes an 80 % boiler (85 % on pellets) and ~2.6 kWh/kg for
|
||||||
|
fresh chips, ~4 for air-dry wood, ~4.2 for corn cobs, ~3.75 for rice husk
|
||||||
|
and ~4.7 for pellets (estimates).
|
||||||
|
|
||||||
|
What it means for the plan:
|
||||||
|
|
||||||
|
- **Planning price: 1.35 to 2 THB/kg delivered**, which is ~0.5 to 0.9 THB
|
||||||
|
per kWh of heat. The earlier assumption of 1 to 2 THB/kg of air-dry wood
|
||||||
|
(~0.3 to 0.6 THB/kWh) was too low at the bottom: the cheap end is
|
||||||
|
farm-gate wood, not chipped fuel at the plant gate. At maturity the fuel
|
||||||
|
bill is **~0.6M to 1.2M THB a year** (~0.15M to 0.3M early), still a
|
||||||
|
quarter to a tenth of electric steam (see
|
||||||
|
[grid tariff](sustainability.md#grid-tariff-pea-and-what-it-decides))
|
||||||
|
- **Prices are rising and follow diesel.** With diesel near 40 THB/L in
|
||||||
|
2026, chip traders feeding power plants parked trucks and cut purchases
|
||||||
|
([Thai Post](https://www.thaipost.net/district-news/971839/), 30 March
|
||||||
|
2026), and rubberwood firewood roughly doubled since late 2025. Haulage
|
||||||
|
is a large share of a delivered tonne, so source within ~50 km and write
|
||||||
|
a diesel clause into the fuel contract rather than a fixed price
|
||||||
|
- **Supply is not the constraint.** Lamphun alone produces more than
|
||||||
|
900,000 t of farm residues a year (Maejo University, via
|
||||||
|
[ThaiPublica](https://thaipublica.org/2026/08/lamphun-reduce-pm2-5-agricultural-waste-biomass-fuel/),
|
||||||
|
August 2026) against the plant's ~600 t. Buying them also counts against
|
||||||
|
the burning season, which is part of the story
|
||||||
|
- **The local price-setter is in Mueang Lamphun.** Ratch Pathana's
|
||||||
|
[biomass buying centre](https://www.ratchpathana.com/th/our-businesses/related-and-other-businesses/biomass-business)
|
||||||
|
at Pa Sak, Mueang Lamphun, buys wood waste, sawdust and corn cobs from
|
||||||
|
farmers for Saha Cogen Green's 9.6 MW, 25 t/h steam cogeneration plant
|
||||||
|
in the Saha Group Lamphun industrial park. It is the reference price to
|
||||||
|
ask for and the main competitor for the same fuel. Further out, Clover
|
||||||
|
Power at Wang Chin (Phrae) buys chips, corn husks and cobs, and bamboo
|
||||||
|
([DEDE buyer list](finance/biomass/DEDE_biomass_buyers_2026-02.pdf),
|
||||||
|
February 2026)
|
||||||
|
- **Next step:** written quotes from the Pa Sak centre and two or three
|
||||||
|
chip suppliers within 50 km, priced by moisture content (an oven-dry
|
||||||
|
tonne carries roughly twice the heat of a fresh one), before the boiler
|
||||||
|
decision
|
||||||
|
|
||||||
## Logistics on site
|
## Logistics on site
|
||||||
|
|
||||||
To reflect in the facility planning: a fuel storage shed (biomass
|
To reflect in the facility planning: a fuel storage shed (biomass
|
||||||
@@ -82,8 +141,8 @@ storage are additional.
|
|||||||
- The electric boiler remains the alternative: cleanest permitting, no fuel
|
- The electric boiler remains the alternative: cleanest permitting, no fuel
|
||||||
logistics, but effectively grid-powered steam at a ~300 kW draw. On
|
logistics, but effectively grid-powered steam at a ~300 kW draw. On
|
||||||
PEA's time-of-use tariff that costs ~4.7M to 5.5M THB a year at mature
|
PEA's time-of-use tariff that costs ~4.7M to 5.5M THB a year at mature
|
||||||
load against ~0.35M to 0.8M of fuel for biomass, and ~1.4M to 1.7M
|
load against ~0.6M to 1.2M of fuel for biomass, and ~1.4M to 1.7M
|
||||||
against ~0.1M to 0.2M at early load, because the demand charge follows
|
against ~0.15M to 0.3M at early load, because the demand charge follows
|
||||||
the boiler's full-power draw (estimates; see the
|
the boiler's full-power draw (estimates; see the
|
||||||
[grid tariff](sustainability.md#grid-tariff-pea-and-what-it-decides)).
|
[grid tariff](sustainability.md#grid-tariff-pea-and-what-it-decides)).
|
||||||
The electric boiler is the more efficient machine; biomass is the far
|
The electric boiler is the more efficient machine; biomass is the far
|
||||||
@@ -92,6 +151,6 @@ storage are additional.
|
|||||||
the coppice now (first harvest in 2 to 4 years), and add the biomass
|
the coppice now (first harvest in 2 to 4 years), and add the biomass
|
||||||
boiler at the automated-line expansion when demand and the fuel supply
|
boiler at the automated-line expansion when demand and the fuel supply
|
||||||
have both matured. At the tariff above that is a permitting and logistics
|
have both matured. At the tariff above that is a permitting and logistics
|
||||||
choice, not a cost one: every year on electric steam costs roughly 1.2M
|
choice, not a cost one: every year on electric steam costs roughly 1.1M
|
||||||
to 5M THB more than biomass, so the switch should come as soon as the
|
to 4.9M THB more than biomass, so the switch should come as soon as the
|
||||||
permit and a fuel contract are in place
|
permit and a fuel contract are in place
|
||||||
Binary file not shown.
