grabowski d42e99389b Business plan draft 0.2: re-based on the launch plant
The investor business plan (docx + pdf) rebuilt for the launch plant
decided in October 2026: one Duplex system and one Classic, Pheenix
galvanics with zero discharge, the Sibert line, a Sillitoe cutting room,
modular steam and cooling (rooms for four), cassette and CD-R; no bridge
stampers, no outsourced cutting; second Duplex as a growth option.

- Part A: executive summary (what changed since 0.1, the numbers, the
  180M / 216M answer, first release marked open), reading guide, two
  price points (ResurRec and Record Industry), anatomy rewritten for
  Sillitoe, Pheenix, Sibert, Duplex + Classic, lead times without bridge
  stampers, new 4.8 artist platform, cassette 4.9, CD 4.10.
- Part B: traceability with ERPNext as system of record, metrology launch
  tier as the investor's choice, QC, efficiency (PEA tariff, utility
  modules, fuel open, Chinese boilers and DIW rules), site (Mueang Chi,
  Payap zoning result), building blocks, safety, BOI and licences with
  galvanics in the first factory licence.
- Part C: launch-plant investment table, the investor's question and
  levers, tranches, currency, operating picture of the launch plant,
  timeline with the metal path on the critical path, commissioning
  sequence and why the whole chain at launch, team, 22 risks, 17 phase 0
  actions, the ask.
- plan_lib: grid column widths so LibreOffice keeps table widths.
- export_pdf.py: LibreOffice UNO export that fills the table of
  contents (47 pages).
- README: total investment, revenue model and business plan bullets.
2026-10-16 16:01:25 +07:00

372 lines
22 KiB
Markdown
Raw Blame History

This file contains ambiguous Unicode characters
This file contains Unicode characters that might be confused with other characters. If you think that this is intentional, you can safely ignore this warning. Use the Escape button to reveal them.
# CNX Vinyl / Poy Records
<img src="docs/brand/poyrecord-logo-1536x1536.png" alt="Poy Records logo" width="160">
A vinyl record factory in planning for the Chiang Mai area of northern
Thailand (site candidates include Lamphun and Lampang provinces and, since
October 2026, Payap University land in Chiang Mai). This repository is
the source of truth for the project: planning documents and cost data
today. As the factory takes shape it will also hold the data and software
used to run it.
## Team
- **Simona Meesaiyati**, Project Lead: management and the audio side
- **Alexander Grabowski**, Technical Consultant: the technical side
[buildfor.life](https://buildfor.life) supports the project in a consulting
capacity.
## Vision: Full-Service Production
The goal is the complete vinyl production chain under one roof, from audio
file to delivered record:
1. **Mastering**: audio mastering for vinyl
2. **Lathe cutting**: cutting the master disc
3. **Silvering**: metallizing the cut master
4. **Stamper production**: electroforming nickel stampers in-house
5. **Pressing**: extrusion and pressing of the records, with the labels
pressed in
6. **Finishing**: trimming, sleeving, shrink wrapping
7. **Packaging**: folded paper cartons (jackets and sleeves), produced in
collaboration with local packaging manufacturers
8. **Fulfillment**: dropshipping directly to end customers on behalf of
labels and artists, alongside conventional bulk delivery
In-house galvanics (steps 3 and 4) removes the dependency on overseas stamper
suppliers, a common bottleneck for pressing plants, and shortens turnaround
for clients. Partnering with local carton manufacturers keeps packaging
sourcing close to the plant, in line with the local-sourcing preference for
materials. The pressing line is documented in detail, galvanics and stamper
prep from vendor datasheets; equipment, partners, and budgets for the other
steps are open planning items.
## Project Status
**Planning stage** (as of October 2026).
- Industry outreach has been ongoing for several years: equipment vendors,
material suppliers, and independent consultants.
- Alexander and Simona attended
[Making Vinyl Europe 2026](https://makingvinyl.com/) in Haarlem (30
September to 2 October). Most people they talked to were strongly
interested in the full-traceability approach, and for Sibert it was a
reason to engage at all (notes in the
[exhibitor briefing](docs/suppliers/making-vinyl-europe-2026-exhibitors.md#after-the-show)).
- Payap University (Chiang Mai) has offered land on lease and wants to
build joint student programmes with the plant. The point it gave for the
land is zoned very high density residential in the Chiang Mai city plan,
where record pressing is not permitted (checked October 2026); other
Payap land would need checking
([site candidates](docs/site-candidates.md),
[Payap partnership](docs/payap-partnership.md)).
