User (October 2026): we only build tools and interfaces that interact with ERPNext; invoices, stock and the rest are kept there, except telemetry and other machine data. digital-factory.md: standing decision, decisions 2, 3, 6, 7 and 10 rewritten (ERPNext holds every record of the business and of production, including artist gates, metal-part genealogy as serial numbers with parents, and quality inspections; the machine-data store keeps only cycle and record rows, the hash chain and time series, keyed to ERPNext names; ERPNext first, then custom fields or document types in cnx_erp, then a tool, never a second business database). Systems table, architecture labels, factory application section (modules as a table: records in ERPNext, what we build, machine data outside; our only tables are the machine-data ones), ownership table, integration rules 4 and 8, phasing and estimates (cnx_erp app 2 to 3 person-months; total 3.5 to 6). artist-platform.md: campaigns are an ERPNext document from launch, pledges post as advance payment entries; traceability, README, facility security (archive location on the serial number), production timeline (sets per mother on the mother's serial number), crane-workshop spares store, total-investment. Factory console: KPI row no longer touches the postings card (user screenshot); ERPNext page, order card, sidenote and ledger say every record lives in ERPNext and only machine data stays outside; new postings for artist gates, stamper metrology inspections, stamper set serial numbers (grown, retired with play count). Checked headless: Edge dark and light, 1440/1024/390, no overflow or page errors, rows aligned, pw_fc, pw_wo, pw_feed and pw_erp pass.
267 lines
14 KiB
Markdown
267 lines
14 KiB
Markdown
# Production Timeline: Order to Delivered Record
|
||
|
||
How long an order actually takes, stage by stage. This is the time
|
||
dimension of [process-flow.md](process-flow.md), which lists all nine
|
||
stages and every check but no durations.
|
||
|
||
The repo asserts turnaround as the core regional advantage in four
|
||
places — "competes on turnaround and freight against EU/US plants",
|
||
"in-house galvanics removes days of turnaround", "validate turnaround
|
||
against the regional pitch", "get a written turnaround SLA" — without
|
||
ever putting a number on it. This page puts numbers on it so the claim
|
||
can be tested at Making Vinyl instead of repeated.
|
||
|
||
**Every figure is an estimate** from industry norms and this repo's own
|
||
equipment data. Nothing is vendor-confirmed and no order has ever run
|
||
through this plant. Durations are **working days** unless stated;
|
||
divide by 5 for weeks, and note that Thai public holidays run to
|
||
16–20 days a year, clustered heavily around Songkran in April.
|
||
|
||
## The headline
|
||
|
||
| Configuration | Plant-controlled | Including customer gates |
|
||
|---|---|---|
|
||
| **Launch** (bridge stampers, no in-house cutting or galvanics) | 22–49 days | **~6 to 17 weeks** |
|
||
| **Mature** (full chain in-house) | 11.5–22 days | **~4 to 11.5 weeks** |
|
||
| **Repress** from an archived mother, no changes | 6.5–11.5 days | **~1.5 to 2.5 weeks** |
|
||
|
||
These are straight sums of the stage table below, plus 9–35 days of
|
||
customer gate time for the first two rows. They are wide because the
|
||
stages are wide, and they are not a quotable lead time — see "What to
|
||
promise a customer" at the end, which adds queue and buffer on top.
|
||
|
||
Reported EU/US plant lead times run roughly **10 to 16 weeks** for a
|
||
standard black LP, down from the 6-to-9-month peak of 2021–22. That
|
||
figure is an industry impression gathered in conversation, not a
|
||
surveyed one, and it should be tested at Making Vinyl alongside the
|
||
price. One published data point: Record Industry (Haarlem, NL) quotes
|
||
**3 weeks to test pressings** (from complete files, or from a supplied
|
||
lacquer's arrival) and then **9 to 11 weeks** for the finished order
|
||
after the customer approves the test pressings and the artwork
|
||
(calculator FAQ, checked October 2026), which on the same reference
|
||
point compares with the 7 to 9 week mature quote below. Two cautions on the comparison:
|
||
|
||
- **It is not like-for-like.** The EU/US figure is a *quoted* lead time
|
||
carrying queue and buffer; the CNX figures above are unbuffered stage
|
||
sums. The honest comparison is against the quote table at the end of
|
||
this page — 7–9 weeks mature, 10–14 launch.
