User, 19 Oct 2026: plan the current EtherCAT setup, keep the 100 W servo, check prices on geizhals.de. - New docs/equipment/inline-qc-control-plan.md: decisions, bus layout (drives at the end of the line because the A6-200EC takes control power from the main supply), I/O list for EL1809/EL2809/EL3152/EL5101 and the drive touch probe, PDO and DC notes from the A6-EC manual, geizhals.de price table (EUR 1,891.60 to 2,104.39 + USD 246.58 for the servo kits, THB 80k to 88k), NixOS/EtherCrab software, safety circuit (PNOZ s3, two contactors, dump valve), bench test with pass marks (parts about THB 64k, all reused), build order, spares, open points. - EL3102 replaced by EL3152: the optoNCDT 1420 output is 4 to 20 mA. - Spindle encoder index goes to an EL5101 instead of the drive touch probe; encoder 2,000 to 2,500 pulses. - BOM: control lines split per part with geizhals.de prices (+30% high end for shipping and Thai duty/VAT, estimate); total USD 16,912 to 33,061 (THB 0.56M to 1.09M). Doc, render caption and fleet calculator text now say USD 17k to 33k. - README links the plan.
282 lines
16 KiB
Markdown
282 lines
16 KiB
Markdown
# Optical QC station: EtherCAT control plan
|
||
|
||
How the [inline optical QC station](inline-optical-qc.md) is controlled,
|
||
wired, priced, built and tested. Decided in October 2026: EtherCAT, no
|
||
PLC, and the 100 W StepperOnline servo kit on both axes. Prices for the
|
||
EtherCAT parts were checked on [geizhals.de](https://geizhals.de/) on
|
||
19 October 2026. The station hardware itself (frame, cameras, lights,
|
||
lasers) is in the station doc and its
|
||
[bill of materials](inline-qc-station/inline-qc-station-bom.csv).
|
||
|
||
## 1. What is decided
|
||
|
||
| Part | Choice | Why |
|
||
|---|---|---|
|
||
| Fieldbus | EtherCAT, 1 ms cycle, distributed clocks | one cable for drives and I/O; the laser samples and the spindle position come from the same cycle |
|
||
| Spindle drive | StepperOnline A6-EC100L2A1-M17 (100 W, A6-200EC drive), cyclic synchronous position, 1:6 timing belt | torque need about 0.02 N·m at the motor against 0.32 N·m rated; the belt brings the load inertia to about 28 times the rotor (station doc) |
|
||
| Conveyor drive | the same kit, cyclic synchronous velocity | one spare covers both axes |
|
||
| Controller | fanless Intel N100 mini PC with Intel i226-V ports, NixOS with a real-time kernel | open source stack, declared in the plant's clan like every other machine |
|
||
| Master software | EtherCrab (Rust, MIT or Apache-2.0); IgH EtherCAT Master as the fallback | EtherCrab fits the Rust factory application; IgH is older and proven |
|
||
| Camera clock | separate RS-422 encoder on the spindle shaft | the A6-EC drive has no divided encoder output |
|
||
| Safety | hardwired: safety relay, two contactors in the drive supply | the 100 W kit has no STO; the 400 W STO kit's manual names no safety rating (station doc) |
|
||
|
||
## 2. Bus layout
|
||
|
||
```
|
||
Station controller (N100, NixOS, real-time kernel)
|
||
|
|
||
|-- port 1 (i226-V) == EtherCAT ==> EK1100 coupler
|
||
| |-- EL1809 16 digital inputs
|
||
| |-- EL2809 16 digital outputs
|
||
| |-- EL3152 2 analog inputs (warp lasers, 4 to 20 mA)
|
||
| |-- EL5101 spindle encoder (A, B, index)
|
||
| |-- EL9011 end cap
|
||
| |
|
||
| X2 out ==> A6-200EC spindle (CSP)
|
||
| ==> A6-200EC conveyor (CSV)
|
||
|
|
||
|-- port 2 (i226-V) -- plain Ethernet --> edge PC, plant OT network
|
||
|
||
Spindle encoder (RS-422, 5 V from the EL5101)
|
||
A, B ---> racer 2 line-scan 1 ---> racer 2 line-scan 2 ---> EL5101 (A, B, index)
|
||
```
|
||
|
||
- **The drives sit at the end of the line.** On the small A6-200EC the
|
||
control electronics share the main supply; there are no separate
|
||
control-power terminals ([A6-EC manual](https://www.omc-stepperonline.com/download/A6-EC_series_servo_drive_manual.pdf),
|
||
specification table). So when the safety contactors open, both drives
|
||
leave the bus. At the end of the line that cuts nothing else off: the
|
||
coupler, the I/O and the encoder count stay up, and the master can read
|
||
the e-stop and door status and bring the drives back after the reset.
