grabowski 20c8d283d5 Rebase costs on USD/THB; add timelines and first market data
Currency
- Base currency moves from EUR to USD and THB throughout. Rates at
  5 Aug 2026: 1 USD = 33 THB, 1 EUR = 1.155 USD, 1 GBP = 1.35 USD.
  EUR/THB lands at ~38, so existing THB research needed no change.
- Vendor quotes keep their original currency with a USD/THB equivalent
  alongside, so they stay checkable against the source PDFs.
- Full vision ~4.7-8.9M USD; phased entry ~1.7-2.9M USD.

New documents
- production-timeline.md: order turnaround stage by stage. Launch
  8-14 weeks, mature 5-10, repress 2-3. Quantifies the in-house
  galvanics turnaround claim the repo had asserted without a number,
  and flags artwork as an unmodelled fourth approval gate.
- project-timeline.md: calendar to first paying release, ~Q4 2028.
  Critical path is BOI certificate to press order to build to
  commissioning. Two findings: Newbilt build time is absent from the
  repo yet carries ~40% of the schedule, and the BOI rule may be
  over-serialised since duty exemption attaches at importation rather
  than at contract signature.

First market data (ResurRec, Bangkok)
- Invoice-derived prices, a factory tour, and a confirmed fleet of one
  Newbilt Classic 12" automatic plus one semi-automatic.
- Price ladder recorded at 300/500/1000-3000/3000+ units. Decomposes
  to roughly 34-50k THB fixed per title and 535-780 THB variable per
  unit, which is 4-7x the price this model assumes.
- The incumbent presses 230-350k records/yr but buys every stamper as
  an import. That single constraint plausibly explains their 150-unit
  floor, their flat discount ladder and their large-run lead time, and
  it is what an in-house galvanics line attacks. Logged as an open
  question on whether galvanics should move from phase 5 to phase 1.
- Inferences are marked as inferences; the whole set is one buyer and
  one plant, and the model is deliberately left unrebased until a
  second data point exists.

Corrections
- Gross margin arithmetic did not follow from its own inputs. Restated
  as ~1.95 USD at the midpoint with the 0.75-3.15 spread shown; the
  previous "40 to 55%" was not supported.
- Direct cost low total 1.50 to 1.45 USD; contingency THB high 40M
  to 38M.
- README indexes the construction RFQ, which was missing.
2026-08-06 12:22:40 +07:00

77 lines
4.6 KiB
Markdown
Raw Blame History

This file contains ambiguous Unicode characters
This file contains Unicode characters that might be confused with other characters. If you think that this is intentional, you can safely ignore this warning. Use the Escape button to reveal them.
# Total Investment: Rough Picture
Everything priced or estimated so far, rolled into one view. Blocks marked
"estimate" have no vendor confirmation; the rest trace to quotes or the
researched ranges in this repo. Treat all figures as budgetary with a wide
margin (plus or minus 30 to 50% on the estimates) until RFQs replace them.
**Currency: USD and THB.** FX at 5 August 2026: **1 USD = 33 THB**.
Vendor quotes issued in another currency are kept in that currency
wherever they appear next to their source document, and converted here at
**1 EUR = 1.155 USD** and **1 GBP = 1.35 USD**. Original figures compiled
July 2026; the underlying THB estimates are unchanged, because EUR/THB at
~38 is where it was when they were made.
## Full vision, all blocks
| Block | USD | THB | Basis |
|---|---|---|---|
| Newbilt semi-auto line, full Duplex | 350k – 370k | 11.5M – 12.2M | 2024 quote EUR 200,500 (~USD 232k) + quoted 2nd press/extruder ~USD 115k; expired, needs re-quote |
| 2 automated presses (Pheenix AD12) | 580k – 920k | 19.1M – 30.5M | unverified ~USD 340k/press indicative + delivery and commissioning |
| Galvanics line (Digital Matrix) | 320k – 650k | 10.7M – 21.4M | six-figure-USD turnkey inference from vendor research |
| Zero-discharge water treatment (ZLD) | 90k – 240k | 3.0M – 8.0M | utilities CSV option row |
| Stamper prep (Sibert VSP, VSF, VSC) | 60k – 170k | 1.9M – 5.7M | estimate, pricing unpublished |
| Mastering and cutting room (Agnew lathe and head, cutter amps, console, room treatment) | 290k – 580k | 9.6M – 19.1M | estimate, bespoke market |
| Metrology and QC stack (confocal, profiler, XRF, inline vision, audio station) | 350k – 810k | 11.5M – 26.7M | estimate, phaseable |
| Utilities, solar, HVAC, racking baseline | 730k – 1,270k | 24.0M – 41.6M | reviewed [utilities CSV](utilities-investment.csv), THB-native |
| Building ~1,500 m² plus civil works | 650k – 1,100k | 21.4M – 36.2M | estimate at 12,000–20,000 THB/m² Thai industrial construction plus ~20% site works |
| Land 6–8 rai, if purchased | 360k – 970k | 12.0M – 32.0M | estimate at 2–4M THB/rai industrial; leasing cuts this to near zero upfront |
| Traceability and factory software | 60k – 170k | 1.9M – 5.7M | estimate |
| Freight, installation, training (non-Newbilt equipment) | 120k – 230k | 3.8M – 7.6M | estimate |
| Working capital, PVC stock, spares | 120k – 230k | 3.8M – 7.6M | estimate |
| Subtotal | ~4.1M – 7.7M | ~135M – 254M | |
| Contingency 15% | ~0.6M – 1.2M | ~20M – 38M | |
| **Total, full vision** | **~4.7M – 8.9M USD** | **~155M – 294M THB** | |
## Phased entry
A credible launch phase is far smaller, roughly **1.7M to 2.9M USD
(~57M to 95M THB)**:
- Newbilt Single system (not Duplex yet)
- Bridge stampers from Stamper Discs, so no galvanics line at launch
- Basic QC (microscope, benchtop PVC lab, sampled listening), full
metrology deferred
- Leased building instead of purchase, modest first solar array
- Galvanics, automated presses, full metrology, and the biomass boiler
follow as revenue-funded or second-round expansions
The planning already supports this: the Duplex-ready hydraulics, the
bridge-supplier role for Stamper Discs, the staged electric-to-biomass
steam path, and the phaseable metrology stack are all documented for
exactly this reason.
## What moves the number
- **BOI**: machinery duty exemption applies across most of the equipment
blocks, and the solar and automation spend converts into CIT-exemption
headroom; the application precedes every purchase order (see
[boi.md](../boi.md))
- **Buy vs lease** on land and building swings roughly **1.0M to 2.1M
USD (~34M to 69M THB)** of upfront capital, and also moves the launch
date by about three quarters — see
[project-timeline.md](../project-timeline.md)
- **Biggest uncertainty bands**: metrology (partly a choice of ambition),
the mastering/cutting room (bespoke vendor, no public pricing), the
automated presses (single unverified price point), and land
- **Currency exposure is real and is not modelled here.** Revenue is
mostly USD/EUR from export customers, the cost base is mostly THB, and
the largest single equipment block is EUR-denominated and unhedged
against an order that will not be placed for roughly a year (see
[project-timeline.md](../project-timeline.md)). A 10% move in EUR/THB
between now and the Newbilt order is worth ~USD 25–35k on that line
alone. Ask for the re-quote to state its currency and validity period.
- Every band narrows only with RFQs; the supplier map in
[equipment-suppliers.md](../suppliers/equipment-suppliers.md) lists who
to ask