|
||
- **On that basis the launch configuration is at parity, not ahead.**
|
||
Its 10–14 week quote sits inside the EU/US 10–16 week band, and its
|
||
unbuffered worst case of 17 weeks is beyond it. The regional advantage
|
||
comes from freight and time zone at launch, and only becomes a
|
||
manufacturing advantage once cutting and plating come in-house. That
|
||
matters, because launch is what the first two years actually sell.
|
||
|
||
**Bringing cutting and galvanics in-house takes roughly 1.5 to 5 weeks
|
||
out of the lead time** — replacing a 13–27 day outsourced metal block
|
||
plus freight with 4–7 days of in-house cutting, plating and stamper
|
||
prep. The spread is wide because the outsourced block is the part
|
||
nobody has measured. That is the commercial case for the galvanics line
|
||
stated in time rather than in the stamper cost that
|
||
[revenue-model.md](finance/revenue-model.md) counts separately.
|
||
|
||
## Two tracks run in parallel
|
||
|
||
A full-service order is not one chain. The metal path and the packaging
|
||
path run concurrently and converge at assembly, and **the packaging path
|
||
is the one that most often slips**, because it waits on artwork the
|
||
customer owes and on a print partner who is not us.
|
||
|
||
```mermaid
|
||
flowchart LR
|
||
subgraph M[Metal and record path]
|
||
A[Audio intake] --> B[Mastering] --> C[Cutting]
|
||
C --> D[Galvanics] --> E[Stamper prep] --> F[Test pressing]
|
||
F --> G[Production run] --> H[Finishing]
|
||
end
|
||
subgraph P[Packaging path]
|
||
X[Artwork received] --> Y[Proof and Delta E approval]
|
||
Y --> Z[Carton and sleeve print run]
|
||
end
|
||
H --> I[Assembly and packaging]
|
||
Z --> I
|
||
I --> J[Fulfilment]
|
||
```
|
||
|
||
Printed jackets from a local carton partner typically need **10 to 20
|
||
working days** from approved artwork. That fits comfortably underneath
|
||
the metal path, but only if artwork lands early. When a label delivers
|
||
artwork after approving the test pressing, the jackets become the
|
||
critical path and every day of metalwork saved is wasted.
|
||
|
||
**Consequence for the order intake process:** artwork deadline is
|
||
effectively a fourth approval gate and should be contracted as one,
|
||
alongside the three artist gates in
|
||
[process-flow.md](process-flow.md). It is not currently modelled as a
|
||
gate anywhere in the repo.
|
||
|
||
## Stage by stage
|
||
|
||
Times below are elapsed scheduled duration for one title, not touch
|
||
labour. The "launch" column reflects the phased entry in
|
||
[total-investment.md](finance/total-investment.md): bridge stampers from
|
||
Stamper Discs, lacquer cutting brokered through their EU partners or
|
||
bought direct (SST in Frankfurt already cuts for Poy Records, see the
|
||
[vendor landscape](suppliers/vendor-landscape.md#lacquer-cutting-service-schallplatten-schneid-technik-germany)),
|
||
and no mastering room of our own.
|
||
|
||
| # | Stage | Launch | Mature | Notes |
|
||
|---|---|---|---|---|
|
||
| 1 | Audio intake and technical QA | 1–2 | 1–2 | Checksums, format, levels, side-length vs format. Rejects here are cheap; rejects later are not |
|
||
| - | **Gate: master plan approved** | *customer* | *customer* | 2–10 days in practice |
|
||
| 2 | Vinyl mastering | 3–7 | 2–4 | Launch: external engineer or partner. Mature: in-house room, and queue depth becomes ours to manage |
|
||
| - | **Gate: master approved** | *customer* | *customer* | 2–10 days; more if the artist wants revisions |
|
||
| 3 | Lathe cutting to lacquer | - | 1–2 | Includes test cut, groove microscope, dead-wax scribe |
|
||
| 4 | Silvering and electroforming | - | 2–4 | Three generations plus XRF, metrology, mother listening check |
|
||
| 5 | Stamper prep | - | 1 | Punch, back-finish, coin, concentricity |
|
||
| 3–5 | **Outsourced cut + metal** (launch only) | 10–20 | - | Stamper Discs, Sheffield; queue is theirs, not ours |
|
||
| - | **Stamper freight UK → TH + customs** | 3–7 | - | Air freight; nickel travels well, unlike lacquer |
|
||
| 6 | Press setup and test pressing | 1 | 0.5–1 | Mold change, stamper mount, warm-up, 10–20 TPs |
|
||
| - | **TP to artist + gate: TP approved** | *5–15* | *5–15* | Courier plus listening time. The single largest customer-side block |
|
||
| 7 | Production run | 1–5 | 1–3 | Throughput table below |
|
||
| 8 | Finishing, assembly, packaging | 2–4 | 2–3 | Trim is inline; shrink and jacket assembly are labour-bound |
|
||
| 9 | Fulfilment and dispatch | 1–3 | 1–2 | Bulk pallet, or per-parcel dropship on an ongoing basis |
|
||
|
||
Two things the table deliberately does not hide:
|
||
|
||
- **Stages 3, 4 and 5 collapse into one 10–20 day external block at
|
||
launch**, and its duration is not ours to control. That is precisely
|
||
why [roadmap.md](roadmap.md) item 14 calls for a **written turnaround
|
||
SLA** with Stamper Discs. Without one, the whole quoted lead time
|
||
rests on a supplier's goodwill, and they have no documented Asian
|
||
customers to set expectations from.