|
||
The distributed-clock reference also sits on the I/O side for the same
|
||
reason.
|
||
- **One RS-422 line, three receivers.** The encoder's line driver feeds
|
||
both cameras and the EL5101 in a chain (RS-422 allows up to ten
|
||
receivers). The racer 2 inputs take RS-422 with a switchable 120 Ω
|
||
terminator ([Basler](https://docs.baslerweb.com/io-control-racer-2-l-xl)).
|
||
Only the last receiver on the line is terminated; check on the bench
|
||
whether the EL5101 input already is.
|
||
- **Port 2 is ordinary Ethernet** to the edge PC and the plant's OT
|
||
network (VLAN as in [digital factory](../digital-factory.md)). The
|
||
EtherCAT port is a point-to-point cable to the EK1100, never a switch.
|
||
|
||
## 3. Signals
|
||
|
||
**EL1809, 16 inputs (24 V):**
|
||
|
||
| Ch | Signal | Device |
|
||
|---|---|---|
|
||
| 1 | record at the infeed | diffuse photoelectric sensor |
|
||
| 2 | label trigger (also wired straight to the two colour cameras' trigger inputs) | diffuse photoelectric sensor |
|
||
| 3 | record at the inspection position (also to the conveyor drive's touch probe 1, CN1 DI5) | through-beam pair |
|
||
| 4 | outfeed full | diffuse photoelectric sensor |
|
||
| 5, 6 | lift up, lift down | cylinder switches |
|
||
| 7, 8 | mandrel open, mandrel clamped | cylinder switches |
|
||
| 9, 10 | pusher home, pusher out | cylinder switches |
|
||
| 11 | safety relay status | PNOZ s3 semiconductor output |
|
||
| 12 | door closed (status contact) | safety door switch |
|
||
| 13 | contactors closed | contactor auxiliary contact |
|
||
| 14 | reset pressed | second contact on the reset button |
|
||
| 15 | air pressure ok | pressure switch on the FRL |
|
||
| 16 | spare | |
|
||
|
||
**EL2809, 16 outputs (24 V, 0.5 A):** lift up, lift down, mandrel clamp,
|
||
pusher out, pusher back, stack light green, amber and red, buzzer, light
|
||
controllers on (lights only during the turn), reset-button lamp; five
|
||
spare (an ionising bar at the infeed is one candidate).
|
||
|
||
**EL3152, 2 analog inputs:** the two optoNCDT 1420 lasers at 90 and 130 mm
|
||
radius. Their analog output is 4 to 20 mA; voltage only comes through a
|
||
load resistor in the cable
|
||
([Micro-Epsilon manual](https://micro-epsilon.com/download/manuals/man--optoNCDT-1420--en.pdf)),
|
||
so the current-input EL3152 replaces the ±10 V EL3102 of the first draft.
|
||
|
||
**EL5101:** spindle encoder A, B and index. It counts the spindle angle
|
||
directly (not the motor behind the belt) and latches the count at the
|
||
index once a turn.
|
||
|
||
**Drive inputs:** only the conveyor drive's touch probe 1 is used: the
|
||
through-beam latches the conveyor position at the record's leading edge,
|
||
so the stop over the chuck does not depend on the 1 ms cycle or the
|
||
input filter.
|
||
|
||
**Process data per drive.** The A6-EC has one freely mapped RPDO and
|
||
TPDO plus fixed sets; the fixed 1702h set carries control word, target
|
||
position, target velocity and mode together (manual, PDO section), so
|
||
both drives can share one mapping and differ only in the mode (8 for
|
||
CSP, 9 for CSV). The drive runs only in DC sync mode; its SYNC0 period
|
||
range depends on the mode, so the 1 ms cycle is the first bench check.
|
||
|
||
## 4. Prices from geizhals.de
|
||
|
||
Lowest listed price on 19 October 2026, in EUR including 19% German VAT;
|
||
THB at 38.115 per EUR.