- A collaboration with [ResurRec](https://www.resurrec.com/) is under
discussion.
- Back from Haarlem, the team is preparing a meeting with the project's
investor (October 2026). Post-show follow-ups with Pheenix, Sibert, OMS
and SST are in the
[exhibitor briefing](docs/suppliers/making-vinyl-europe-2026-exhibitors.md#after-the-show).
- The plant now launches with everything in one capital round (October
2026): one Newbilt Duplex system and one Classic, a Pheenix galvanics
line, the Sibert stamper-prep line, a Sillitoe cutting room and the
modular boiler and chiller plant. The investor asked whether it can be
built for 180M THB, possibly 20 % more: on current estimates it costs
~161M to 292M THB (midpoint ~227M), so 216M is a realistic target with
four levers and 180M a low-quote case
([total investment](docs/finance/total-investment.md#launch-plant-october-2026)).
Chinese boilers, compressor and hydraulics save about 2M THB of that
([Chinese suppliers](docs/suppliers/china-utilities.md)).
The business plan is re-based on it (draft 0.2).
## Planning Documents
The detail lives in dedicated documents:
- [Roadmap](docs/roadmap.md): next steps in dependency order, from the
three current gates (market validation, BOI, land title check) through
quotes, commitment, build, launch, and expansion
- [Pressing line equipment plan](docs/equipment/pressing-line.md): the
current all-Newbilt fleet (two Duplex systems, each with an EX 50 main
and an EX 35 colour extruder, plus one Classic automatic press), the 2024
Newbilt quote (~USD 232k,
expired), the 2026 product flyers, and site requirements
- [Galvanics and stamper prep equipment plan](docs/equipment/galvanics.md):
the metal path from lacquer to press-ready stamper, from vendor
datasheets: Pheenix Alpha's electroforming range as a second turnkey
vendor next to Digital Matrix, OMS as a third named by Sibert (reference
prices for a 4-cell wet room, EUR 224k to 311k), Sibert's
VSP/VSF/VSC stamper prep line (USD 250k budget for the three confirmed),
the utilities they need, a first cell-count estimate, and Sibert's
optical-disc reference material
- [Vendor landscape](docs/suppliers/vendor-landscape.md): researched
candidates for mastering and cutting (Agnew Analog, and the Sillitoe
SDMS with integrated cutting automation at a published USD 125k),
galvanics equipment
(Plating Power / Digital Matrix, Pheenix Alpha, Optical Media Services),
used lathes and cutting-room contacts (via OMS),
stamper preparation
(Sibert), bridge stamper service (Stamper Discs), and automated presses
(Pheenix Alpha, the comparison for the Classic)
- [Equipment needs and supplier map](docs/suppliers/equipment-suppliers.md):
the full needs list per production step with supplier tables and contacts
- [Chinese suppliers](docs/suppliers/china-utilities.md): boilers,
compressed air and hydraulics from China (makers, published prices,
Thai offices, Thai boiler rules for imports); saves about 2M THB, ~1 %
of the budget
- [Sustainability](docs/sustainability.md): the solar installation (Deye
inverters, 271 kWh Gobel Power battery stack), the PEA grid tariff and
what it decides (biomass steam at a quarter to a tenth of the cost of
electric, PV rather than solar thermal), the zero contaminated water commitment,
and the materials strategy
- [Worker safety](docs/worker-safety.md): safety training, galvanics clean
rooms and decontamination, PPE
- [Biomass fuel strategy](docs/biomass.md): the 60 rai own-grown coppice
idea (with the forestry-classification check that comes first), northern
agricultural waste as the main supply, reported northern fuel prices
(October 2026) and who sets them, and the staged electric-to-biomass path
- [BOI investment promotion](docs/boi.md): the promotion strategy (Group B
base activity plus solar, automation, and R&D measures for the tax value),
requirements, Northern-region angle, and why BOI approval precedes
machinery orders
- [Facility security and site systems](docs/facility-security.md): access
control, CCTV, whole-factory HVAC (temperature, humidity, PM), archive and
audio protection, fire and life safety, plant monitoring, Thai compliance
anchors
- [Overhead crane, workshop and visitor corridor](docs/crane-workshop-tours.md):
a 5 t crane over the whole production floor to move machines in and
out, a crane-served maintenance workshop and machine bay at the ramp
end, and a glazed ground-level corridor for guided tours without noise,
dust or plating chemistry; what each changes in the building and what
it costs
- [Production hall layout sketch](docs/production-hall-layout-sketch.png):
a rough BIM sketch in FreeCAD (`docs/production-hall-layout-sketch.FCStd`)