|
||
- **Lacquers do not fly.** A cut lacquer is soft nitrocellulose, heat-
|
||
and shock-sensitive, and wants plating within roughly 24 to 72 hours.
|
||
The launch configuration is sound precisely because it never ships
|
||
one: audio goes to Europe as a file, the lacquer is cut and plated in
|
||
the same region, and only finished nickel stampers make the journey.
|
||
Any future arrangement that cuts in Thailand and plates abroad, or
|
||
the reverse — would be a quality risk, not just a slower schedule.
|
||
|
||
## Production run throughput
|
||
|
||
From the fleet assumptions in [scale.md](scale.md), after the 60–70%
|
||
overall effectiveness already applied there.
|
||
|
||
| Fleet | Good records/day | 300 units | 500 | 1,000 | 2,000 |
|
||
|---|---|---|---|---|---|
|
||
| Launch: 1 semi-auto, 1 shift | ~300–450 | <1 day | 1–2 | 2–3 | 5–7 |
|
||
| Duplex: 2 semi-auto, 2 shifts | ~1,150–1,790 | <1 | <1 | 1 | 1–2 |
|
||
| Mature: 2 semi + 2 auto, 2 shifts | ~3,300–5,000 | <1 | <1 | <1 | <1 |
|
||
|
||
Read these as **press-days, not calendar days**. At mature scale no
|
||
single title gets the whole plant; it gets a scheduled slot. Past
|
||
roughly 60% utilisation the queue in front of the press starts to
|
||
dominate everything in the table above it, and quoted lead time
|
||
decouples from process time entirely.
|
||
|
||
That is the standard failure mode for pressing plants and it is worth
|
||
stating plainly: **lead time is a capacity decision, not a process
|
||
decision.** A plant running at 90% quotes 16 weeks with the same
|
||
equipment that quotes 6 weeks at 50%. Any turnaround promise made to
|
||
the market is implicitly a promise to hold spare capacity.
|
||
|
||
Small runs invert the arithmetic, though not as sharply as it first
|
||
looks. At 300 units on the semi-automatic line the run is **5 to 8
|
||
hours**, most of a shift, once the 60–70% effectiveness above is
|
||
applied; it is roughly an hour on the full mature fleet. What dominates
|
||
a small order is not the pressing but the setup, the approvals and the
|
||
assembly, all of which cost the same at 300 units as at 3,000, which
|
||
is exactly the boutique/color work the semi-automatic
|
||
line exists to serve, per
|
||
[pressing-line.md](equipment/pressing-line.md). Small runs are not
|
||
faster to deliver; they are only cheaper to press.
|
||
|
||
## Repress: the shortest path in the plant
|
||
|
||
A repress of an existing title with no artwork or audio changes skips
|
||
stages 1 through 3 and all three artist gates. If a **mother** was
|
||
archived, a fresh stamper is pulled and the order runs:
|
||
|
||
| Step | Days |
|
||
|---|---|
|
||
| Pull stamper from archived mother | 1–2 |
|
||
| Stamper prep | 1 |
|
||
| Press setup, first-article check | 0.5 |
|
||
| Production run (1,000) | 1–3 |
|
||
| Finishing, assembly, dispatch | 3–5 |
|
||
| **Total** | **~7–11 working days** |
|
||
|
||
Two commercial consequences worth acting on:
|
||
|
||
- **Choose the 3-step process and archive fathers and mothers.** Stamper
|
||
Discs offers both 1-step and 3-step. A 1-step stamper is faster and
|
||
cheaper for a one-off, but it is a single-use part: there is no mother
|
||
to go back to, so a repress restarts at lacquer cutting and costs the
|
||
customer six weeks and a new cutting fee. 3-step buys the two-week
|
||
repress, and that repress is the highest-margin order the plant will
|
||
ever take. Decided (October 2026): the plant keeps the **father as well
|
||
as the mother** of every side.