|
||
|
||
| Part | Qty | Example | EUR | THB | Source |
|
||
|---|---|---|---|---|---|
|
||
| Station controller | 1 | ANDAQI RS55 (6 × i226-V) / MNBOXCONET P2-N100 (2 × i226-V, fanless) | 393.99 to 455.99 | 15,017 to 17,380 | [geizhals](https://geizhals.de/mini-pc-barebone-netzwerk-pc-intel-n100-a2926989.html) |
|
||
| EtherCAT coupler | 1 | Beckhoff EK1100 | 150.75 | 5,746 | [geizhals](https://geizhals.de/144468496) |
|
||
| 16 digital inputs | 1 | Beckhoff EL1809 | 93.97 | 3,582 | [geizhals](https://geizhals.de/1371087148) |
|
||
| 16 digital outputs | 1 | Beckhoff EL2809 | 102.97 | 3,925 | [geizhals](https://geizhals.de/1371087504) |
|
||
| 2 analog inputs, 4 to 20 mA | 1 | Beckhoff EL3152 | 208.90 | 7,962 | [geizhals](https://geizhals.de/185886294) |
|
||
| Encoder interface, RS-422 | 1 | Beckhoff EL5101 | 291.04 | 11,093 | [geizhals](https://geizhals.de/2974477757) |
|
||
| End cap | 1 | Beckhoff EL9011 | 4.33 | 165 | [geizhals](https://geizhals.de/455904583) |
|
||
| Spindle encoder | 1 | E6B2-CWZ1X 2000 P/R (marketplace) / GHH60 2500 P/R line driver | 45.52 to 187.83 | 1,735 to 7,159 | [geizhals](https://geizhals.de/6925000400) |
|
||
| Safety relay | 1 | Pilz PNOZ s3 750103 | 148.38 | 5,656 | [geizhals](https://geizhals.de/pilz-pnoz-s3-24vdc-2-n-o-750103-a3204143.html) |
|
||
| Contactor, 24 V DC coil | 2 | Siemens 3RT2015 | 27.95 each | 2,131 | [geizhals](https://geizhals.de/siemens-leistungsschuetz-3rt2015-1bb41-a3269085.html) |
|
||
| E-stop button | 1 | Schneider Harmony, 40 mm head | 45.08 | 1,718 | [geizhals](https://geizhals.de/208045150) |
|
||
| HMI touch monitor 10.1 inch | 1 | iiyama ProLite TF1015MC-B3 | 311.90 | 11,888 | [geizhals](https://geizhals.de/iiyama-prolite-tf1015mc-b3-a3228748.html) |
|
||
| 24 V supply, 120 W | 1 | Mean Well SDR-120-24 | 38.87 to 47.35 | 1,482 to 1,805 | [geizhals](https://geizhals.de/980542712) |
|
||
| Servo kit 100 W, EtherCAT | 2 | StepperOnline A6-EC100L2A1-M17 | USD 123.29 each | 8,137 | not on geizhals; [StepperOnline](https://www.omc-stepperonline.com/a6-series-100w-ethercat-ac-servo-motor-kit-3000rpm-0-32nm-17-bit-absolute-encoder-ip67-a6-ec100l2a1-m17), China warehouse |
|
||
| **Total** | | | **1,891.60 to 2,104.39 + USD 246.58** | **80,235 to 88,346** | |
|
||
|
||
Notes on the prices:
|
||
|
||
- **German VAT comes off, Thai duty and VAT go on.** For an order
|
||
shipped to Thailand the 19% German VAT is not charged; Thai import VAT
|
||
(7%) and duty are added. The listed gross price is therefore used as
|
||
the landed low end; the bill of materials adds 30% for shipping and a
|
||
Thai distributor as the high end (estimate).
|
||
- **EK1100:** geizhals has no current offer; EUR 150.75 is the last
|
||
price, with EUR 255.43 at the top of the range.
|
||
- **Mini PCs** on geizhals are marketplace brands (ANDAQI, MNBOXCONET,
|
||
AIOPCWA). Before ordering, check that the ports are i226-V (not the
|
||
older i225) and that the BIOS lets C-states be switched off.
|
||
- **Encoder:** the EUR 45.52 E6B2-CWZ1X listings come from marketplace
|
||
sellers and may be copies; the bench test decides whether one is good
|
||
enough. A genuine Omron or a 2,500-pulse line-driver encoder (GHH60,
|
||
EUR 187.83) is the fallback.