of the 60 x 25 m phase 1 hall at Mueang Chi, with the fleet before
October 2026: zones in process order along the visitor corridor, the
crane zone, room-in-room boxes and the main equipment; every position is
an estimate
- [Payap scenario model](docs/cnx_vinyl_parametric_payap.png): a parametric
BIM model in FreeCAD 26.3 (`docs/cnx_vinyl_parametric_payap.FCStd`,
[isometric](docs/cnx_vinyl_parametric_payap-iso.png)) of the whole plant
on a square placeholder plot of Payap land: a 128 x 25 m production-only
factory with the five-press fleet, room for ten more Classics, one
shared hydraulic and air plant, a colour store with outdoor silos and a
two-storey finishing and print block
([plans](docs/cnx_vinyl_parametric_payap-block.png)), a separate
two-storey office building
([floor plans](docs/cnx_vinyl_parametric_payap-office.png): canteen,
changing rooms and showers, mastering and listening below; ~150 m² of
offices, training room and IT above), a separate water treatment
building next to galvanics, the utility yard and site access, all
driven by one parameter sheet
- [Process logging and traceability](docs/traceability.md): end-to-end
per-order traceability for customers, batch genealogy from audio file to
shipment, and the requirements this sets for the factory software
- [Digital factory systems plan](docs/digital-factory.md): every system
that has to exist for environment, machine, QC and genealogy data to land
in one place keyed to one record identity, with ERPNext as the plant's
only system of record (every tool we build reads and writes it; only
machine data stays outside): the plant as one more site in B4L's
existing NixOS fleet (the cnx-network clan: mesh, DNS, fleet
monitoring, site gateway module, public proxy), what changes in that
repo, VLAN zoning, Telegraf/MQTT acquisition source by source, QC
instrument integration, the factory application, alerting, backup,
security, the data clauses for every RFQ, build order and rough cost
- [Quality automation](docs/quality-automation.md): stamper metrology
(Keyence-class confocal, profiler, XRF), layered pressed-record QC (100%
optical inspection, per-cycle press telemetry, sampled automated audio
comparison), and how it feeds traceability
- [Process flow](docs/process-flow.md): the whole chain from audio file to
delivered record as a chart and stage table, with every check and the
three artist approval gates (printable diagram alongside)
- [Artist platform](docs/artist-platform.md): upload a master and
artwork, get a transparent itemised offer from the price calculator
(for artists, labels and any other customer), and optionally launch a
fan-funded campaign that the plant presses and ships to each fan once
enough have pre-ordered, with refunds if not
- [Artist ordering demo](docs/artist-order.html): the artist platform as a
clickable single page: configure a record (jacket with a 3 or 5 mm
spine), type the track list or drop the master files and artwork
(checked in the browser, never uploaded: format, sample rate, bit
depth, clipping, side length against the format; artwork as PDF, AI or
image against the downloadable jacket and label templates: size and
spine, bleed, resolution, colour, fonts), approve gate 1, get the itemised offer with
its price curve and lead time, then order directly or run a fan-funded
campaign to a funded or missed end (refund, or go ahead at the
minimum) and follow the production through the three artist gates
- [Make a record](docs/make-a-record.html): the investor demo of the same
platform as a customer sees it, in one polished flow: design the record
against a to-scale mock-up, check the music and artwork, see the price,
let fans fund it, follow the production and open the record passport
(the traceability record of one copy); investor notes on every step and
a one-minute guided tour (`#tour`)
- [Factory console and order status](docs/factory-console.html): the
factory application of the [digital factory](docs/digital-factory.md)
plan as a demo on a simulated plant day: the press floor with live
counters, work orders per station (kiosk steps: badge in, scan,
confirm), the inspection stream, audio samples, the material lab gate,
stamper metrology, the hash-chained event log, and the customer portal
for the same orders (steps, copies pressed so far, lab and inspection
results, approving a test pressing)
- [Steam and cooling](docs/steam-cooling.html): the utility plant for the
five-press fleet as a clickable process diagram: water treatment, feed
tank and heat recovery, a bank of two 500 kg/h boilers, the steam header
and condensate return, and process cooling with three 250 kW chillers,
