New page docs/steam-cooling.html (site /demos/steam-cooling/): the utility plant as a clickable process diagram. Steam side: raw water, softener and dosing, feed tank with heat-pump feedwater recovery, feed pumps, a bank of two 500 kg/h boilers (third for N+1 as an option), separator and metering, optional accumulator, blowdown, the 10 bar header with a valved, metered branch and trap per press, drip legs and condensate return. Cooling side: Newbilt's press outlets are open (max. 2 bar), so returns drain to a warm tank, pass the heat pump, an optional dry cooler and a plate heat exchanger to a cold buffer tank, and VFD pumps feed the 20 to 25 C header at ~10 bar to every press, the extruders and the central hydraulic oil cooler; the chiller loop (three 250 kW air-cooled modules at 40 C ambient, fourth as option) stays closed and clean. Galvanics cooling (12 to 20 C) is a separate circuit. Operating cases (launch, Duplex system 1, five presses, one module down) show demand against installed capacity; design basis with sources, equipment schedule, RFQ questions. Static SVG, no per-frame work. Design basis at Newbilt's per-machine figures: steam 750 to 900 kg/h, cooling 652.5 kW (625 presses, 15 extruders, 12.5 hydraulics), 305 to 540 l/min circulating. Also found: Newbilt's 53 l/min at ~60 C out is ~140 kW, above its 125 kW peak; listed as a re-quote question. Re-based in the same commit: - scale.md: electrical table (chiller bank ~210 to 325 kW electrical, plant peak ~430 to 700 kW, ~950 to 1,330 kW with electric steam), grid 800 to 1,000 kVA (1,250 to 1,600 with electric steam, Schedule 4 past 1,000 kW), tariff 4.5M to 6.8M THB/yr, battery ~1 h of chiller peak, boiler and chiller banks, biomass up to ~550 t/yr at 1.5 M records, utilities money line. - sustainability.md, biomass.md: same figures; electric steam 5.2M to 6.0M THB/yr mature, 1.6M to 1.8M early; fuel saving 4.0M to 5.4M. - utilities CSV: boiler bank, chiller bank with HX and tanks, softener and loop treatment re-sized; baseline 23.98M-41.63M -> 30.07M-51.33M. - total-investment.md: re-size as an added-scope row (+185k / +294k USD); headline 4.7M to 8.9M unchanged until the investment re-base. - pressing-line, equipment-suppliers, facility-security, fleet calculator (boiler 1000 kg/h, chiller 750 kW), plant page detail texts; README, landing page, build.sh.
19 lines
6.0 KiB
CSV
19 lines
6.0 KiB
CSV
category,item,spec_summary,candidate_thai_suppliers,cost_low_thb,cost_high_thb,cost_basis,notes
|
|
steam,Electric/gas once-through boiler bank,"2 x 500 kg/h modules at 10.5 bar / 180 C, lead/lag, shared feed tank, feed pumps, economizer, installed",Miura Thailand (Chachoengsao); Bangkok Industrial Boilers; STE Thailand,4500000,7000000,engineering estimate,"Five-press fleet 750-900 kg/h (steam-cooling.html); B-1 with the launch press, B-2 with Duplex 2; a third module for N+1 is an RFQ option; Miura-class modular once-through; service is Bangkok-centric, confirm northern dispatch SLA"
|
|
steam,Biomass/wood-fired boiler package (option),"~1 t/h solid fuel (wood chips/pellets/rice husk) incl. fuel feed, grate, dust control, softener, installed",Getabec PCL (Thai fabrication and service),6000000,10000000,engineering estimate,"Sized for the five-press fleet (was ~0.5 t/h for one Duplex); sustainability path matching Deepgrooves NL precedent; higher capex, lower fuel opex in the North; NOT included in baseline total"
|
|
steam,Steam balance of plant,"Traps, accumulator, condensate return",Forbes Marshall Thailand,0,0,included,Largely included in boiler package rows; line kept for RFQ completeness
|
|
compressed_air,Screw compressor skid (oil-injected),"~7.5 kW VSD screw + refrigerated dryer (3 C PDP) + coalescing filters + ~500 L receiver, installed",Atlas Copco Thailand; Kaeser Thailand (SM-T/Aircenter); Ingersoll Rand Thailand,350000,600000,engineering estimate,14-30 m3/h demand is small (5-10 hp class); oil-injected + filter train meets 5 micron / 3 C spec
|
|
compressed_air,True oil-free class-0 (option),Same duty in oil-free class-0,Atlas Copco (ZR/ZT); Kaeser,1200000,1800000,engineering estimate,Only if air contacts product stream; NOT included in baseline total
|
|
