Deploy test site / deploy (push) Successful in 52s
User (October 2026): "lets say 60+% special prints" (the plant focuses on special prints, not mono colours). - Specials (splatter, marble, colour effects) run only on the Duplex systems, so at 60 % the Duplex sets the launch plant's output: ~0.58 / 0.74 / 0.90M records a year (was 0.71 / 0.84 / 0.97 at ~20 %), the Classic at about two thirds load. Full 60/40 hall: ~2.3 to 3.6M (Duplex -limited, Classics about half loaded); five-press fleet unchanged. A hall balanced by output at 60 % would give Duplex ~70 to 75 % of the floor (estimate; noted, not applied). - Blended price 3.76 / 4.49 / 5.27 USD (standard 3.40 / 3.80 / 4.25 plus the 0.60 / 1.15 / 1.70 specials premium on 60 %). Launch operating picture: revenue 2.28 / 3.65 / 5.41M USD, EBITDA 0.23 / 1.73 / 3.79M, operating profit -0.66 / 1.21 / 3.46M, payback ~3.8 yr central, break-even ~0.25M records; adverse needs ~1.1M records to cover depreciation. Specials' extra direct cost (coloured compound, purge, trim only into black) is not in the cost table yet: flagged as an upper bound until compound quotes. - Calculator default specials share 20 -> 60 % (planning rates keep the launch plant balanced at 850k: revenue 4.14M, EBITDA 2.07M, payback 3.3 yr, cash payback year ~4.8, IRR ~18 %). - revenue-model.md, scale.md, pressing-line.md, README; business plan draft 0.2 rebuilt (sections 1, 4, 9, risks). Checks: calculator regression 0 fails, no page errors, node --check on all scripts; PDF 47 pages, table of contents filled; no em dashes added.
392 lines
23 KiB
Markdown
392 lines
23 KiB
Markdown
# Project Scale: Rough Numbers
|
||
|
||
One-page sizing of the whole project. Everything here is a planning
|
||
estimate derived from the session's vendor data and standard ratios;
|
||
figures marked "estimate" have no vendor confirmation yet. Update this
|
||
page as real quotes and the site decision land.
|
||
|
||
## Production capacity
|
||
|
||
| Phase | Fleet | Rough output |
|
||
|---|---|---|
|
||
| Launch plant (decided October 2026) | 2 semi-auto (Duplex system 1: EX 50 main + EX 35 colour extruder) + 1 automated (Newbilt Classic), commissioned in sequence, 2 shifts at volume | ~0.58 to 0.90 million records/yr at the planned 60 % specials (Duplex-limited); ~0.71 to 0.97 million at ~20 % |
|
||
| Growth option: second Duplex | 4 semi-auto (two Duplex systems) + 1 Classic, 2 shifts; room reserved, not in the investment | ~1.0 to 1.5 million records/yr |
|
||
| Full hall (option) | 4 Duplex systems + 6 Classics, the hall laid out 60/40 for Duplex, 2 shifts | ~2.3 to 3.6 million records/yr at 60 % specials, ~3.6 to 4.7 million at ~20 % (estimate) |
|
||
|
||
The [press fleet calculator](fleet-calculator.html) sizes the fleet for
|
||
any yearly output and specials share, with the people and utilities it
|
||
needs; at the user's planning rates (3 records a minute per Duplex
|
||
system, 2 per Classic, 65 % effectiveness, two shifts) the launch plant
|
||
makes ~0.94 million records a year, the five-press fleet ~1.5 million and
|
||
a full Payap press hall (two Duplex systems and eleven Classics) ~5.2
|
||
million.
|
||
|
||
**Launch plant (October 2026).** The plant launches with one Duplex
|
||
system and one Classic, with cutting and galvanics in-house
|
||
([total investment](finance/total-investment.md#launch-plant-october-2026)).