|
||
- **Contactors:** the price is for 3RT2015-1BB41 (one NO auxiliary
|
||
contact). The feedback loop needs the NC version, 3RT2015-1BB42
|
||
(price not checked; same class).
|
||
- **Not on geizhals:** the servo kits (StepperOnline direct), the optoNCDT
|
||
lasers and the Basler cameras (both in the station bill of materials).
|
||
|
||
Bill of materials effect: the control group comes to USD 4.4k to 8.1k
|
||
(edge PC with GPU and the cabinet lot included) and the station to
|
||
**USD 16.9k to 33.1k (THB 0.56M to 1.09M)**, up from 16.1k to 32.9k,
|
||
mostly the EL5101 and the retail price of the mini PC.
|
||
|
||
## 5. Software on the station controller
|
||
|
||
**Operating system (NixOS module in the plant's clan):**
|
||
|
||
- Kernel 6.12 LTS with PREEMPT_RT, which is in the mainline kernel since
|
||
6.12. The same kernel suits the IgH fallback, whose native i226 (igc)
|
||
driver is listed for 6.12
|
||
([IgH device drivers](https://docs.etherlab.org/ethercat/1.6/doxygen/devicedrivers.html)).
|
||
- One core isolated for the bus loop (`isolcpus`, `nohz_full`,
|
||
`rcu_nocbs`), the EtherCAT port's interrupts pinned to it, deep
|
||
C-states and Energy Efficient Ethernet off on that port.
|
||
- The station service runs under systemd with real-time priority and
|
||
restarts on failure; logs go to the plant's log store.
|
||
|
||
**Station service (Rust, one program, written by us):**
|
||
|
||
1. **Bus loop:** EtherCrab every 1 ms with distributed clocks; brings
|
||
all slaves to OP, maps the drive PDOs, runs the CiA402 state machine
|
||
of both drives, and re-adds a drive that left the bus after an
|
||
e-stop.
|
||
2. **Sequence:** one state machine per record: wait at the infeed,
|
||
convey, stop on the latched leading edge, lift, clamp, one turn,
|
||
unclamp, lower, convey out, push if rejected. Every step has a
|
||
timeout and a fault text (for example "lift up not reached in 0.8 s").
|
||
3. **Measurement:** during the turn, each cycle stores the EL5101 count
|
||
and both laser values, about 1,000 points a turn at one turn a
|
||
second. The laser output lags 750 µs at 4 kHz (Micro-Epsilon), a fixed
|
||
offset of about 0.3° at that speed, corrected in software. Edge
|
||
run-out and dish are computed at the end of the turn.
|
||
4. **Edge PC link** over port 2: record in place, turn started, turn
|
||
done with the warp values; the edge PC answers with the verdict and
|
||
the reason. No answer in time means reject and an alarm.
|
||
5. **HMI:** a web page served by the same program and shown on the touch
|
||
monitor in a kiosk browser: state, last results, alarms, counters, and
|
||
a setup mode (jog, single steps) that works only with the door shut.
|
||
|
||
The cameras keep their clock in hardware: the encoder pulses go straight
|
||
into the racer 2 encoder input, and the camera's frequency converter
|
||
scales them to the line count the optics need
|
||
([Basler](https://docs.baslerweb.com/frequency-converter)). No software
|
||
sits between the spindle and the line timing.
|
||
|
||
## 6. Safety
|
||
|
||
- **Circuit:** e-stop (two channels) and the tunnel door switch (two
|
||
channels) on a Pilz PNOZ s3 with a monitored manual reset. Its two
|
||
safety contacts switch two contactors in series in the 230 V supply of
|
||
both drives; the contactors' NC mirror contacts sit in the relay's
|
||
feedback loop. A dump valve on the FRL, wired with the contactor
|
||
coils, vents the cylinders at the same time.
|
||
- **Stop category 0:** power off at once. Both axes carry a few
|
||
kg·cm², so they coast to a stop in well under a second (estimate). If
|
||
the risk assessment asks for a controlled stop first (category 1), a
|
||
relay with delayed outputs (Pilz PNOZ s5 class) lets the master brake
|
||
the axes before the power goes.
|
||
- **Target:** PL d (estimate). A risk assessment to ISO 12100 and
|
||
ISO 13849-1 by the machine builder decides; it is part of the
|
||
acceptance test.