cooling,Process chiller bank 3 x 250 kW,"3 x ~71 RT air-cooled screw/scroll chillers rated at 40 C ambient + primary pumps + plate HX + warm and cold tanks + VFD supply pumps + controls, installed",Trane Thailand; Carrier Thailand; Daikin Applied Thailand; Hitachi Thailand,6500000,10500000,engineering estimate,"Five-press fleet up to ~650 kW and 305-540 l/min (Newbilt site requirements, 20-25 C supply); one module per press stage; 3 x 350 kW for N+1 as the alternative (steam-cooling.html)"
|
|
cooling,Cooling tower + HX loop (alternative),Dry cooler or FRP tower ~650-750 kW reject + plate HX + pumps + tanks + water treatment,"Liang Chi Thailand (tower, large service org); Process Cooling Solutions; Tasaki (integrators)",2000000,3500000,engineering estimate,Cheaper capex but wet-bulb-limited; hybrid tower + trim chiller is the efficiency-optimal design; NOT included in baseline total
|
|
water,Boiler feedwater duplex softener,~1.0-1.2 m3/h feedwater duty (five-press boiler bank),Veolia Water Technologies Thailand; Hydrotek; local RO/softener integrators,120000,300000,market estimate,May suffice alone for a small fire-tube boiler
|
|
water,RO skid (option),0.5-1 m3/h low-TDS feed,Veolia; Hydrotek; local integrators,200000,500000,market estimate,Only if low-TDS feed needed; NOT included in baseline total
|
|
water,Closed-loop cooling water treatment,Side-stream filtration + dosing + conductivity blowdown control,Veolia; Hydrotek; local integrators,200000,500000,engineering estimate,"Sized for the five-press loop with its open return tank (Newbilt press outlets are open, max. 2 bar); chemicals are ongoing opex on top"
|
|
water,Galvanics ZLD evaporator (future),"Small MVR or low-temp vacuum evaporator for plating rinse, installed","Core unit imported (WTEYA, Greenlan, Fred); Thai integration via Veolia or Hydrotek",3000000,8000000,market estimate,"For the future galvanics line, zero-discharge requirement; NOT included in baseline total"
|
|
storage,Pallet racking and shelving,"100-200 pallet positions selective/heavy-duty (beams sized 1000-1500 kg/pallet, records are dense) + archive and finished-goods shelving, installed","Jenbunjerd; local fabricators (Sahawatthanakit, UPR, SD Shelf); SSI Schaefer (premium)",800000,1500000,published list prices + engineering estimate,SSI Schaefer premium tier ~1.5-3M for same scope; ~1000-2000 THB per pallet position at local tier
|
|
hvac,Whole-factory HVAC,"~1500 m2 at 20-26 C, 35-60% RH, ePM1/F7-F9 filtration sized for burning-season PM2.5, ducting and controls","Daikin Thailand; Trane; Mitsubishi Electric; Carrier; filtration: Camfil Thailand, AAF",7500000,15000000,engineering estimate at 5000-10000 THB/m2,"RH low end of 35% is aggressive for tropics and drives desiccant cost; if 45-60% RH acceptable, cost drops materially"
|
|
hvac,Clean-room-grade zone adder,"Cutting room + galvanics clean room, ~2 x 60 m2, ISO 7/8 with HEPA terminals, positive pressure, airlocks",Same HVAC vendors + clean-room contractors; Camfil HEPA,1200000,3400000,engineering estimate at 10000-28000 THB/m2 adder,Applied only to the two tight zones
|
|
solar,PV rooftop EPC (illustrative 300 kWp),"Turnkey C&I rooftop EPC incl. Deye hybrid inverters, at 25000-35000 THB/kWp",Solar Nicolo (Deye tier-1 distributor); Banpu NEXT; SCG Cleanergy; Sermsang; local Chiang Mai installers,7500000,10500000,market rate per kWp; size illustrative,"Final kWp open until site selection; PEA TOU 3.2.2 plus Ft (Sep-Dec 2026): self-consumed PV worth ~3.7 THB/kWh, ~4.5-7 yr payback (sustainability.md, grid tariff)"
|
|
solar,Battery stack 271 kWh (Gobel),"GP-SRA-HV314 HV LiFePO4 rack, 15 x 18 kWh packs, direct from Shenzhen, 50-60 day lead",Gobel Power (no Thai distributor; integration by solar EPC),1400000,2030000,vendor listed price USD 39900-58000 at ~35 THB/USD,Confirm Deye BMS protocol compatibility and that the EPC warrants a mixed-vendor DC bus; certs (UN38.3/IEC 62619/CE) to be requested
|
|
total,BASELINE TOTAL,Electric steam bank + oil-injected air + chiller bank + softener + loop treatment + local racking + HVAC + clean zones + 300 kWp solar + 271 kWh BESS,,30070000,51330000,sum of baseline rows,"Five-press fleet (October 2026; was 23.98M-41.63M THB for one Duplex); ~790k-1350k EUR at 38 THB/EUR; excludes options rows (biomass premium, oil-free, tower alternative, RO, ZLD evaporator, SSI premium tier); all figures budgetary +/- 30%, get RFQs before BOI/finance filings"
|