|
||
Its utilities: steam 450 to 540 kg/h on boiler modules B-1 and B-2, cooling
|
||
~390 kW at the hot-afternoon peak on chillers CH-1 and CH-2 (2 × 250 kW),
|
||
with the boiler hall, chiller compound and ring mains built for the
|
||
larger fleet as in [utility phasing](#utility-phasing-backbone-once-modules-with-the-presses).
|
||
The building, electrical and steam sections below still size the
|
||
five-press fleet that the backbone is built for.
|
||
|
||
Basis: the fleet plan of October 2026
|
||
([pressing line](equipment/pressing-line.md)). Launch plant: two
|
||
semi-automatic presses at 60 to 80 records/hour each plus the Classic at
|
||
~128/hour, 248 to 288 records/hour, with 60 to 70 % effectiveness ~149 to
|
||
202 an hour, 0.71 to 0.97 million a year on the same 16 h and 300 days.
|
||
Five-press fleet: The automated Classic
|
||
~128 records/hour (28 s cycle, vendor flyer); semi-automatic throughput is
|
||
unpublished, assumed 60 to 80 records/hour per press with operator
|
||
handling (estimate); 16 h/day, 300 days/yr, with realistic overall
|
||
effectiveness of 60 to 70% applied: 368 to 448 records/hour, ~1.06 to 1.5
|
||
million a year. The theoretical ceiling of the mature fleet at 100% uptime
|
||
is roughly 1.8 to 2.2 million records per year. (The earlier 50/50 fleet,
|
||
two semi-automatic presses and two Pheenix AD12s, landed in the same
|
||
range.) The full-hall row is an option the plant keeps room for, not a
|
||
plan: the press hall is laid out 60/40 by floor for Duplex systems, since
|
||
the plant focuses on special pressings
|
||
([pressing line](equipment/pressing-line.md)). Eight semi-automatic
|
||
presses and six Classics give 1,250 to 1,410 records/hour gross, ~3.6 to
|
||
4.7 million a year on the same basis, and neither the
|
||
[revenue model](finance/revenue-model.md) nor the investment includes
|
||
them.
|
||
|
||
**Specials share 60 % and more (October 2026).** Specials run only on the
|
||
Duplex systems, so at 60 % they set the output wherever the Duplex makes
|
||
less than 60 % of the fleet's records: the launch plant drops to ~0.58 to
|
||
0.90 million (the Classic runs at about two thirds load) and the full
|
||
hall to ~2.3 to 3.6 million (the six Classics about half loaded). The
|
||
five-press fleet is not affected. At the planning rates of the
|
||
[calculator](fleet-calculator.html) (3 a minute per Duplex system) the
|
||
launch plant stays balanced at ~0.94 million. A hall balanced by output
|
||
at 60 % specials would give the Duplex systems ~70 to 75 % of the floor
|
||
(estimate), e.g. five Duplex bays and four Classic positions.
|
||
|
||
**The 60–70% effectiveness assumption is worth challenging, but not yet
|
||
changing.** Newbilt publishes ≥95% yield and ≥95% uptime for the Classic
|
||
12" automatic at a 28 s cycle (~128 records/h), and quotes ~30 s average
|
||
for the Duplex. Three reasons not to adjust anything on that basis:
|
||
|
||
- **Machine uptime is not plant OEE.** A vendor uptime figure excludes
|
||
stamper and mould changes, label reels, colour changeovers, PVC lot
|
||
changes, first-article QC and breaks — precisely the losses that
|
||
dominate a short-run boutique plant. They are different quantities.
|
||
- It would apply only to the **automated press** (the Classic). The
|
||
60–80/h semi-auto figure already embeds operator handling, so applying
|
||
an uplift to that half would double-count.
|
||
- 0.95 × 0.95 is 0.90 before any performance factor; reaching 80% OEE
|
||
needs a performance factor near 0.89, which nobody has estimated.