|
||
- **After a stop:** reset, the drives power up and rejoin the bus, the
|
||
master takes them back to OP, and the spindle angle comes from the
|
||
EL5101 count, which never lost power.
|
||
|
||
## 7. Bench test, before the frame is built
|
||
|
||
**Parts:** one servo kit, the mini PC, the EK1100 with the four I/O
|
||
terminals and the end cap, the spindle encoder, the PNOZ s3, two
|
||
contactors, the e-stop and the 24 V supply: EUR 1,579.70 on geizhals
|
||
plus USD 123.29, about **THB 64,000 (USD 1,950)**. Every part goes into
|
||
the station afterwards. One laser and one line-scan camera, ordered
|
||
early from the station list, make the test complete. A reject record on
|
||
a test mandrel is the load.
|
||
|
||
| # | Test | Pass (our targets) |
|
||
|---|---|---|
|
||
| 1 | EtherCrab brings coupler, terminals and drive to OP with distributed clocks at 1 ms | all slaves in OP, no lost frames over 24 h |
|
||
| 2 | Cycle timing under load: images streaming on port 2, HMI open, CPU stress on the other cores | worst-case jitter under 50 µs over 24 h |
|
||
| 3 | Spindle in CSP: one turn a second, 0.15 s run-up | stop repeatable within ±0.1° at the spindle |
|
||
| 4 | EL5101 count against the servo position | exactly 6 motor turns per spindle turn over 1,000 turns, index latched every turn |
|
||
| 5 | Laser through the EL3152 on the reject record | the warp trace repeats turn to turn within 0.05 mm, a tenth of the smallest edge run-out limit (0.5 mm, Mobineko) |
|
||
| 6 | Camera clock: racer 2 on the encoder chain | the set number of lines every turn, none missed over 100 turns |
|
||
| 7 | Conveyor (same drive in CSV): through-beam on touch probe 1 | position latched on every pass |
|
||
| 8 | E-stop and door | contactors open, drive leaves the bus, I/O stays in OP; drive back in OP within 10 s of the reset |
|
||
|
||
If EtherCrab fails tests 1, 2, 3 or 8 and a week of work does not fix
|
||
it, repeat them with the IgH master on the same kernel. The station
|
||
service keeps the bus loop behind one interface, so only that part
|
||
changes.
|
||
|
||
## 8. Build order and timing (estimates)
|
||
|
||
| Weeks | Step | Who |
|
||
|---|---|---|
|
||
| 1 to 3 | order the bench parts; servo kits from StepperOnline's China warehouse, Beckhoff and the rest from Germany or a Thai distributor | us |
|
||
| 3 to 6 | bench test (section 7) | us |
|
||
| 5 to 9 | cabinet schematic (QElectroTech, open source) and cabinet build; station service and HMI | us, with a panel builder in Chiang Mai if needed |
|
||
| 7 to 11 | frame, conveyor, spindle head and pneumatics | machine builder |
|
||
| 10 to 12 | cabinet on the frame, wiring, drive tuning on the real spindle, first records | us and the machine builder |
|
||
| 12 to 14 | risk assessment, acceptance test, then into production behind the cooling racks | us and the machine builder |
|
||
|
||
So the control work should start about four months before the first
|
||
records need checking (estimate).
|
||
|
||
## 9. Spares
|
||
|
||
One servo kit (covers both axes), one spindle encoder and one contactor:
|
||
about USD 210 at the prices above. The Beckhoff terminals are not
|
||
stocked at launch; a failed one is a few days by courier from Europe
|
||
(estimate).
|
||
|
||
## 10. Open points
|
||
|
||
1. **EtherCrab with the A6-EC drive** is untested; its CiA402 support is
|
||
basic. The bench answers it, with IgH as the fallback.
|
||
2. **SYNC0 range of the A6-EC** at 1 ms in CSP and CSV: not in the
|
||
material read so far; the bench checks it.
|
||
3. **EL5101 termination** and the RS-422 chain with three receivers.
|
||
4. **Local prices:** ask a Thai Beckhoff source for a quote before
|
||
ordering from Germany.
|
||
5. **Risk assessment** by the machine builder: confirms PL d and stop
|
||
category 0, or asks for the delayed relay.
|
||
6. Still open from the station doc: 7"/10" quick change, anti-static at
|
||
the infeed, belt tension against the motor's 78 N radial load.
|