a plate heat exchanger, warm and cold tanks and a branch to every press,
extruder and the hydraulic oil cooler; operating cases from the launch
press to one module down, the design basis, an equipment schedule and
the open questions for the boiler and chiller RFQs
- [Plant operation page](docs/plant-operation.html): a single static page
animating the mature plant as a simulated SCADA overview at real cycle
times: the Newbilt Duplex and two Classic presses, the Pheenix Alpha
electroforming line and Sibert stamper prep, from PVC intake and the
material lab through pressing, inspection, packaging and fulfillment,
with the three artist gates, the mother archive, utilities and energy;
1× is real time, up to 3600× (a day in 24 s); every station is
clickable and names the source of its figures; on phones and tablets
held sideways it pinch-zooms and opens station details in a side sheet
- [Press fleet calculator](docs/fleet-calculator.html): a single static
page for the business plan: set the records a year and the share of
splatter and specials, and it sizes the mix of Duplex systems (3
records a minute each) and Classics (2 a minute) from the start fleet
of two Duplex and one Classic up to a full press hall, with the people,
power, central hydraulics, steam, cooling, air, floor, compound and
stampers that fleet needs, drawn as a live schematic of the machine
park with the stamper line (lathe, Pheenix galvanics, Sibert prep)
feeding it, each station counted from the galvanics cycle times;
plus the money a year: revenue (standard, specials, title services),
PVC, labels, sleeves, jackets, cartons, lacquers, plating chemistry,
electricity and steam, labour from base salaries with social security,
on-costs and health care for all staff, overheads, EBITDA, depreciation
and payback, with the revenue model's adverse, central and favourable
cases, BOI promotion on or off (machinery import duty and import VAT,
PVC duty relief) and USD, THB or EUR; every assumption is editable, with its
source, and a scenario can be shared by link
- [Test site](site/README.md): `site/` builds https://cnxvinyl.lol/, the
internal test site with demo pages from `docs/` (the plant operation
page first) and any static site we want to share by link; Gitea Actions
deploys it to the buildfor.life web server on every push that touches it
- [Production timeline](docs/production-timeline.md): how long an order
takes stage by stage, launch vs mature configuration, the repress fast
path, and what lead time can honestly be quoted to a customer
- [Project timeline](docs/project-timeline.md): the calendar from today to
first paying release, the BOI-to-machinery critical path, and where the
float actually sits
- [Site candidates](docs/site-candidates.md): the land options side by
side (the Mueang Chi lease, the Northern Region Industrial Estate, and
Payap University's offer of land next to a pharmaceutical facility under
construction) and what has to be checked before any of them is chosen
- [Payap University partnership](docs/payap-partnership.md): joint student
programmes in audio engineering (mastering, lathe cutting), IT and
business built around the plant, what they change in the plan (cutting
room earlier, pre-release security, student access) and what to agree
- [Project scale](docs/scale.md): rough numbers for everything on one page:
output capacity, building area, land, electrical demand, solar and
storage, steam and fuel, headcount, and money cross-references
- [Total investment](docs/finance/total-investment.md): the launch plant
decided in October 2026 (~161M to 292M THB, ~4.9M to 8.9M USD, midpoint
~227M THB) with the basis of every block, and the answer to the
investor's 180M / 216M THB question; the earlier full vision and phased
entry are kept as superseded
- [Phase 1 construction RFQ](docs/finance/phase1-construction-rfq.md):
the spec sheet for asking a contractor to price the phase 1 buildings
and site works, with quantities taken from the parametric BIM model
- [Revenue model](docs/finance/revenue-model.md): pricing, direct cost
and margin per record, the launch plant's operating picture (central
revenue ~3.75M USD a year, EBITDA ~1.6M, payback ~4 years on 216M THB;
the adverse case loses money), the five-press table, and the levers and
caveats behind the numbers
- [Business plan](docs/business-plan/CNX-Vinyl-Business-Plan.docx): the
investor-facing roll-up of everything above, built from
`docs/business-plan/build/` (run `python build_plan.py` to regenerate
after the numbers move; the PDF is exported with LibreOffice so the
table of contents is filled in). Draft 0.2 (October 2026) is built on