|
||
|
||
Ask both press vendors for the **basis** of their uptime and yield
|
||
figures — measured over what period, at what run length, counting which
|
||
stoppages — as part of the re-quote. It is a free question. If the
|
||
figures survive scrutiny they would argue for a higher OEE on the
|
||
automated fleet only, and the same logic would apply to any competitor
|
||
running the same machine.
|
||
|
||
## Building
|
||
|
||
| Zone | Rough area |
|
||
|---|---|
|
||
| Semi-auto press hall (Newbilt Duplex spec) | ~200 m² |
|
||
| Automated press zone | ~100 to 150 m² |
|
||
| Galvanics clean room + water treatment + chemical storage | ~80 to 150 m² |
|
||
| Mastering and cutting room | ~40 to 60 m² |
|
||
| Stamper prep | ~30 m² |
|
||
| Packaging + finished goods warehouse | ~300 to 500 m² |
|
||
| Utility rooms (boiler, compressor, chiller, electrical) | ~100 to 150 m² |
|
||
| Offices, QC/listening, archive, IT, entrance | ~150 to 200 m² |
|
||
| Maintenance workshop and machine bay (crane-served) | ~100 to 150 m² |
|
||
| Visitor corridor (glazed, ground level) | ~110 to 130 m² |
|
||
| Circulation, walls, misc | ~150 to 250 m² |
|
||
| **Total under roof** | **~1,400 to 2,000 m²** |
|
||
|
||
The HVAC budget in the utilities CSV already assumes ~1,500 m² conditioned.
|
||
Single story throughout: all heavy equipment needs ground-slab floor
|
||
loading (multiple tons per m²).
|
||
|
||
The workshop and the visitor corridor were added in October 2026, together
|
||
with an overhead crane over the production compartment; what they need and
|
||
what they change in the shell is in
|
||
[crane, workshop and tours](crane-workshop-tours.md). They add ~210 to
|
||
280 m² to a program that already filled the 60 × 25 m footprint, which
|
||
settles the open question below in favour of growing the program into the
|
||
floor the utility yard frees: at the lower half of the table everything
|
||
fits; at the upper half, finished goods move to the phase 2 building.
|
||
|
||
### Detached utility yard, parking, and what that moves
|
||
|
||
The massing model puts the boiler and chiller in a **detached utility yard**
|
||
alongside the main building rather than inside it, which is what the boiler's
|
||
own-room requirement in [facility security](facility-security.md) and biomass
|
||
fuel delivery both push toward. Its rooms are built once for **four boiler
|
||
and four chiller modules** (decided October 2026), while the modules
|
||
themselves arrive one press stage at a time
|
||
([utility phasing](#utility-phasing-backbone-once-modules-with-the-presses)):
|
||
|
||
| | Area | Height |
|
||
|---|---|---|
|
||
| Boiler hall, four 500 kg/h module positions | ~162 m² (18 × 9 m) | 6.0 m |
|
||
| Biomass fuel store | 42 m² | 5.0 m |
|
||
| Chiller compound, four 250 kW pads, open to the sky, screened | ~135 m² (12.5 × 10.8 m) | screen ~2.5 m |
|
||
| Cooling pump and heat-exchanger room | ~40 m² (8 × 5 m) | 4.0 m |
|
||
| Flue stack | - | 14 m |
|
||
|
||
All sizes are estimates until the boiler and chiller vendors send
|
||
footprints:
|
||
|
||
- **Boiler hall.** The fuel is still open, so the fired case sets the
|
||
size. The largest piece of a 500 kg/h biomass boiler is about
|
||
3.3 × 2.0 × 2.7 m (AIX DZL0.5 listing, checked October 2026). Four
|
||
3.5 m bays plus a 4 m bay for the feed tank, softener, feed pumps and
|
||
steam header make 18 m. A 2.5 m firing aisle, 1.5 m of fuel feed, the
|
||
boiler and 1.3 m behind it make 9 m. Dust collectors, fans and the stack
|
||
stand outside along the back wall. An electric bank (~3.0 × 1.5 m per
|
||
500 kg/h module, vendor listing) would need about half the hall.