|
||
- **How many represses a mother carries.** The common rule of thumb is
|
||
about **10 stamper sets per mother** before it degrades (Third Man
|
||
Pressing's FAQ; a Nashville plater quoted by WPLN, both checked October
|
||
2026); quality-minded sources give fewer: 5 (The VinyLab), 6 to 8
|
||
(Stereo Review, 1962, quoted on pspatialaudio.com). At 1,000 to 2,000
|
||
pressings a stamper that is roughly 10,000 to 20,000 records per side,
|
||
or about ten represses of a few hundred to 1,500 copies. A father grows
|
||
about 5 to 10 mothers (pspatialaudio.com; Third Man: up to 10), so with
|
||
the father archived a worn mother is replaced by plating a new one
|
||
(about an hour in the bath plus the listening check) instead of
|
||
re-cutting, and a title reaches roughly 50,000 to 100,000 records
|
||
before a new lacquer. These are industry rules of thumb, not this
|
||
plant's figures: the galvanics vendors are asked for theirs
|
||
([galvanics](equipment/galvanics.md#open-questions-for-the-quotes)), and
|
||
ERPNext counts stamper sets on each mother's serial number.
|
||
- **The archive is an asset with a shelf life.** It needs the
|
||
storage conditions and the genealogy records that
|
||
[traceability.md](traceability.md) already specifies, and a stated
|
||
retention policy: how long a customer's fathers and mothers are kept before
|
||
they are scrapped or returned. That policy does not exist yet and
|
||
should be in the customer contract, not discovered later.
|
||
|
||
## What to promise a customer
|
||
|
||
A defensible quoted lead time is **not** the sum of the mature column.
|
||
It carries queue and it carries a buffer, and it should be quoted from
|
||
the last customer gate, not from order date — the plant cannot be held
|
||
to a clock the customer keeps stopping.
|
||
|
||
| Order type | Quote | Basis |
|
||
|---|---|---|
|
||
| New title, full service, launch config | **10–14 weeks** | Stage sum plus external metal queue plus buffer |
|
||
| New title, full service, mature config | **7–9 weeks** | |
|
||
| New title, customer supplies jackets | **−1 to 2 weeks** | Removes the print path |
|
||
| Repress from archived mother | **2–3 weeks** | |
|
||
| Rush slot | **premium, capped per month** | Only credible with reserved capacity |
|
||
|
||
Quote in weeks from **test-pressing approval**, with the pre-approval
|
||
stages quoted separately as "typically X weeks, subject to your
|
||
approvals". Every plant that quotes from order date and gets caught by
|
||
a slow artist ends up explaining itself.
|
||
|
||
The price calculator on the [artist platform](artist-platform.md) quotes
|
||
from this table in exactly this form, and a fan-funded campaign shows its
|
||
fans an estimated ship month built the same way: campaign close, plus the
|
||
typical pre-approval stages, plus the quote above.
|
||
|
||
## Honest caveats
|
||
|
||
- **No order has ever run through this plant.** These are planning
|
||
numbers built from vendor throughput data and industry norms, and
|
||
early production will run slower than any of them while the reject
|
||
rate settles — [revenue-model.md](finance/revenue-model.md) already
|
||
concedes the same about its 5–10% reject allowance.
|
||
- **The external metal block at launch is unmeasured.** 10–20 days is
|
||
an industry-typical figure, not a Stamper Discs commitment. Get it in
|
||
writing before it appears in a customer quote.
|
||
- **Equipment lead times are absent from the repo entirely** and do not
|
||
affect this page, but do affect
|
||
[project-timeline.md](project-timeline.md), which is where they
|
||
matter.
|
||
- **The competitive comparison is the least validated part.** Whether
|
||
regional labels will actually pay for 7 weeks instead of 14 plus
|
||
freight is the same open question as the 3.50–4.60 USD blended price,
|
||
and both should be tested in the same conversations at Making Vinyl.
|
||
A turnaround advantage nobody pays a premium for is a cost, not a
|
||
moat.
|