the launch plant: the whole chain at launch, the investor's budget
question, the launch plant's operating picture, the commissioning order
and its risks
## Repository Layout
```
docs/
├── brand/ Poy Records logo (1536 px PNG)
├── business-plan/
│ ├── CNX-Vinyl-Business-Plan.docx Investor business plan (generated)
│ └── build/ Python source of the plan; regenerate with
│ build_plan.py
├── consulting/ Consultancy proposals and overviews
├── equipment/
│ ├── newbilt/ Offers, site requirements, process schematic,
│ │ service rates, 2026 product flyers (vendor PDFs)
│ ├── oms/ OMS introduction letter: wet-room units, reference
│ │ prices, capacities, lathe contacts (vendor docx)
│ ├── pheenix-alpha/ Electroforming range flyers (vendor PDFs)
│ ├── sibert/ Stamper prep specifications and line-up drawing
│ │ (2021 issues in specs-2021/), 2008-09
│ │ optical-disc literature (vendor PDFs)
│ ├── duplex-cell-layout-sketch.png Duplex cell arrangement (sketch, not to scale)
│ ├── galvanics.md Electroforming and stamper prep equipment plan
│ └── pressing-line.md Press fleet strategy and equipment plan
├── finance/ Project cost overviews, revenue model,
│ construction RFQ, PEA electricity tariff
│ schedule (pea/), biomass fuel market
│ reports (biomass/)
├── suppliers/ Supplier contacts, vendor landscape, supplier map,
│ Chinese utility suppliers (china-utilities.md)
├── artist-order.html Artist ordering and fan-funding demo page
├── artist-platform.md Upload, price calculator, fan-funded pressing
├── biomass.md Biomass fuel strategy and the 60 rai coppice idea
├── boi.md BOI promotion strategy and requirements
├── cnx_vinyl_parametric_payap.FCStd Payap scenario parametric BIM model
├── cnx_vinyl_parametric_payap.png Top view of the Payap model
├── cnx_vinyl_parametric_payap-iso.png Isometric view of the Payap model
├── cnx_vinyl_parametric_payap-office.png Office building floor plans
├── cnx_vinyl_parametric_payap-block.png Finishing and print block plans
├── cnx_vinyl_parametric_payap_parts.FCStd Payap model in Part/Draft: roof, PV, parking canopies
├── cnx_vinyl_parametric_payap_parts.png Isometric view of the parts model
├── cnx_vinyl_parametric_payap_parts-top.png Top view of the parts model
├── CNX_apply_Params.FCMacro Pushes Params edits to the model (FreeCAD 26.3 RC1)
├── crane-workshop-tours.md Overhead crane, workshop, visitor corridor
├── digital-factory.md Data platform, NixOS/Clan fleet, acquisition, app
├── facility-security.md Security, HVAC, fire and life safety, compliance
├── factory-console.html Factory application and customer portal demo
├── fleet-calculator.html Press fleet calculator: output, mix, requirements
├── land-listings/ Land offers and zoning records (Mueang Chi, Payap)
├── make-a-record.html Artist platform investor demo (end-user flow)
├── payap-partnership.md Joint student programmes with Payap University
├── plant-operation.html Animated plant overview (simulated SCADA)
├── process-flow.md Audio file to delivered record, with all checks
├── production-hall-layout-sketch.FCStd Rough BIM sketch, Mueang Chi hall (earlier fleet)
├── production-hall-layout-sketch.png Top view of the sketch
├── production-timeline.md Order turnaround, stage by stage
├── project-timeline.md Calendar to first paying release, critical path
├── quality-automation.md Stamper metrology and layered record QC
├── roadmap.md Next steps in dependency order
├── scale.md Rough project sizing on one page
├── site-candidates.md Land options and the checks before choosing
├── steam-cooling.html Steam and cooling plant diagram, five-press fleet
├── sustainability.md Energy, water, materials commitments
├── traceability.md Process logging and per-order traceability
└── worker-safety.md Training, clean rooms, PPE
site/ Internal test site https://cnxvinyl.lol/
├── public/ Served as is: landing page, static sites
├── build.sh Builds site/dist: public/ plus demo pages from docs/
├── Caddyfile Virtual host for the web server (applied by hand)
└── README.md Build, deploy and one-time setup
.gitea/workflows/
└── deploy-site.yml Builds site/ and deploys it on push to master
```
Vendor PDFs and spreadsheets are primary sources and reflect the state of
negotiations at their file dates. Treat prices and lead times as snapshots,
not commitments.
## What This Repo Will Grow to Hold
- Accumulate planning and vendor documents as decisions firm up, including
the mastering, cutting, and galvanics chain
- Add structured data (inventory, orders, production batches) once operations
begin
- Host the software/tooling built to run the factory (tracking, ERP-style
workflows)