|
||
- **Chillers.** Air-cooled chillers need open air, so the earlier
|
||
"chiller room" becomes an open, screened compound plus a small enclosed
|
||
room for the heat exchanger, the cold tank and the pumps. A 250 kW
|
||
module rated at 40 °C is about the size of a Carrier 30RB 080 to 090:
|
||
2.4 to 3.6 × 2.24 × 2.28 m (Carrier's published dimensions, checked
|
||
October 2026). The pads are 4.0 × 2.6 m, in two rows of two, with
|
||
~1.8 m to the screen and 2.0 m between the rows; the chosen unit's
|
||
clearance drawing governs. The cooling tower pad of the earlier
|
||
water-cooled concept is gone; a dry cooler, if bought, gets a pad sized
|
||
with its quote.
|
||
- **What four positions carry.**
|
||
- Steam: four boilers give 2,000 kg/h, or 1,500 kg/h with one held in
|
||
reserve, enough for about eight presses at 180 kg/h. The five-press
|
||
fleet runs on B-1 and B-2, B-3 is the reserve, and B-4 is room for
|
||
about three more presses.
|
||
- Cooling: four chillers give 1,000 kW. The five presses (~652.5 kW)
|
||
already need three, so CH-4 is the reserve and there is no growth
|
||
position. Each further press adds ~130 kW with its extruder and
|
||
hydraulics; a sixth eats into the reserve, and seven is the limit with
|
||
none.
|
||
- Pads laid out for the next frame up (Carrier 30RB 120 to 150 class,
|
||
~4.8 m long, roughly 350 kW at 40 °C, estimate) would let four
|
||
chillers carry about eight presses with one in reserve, matching the
|
||
boiler hall. That is a priced option for the chiller RFQ.
|
||
|
||
The yard grows from 178 m² to ~379 m². The old 126 m² of boiler hall and
|
||
chiller room fitted the 100 to 150 m² the zone table allows for them in the
|
||
main building; the four-module rooms would not, which is one more reason the
|
||
yard stays detached. Moving the plant out frees that zone-table floor for
|
||
production, so either the main building shrinks by that much or the program
|
||
grows into it. Decide which before the building is priced. The
|
||
[Payap parts model](site-candidates.md#roof-pv-and-parking-canopies-part-and-draft-model-october-2026)
|
||
draws the yard this way.
|
||
|
||
Staff parking is roofed, in the front yard clear of the loading route:
|
||
**10 car bays** (27.7 × 7.0 m canopy, 195 m²) and **~30 scooter spaces**
|
||
(13.7 × 5.5 m, 76 m²), carrying a further **~40 kWp** of PV on their
|
||
canopies — dimensions per the modelled layout in the
|
||
[construction RFQ](finance/phase1-construction-rfq.md). At 4.1 m and 3.5 m
|
||
they sit below the main building's 7.0 m low eave, so they cannot shade it.
|
||
Fully covered with the 580 W placeholder module the two canopies take 94
|
||
modules (~54 kWp); see the Payap parts model in
|
||
[site candidates](site-candidates.md#roof-pv-and-parking-canopies-part-and-draft-model-october-2026).
|
||
|
||
### Expansion headroom: a second building
|
||
|
||
Tested against the candidate Mueang Chi parcel, in the massing model at
|
||
`factory_building_rough.FCStd`. The whole zone table above fits inside one
|
||
60 × 25 m building, so a second one is expansion **beyond** the current
|
||
program — doubling pressing capacity, or moving finished goods out to free
|
||
production floor — not a gap in it.