Binary file not shown.
@@ -37,8 +37,9 @@ at 10 bar / 180 °C) and the 250 kW cooling system.
|
|||||||
abundant fuel); solar-thermal pre-heating of boiler feedwater was
|
abundant fuel); solar-thermal pre-heating of boiler feedwater was
|
||||||
considered and is not recommended. No technology choice has been made
|
considered and is not recommended. No technology choice has been made
|
||||||
yet; it will be driven by honest numbers on load profiles, storage, and
|
yet; it will be driven by honest numbers on load profiles, storage, and
|
||||||
grid backup, not by what sounds greenest. At PEA's tariff, biomass heat
|
grid backup, not by what sounds greenest. At PEA's tariff and current
|
||||||
costs about a tenth of electric steam
|
northern fuel prices, biomass heat costs a quarter to a tenth of electric
|
||||||
|
steam
|
||||||
([grid tariff](#grid-tariff-pea-and-what-it-decides)).
|
([grid tariff](#grid-tariff-pea-and-what-it-decides)).
|
||||||
- Whole-factory HVAC (continuous temperature, humidity, and PM control, see
|
- Whole-factory HVAC (continuous temperature, humidity, and PM control, see
|
||||||
[facility systems](facility-security.md)) adds a major tropical-climate
|
[facility systems](facility-security.md)) adds a major tropical-climate
|
||||||
@@ -202,16 +203,16 @@ solar, 0.5M to 0.7M of it demand charge (estimate).
|
|||||||
|
|
||||||
| | Electric boiler (~98 %) | Biomass boiler (~80 %) |
|
| | Electric boiler (~98 %) | Biomass boiler (~80 %) |
|
||||||
|---|---|---|
|
|---|---|---|
|
||||||
| Price of heat | ~3.9 THB/kWh, plus the demand charge | ~0.3 to 0.6 THB/kWh at 1 to 2 THB/kg of fuel (fuel price not yet checked with local suppliers) |
|
| Price of heat | ~3.9 THB/kWh, plus the demand charge | ~0.5 to 0.9 THB/kWh at 1.35 to 2 THB/kg delivered ([reported market prices](biomass.md#fuel-prices-market-check-october-2026), October 2026; no supplier quote yet) |
|
||||||
| Running cost, mature two shifts | **~4.7M to 5.5M THB/yr**: 1,140 to 1,310 MWh plus 200 to 300 kW of extra peak demand (0.3M to 0.5M) | **~0.35M to 0.8M THB/yr** of fuel, plus fuel handling and ash |
|
| Running cost, mature two shifts | **~4.7M to 5.5M THB/yr**: 1,140 to 1,310 MWh plus 200 to 300 kW of extra peak demand (0.3M to 0.5M) | **~0.6M to 1.2M THB/yr** of fuel, plus fuel handling and ash |
|
||||||
| Boiler package ([utilities CSV](finance/utilities-investment.csv)) | 2.5M to 4M THB | 4M to 7M THB, plus the fuel store |
|
| Boiler package ([utilities CSV](finance/utilities-investment.csv)) | 2.5M to 4M THB | 4M to 7M THB, plus the fuel store |
|
||||||
| Grid | peak demand 600 to 750 kW: bigger transformer and deposit | unchanged |
|
| Grid | peak demand 600 to 750 kW: bigger transformer and deposit | unchanged |
|
||||||
|
|
||||||
The electric boiler is the more efficient machine; biomass is by far the
|
The electric boiler is the more efficient machine; biomass is by far the
|
||||||
cheaper heat. At maturity the fuel saving of ~4M to 5M THB a year repays
|
cheaper heat. At maturity the fuel saving of ~3.5M to 4.9M THB a year
|
||||||
the biomass premium in about a year (estimate). Even early, at a quarter of
|
repays the biomass premium in under a year (estimate). Even early, at a
|
||||||
the heat, electric steam costs ~1.4M to 1.7M THB a year against ~0.1M to
|
quarter of the heat, electric steam costs ~1.4M to 1.7M THB a year against
|
||||||
0.2M of fuel, because the demand charge is set by the boiler's full-power
|
~0.15M to 0.3M of fuel, because the demand charge is set by the boiler's full-power
|
||||||
draw, not by its average. Moving electric steam to off-peak hours barely
|
draw, not by its average. Moving electric steam to off-peak hours barely
|
||||||
helps: the presses need steam while they run, and the peak window covers
|
helps: the presses need steam while they run, and the peak window covers
|
||||||
13 of the 16 production hours. The staged electric-first path in
|
13 of the 16 production hours. The staged electric-first path in
|
||||||
|
|||||||