|
||
|
||
| | Phase 1 | Phase 2 | Total |
|
||
|---|---|---|---|
|
||
| Footprint | 60 × 25 m — 1,500 m² | 45 × 38 m — 1,710 m² | 3,210 m² |
|
||
| Roof PV | ~247 kWp | ~251 kWp | **~498 kWp** |
|
||
| Tightest boundary clearance | 15.7 m | 3.0 m | |
|
||
|
||
- **45 × 38 m is the sweet spot.** The plot narrows going south, so past
|
||
~45 m of length the width falls away faster than length adds: 40 m gives
|
||
1,607 m², 45 m gives 1,723 m², 50 m drops to 1,558 m², and beyond 65 m
|
||
nothing useful fits.
|
||
- **A 20 m yard** between the buildings covers fire separation and shared
|
||
loading off the phase 1 circulation road.
|
||
- **Roof form: two-bay sawtooth, shaded rows deliberately left empty.**
|
||
A single 38 m monopitch would be the best solar answer — 28 panel rows,
|
||
none shaded, ~17% more yield than what is drawn, but it needs a **13.7 m**
|
||
high wall. The sawtooth holds the high side to **10.35 m**, at a cost: each
|
||
bay falls toward ESE onto the next bay's 3.35 m riser, so the bottom rows
|
||
sit in shadow (the lowest is blocked below a 53° sun profile angle). Those
|
||
two rows on the first bay are left empty rather than populated, which
|
||
trades ~8% of the roof's yield for clean strings, no mismatch losses, and
|
||
a maintenance walkway. Building height won this trade; revisit it if
|
||
cladding a 13.7 m wall turns out cheaper than the lost generation.
|
||
A 7° single pitch (11.7 m high side) sits between the two if wanted.
|
||
- **Coverage stays comfortable**: 3,210 m² is 39% of the deed area (34% of
|
||
the mapped extent), well under the 50 to 60% typically allowed.
|
||
- **The two roofs together clear 500 kWp**, which removes the need for the
|
||
ground-mount solar assumed further down this page.
|
||
|
||
Two caveats. Phase 2's tightest corner sits **3.0 m** from the boundary and
|
||
must be checked against the local ผังเมือง setback rule before it is taken as
|
||
real. And the plot's zoning for factory use is still unverified — that gates
|
||
phase 1 every bit as much as phase 2.
|
||
|
||
## Land: factory plot
|
||
|
||
Industrial plots typically allow 50 to 60% building coverage, and the site
|
||
needs truck access and turning, parking, the outdoor cooling tower, the
|
||
separated BESS enclosure, possible ground-mount solar, and expansion room.
|
||
|
||
- Minimum workable: **~4 rai** (6,400 m²)
|
||
- Comfortable with expansion and ground-mount solar: **~6 to 8 rai**
|
||
(9,600 to 12,800 m²)
|
||
|
||
Separate asset: the **60 rai** forestry-classified parcel for coppice
|
||
fuelwood (see [biomass](biomass.md)), pending its title check. It is a fuel
|
||
plantation, not a factory site candidate unless the classification allows
|
||
conversion, which forestry land generally does not.
|
||
|
||
## Electrical scale
|
||
|
||
| Load | Rough figure |
|
||
|---|---|
|
||
| Pressing machinery (two Duplex systems + the Classic, central hydraulics) | ~118 kVA connected, ~73 kW average while running (Newbilt per-machine figures; the EX 35 and the Classic counted like the EX 50 and an HRP 12 until published) |
|
||
| Chiller bank (up to ~650 kW cooling) | ~210 to 325 kW electrical at the peak (~80 to 125 kW per 250 kW of cooling, air-cooled, hot season; estimate) |
|
||
| Whole-factory HVAC | ~100 to 200 kW peak (estimate) |
|
||
| Electric steam boiler bank (if chosen over biomass/LPG) | ~520 to 625 kW for 750 to 900 kg/h |
|
||
| Compressed air, lighting, IT, misc | ~30 to 50 kW |
|
||
| **Plant peak demand** | **~430 to 700 kW without electric boiler; ~950 to 1,330 kW with it** |
|
||
|
||
Grid connection: a medium-voltage connection from PEA with a transformer in
|
||
the **800 to 1,000 kVA** class without electric steam, **1,250 to 1,600 kVA**
|
||
with it; past 1,000 kW of demand the plant moves to PEA Schedule 4, whose
|
||
time-of-use rates are the same.
|
||
|
||
**Re-based for the five-press fleet** (October 2026; the concept is drawn
|
||
in [steam and cooling](steam-cooling.html)). At Newbilt's per-machine
|
||
figures the two Duplex systems and the Classic need 750 to 900 kg/h of
|
||
steam and up to ~650 kW of cooling (625 kW presses, 15 kW extruders, 12.5
|
||
kW hydraulic oil cooler) at 305 to 540 l/min of circulating water. The
|
||
peak rows assume all five presses cooling hard on a hot afternoon; the
|
||
Classic counts as one HRP 12 press plus one extruder until Newbilt states
|
||
its figures. The presses share one central hydraulic plant and one
|
||
compressed-air plant. The optional full hall (four Duplex systems and six
|
||
Classics, fourteen presses) would need up to ~1.8 MW of cooling and ~2.1
|
||
to 2.5 t/h of steam: a utility phase of its own.
|
||
|
||
Tariff: PEA Schedule 3.2.2, Medium General Service on time of use at
|
||
22 kV (the flat rate is closed to new customers): 132.93 THB/kW demand
|
||
charge on the peak-hour maximum, 4.1839 THB/kWh peak (09:00 to 22:00 on
|
||
weekdays) and 2.6037 THB/kWh off-peak, plus Ft (0.1623 THB/kWh for
|
||
September to December 2026) and VAT. Two-shift production lands at a
|
||
blended ~3.81 THB/kWh before the demand charge, roughly 4.5M to 6.8M THB a
|
||
year without electric steam, 0.7M to 1.1M of it demand charge (estimate); the deposit for the connection is
|
||
400 THB per kVA. Detail and what it decides for steam, PV and the battery
|
||
in [sustainability](sustainability.md#grid-tariff-pea-and-what-it-decides).
|
||
|
||
Galvanics (Phase 5) is not in the table yet. By the Pheenix Alpha and
|
||
Sibert datasheets, one electroforming line plus the stamper prep machines
|
||
is ~30 kVA connected, two three-phase plating units and the rest
|
||
single-phase (see [galvanics and stamper prep](equipment/galvanics.md)):
|
||
small against the connection, but its own feeder and meter.
|
||
|
||
## Solar and storage
|
||
|
||
- The phase 1 roof carries **~247 kWp** (425 modules on the 1,523 m²
|
||
roof plane, per the [construction RFQ](finance/phase1-construction-rfq.md)).
|
||
This supersedes the older rule of thumb of 150 to 200 kWp on a
|
||
~1,500 m² building, which the massing model has overtaken
|
||
- Northern Thailand yield ~1,400 to 1,500 kWh/kWp/yr, so 300 kWp produces
|
||
roughly **420 to 450 MWh/yr**
|
||
- Plant consumption at mature two-shift operation: roughly **1,000 to
|
||
1,500 MWh/yr** without electric steam, up to **~2,500 MWh/yr** with it
|
||
(estimate), so 300 kWp covers roughly **28 to 45%** of consumption
|
||
without electric steam, falling to **~17%** with it; a bigger array
|
||
shifts that up
|
||
- Battery: **271 kWh** Gobel stack (ride-through, roughly
|
||
an hour of the chiller bank's peak electrical draw; peak shaving earns
|
||
little under PEA's time-of-use tariff, see
|
||
[sustainability](sustainability.md#grid-tariff-pea-and-what-it-decides))
|
||
|
||
## Steam and fuel
|
||
|
||
- Boiler bank: the five-press fleet draws **~750 to 900 kg/h at 10 bar /
|
||
180 °C** (~510 to 610 kW thermal) at Newbilt's 150 to 180 kg/h per press.
|
||
Proposed: **two 500 kg/h modules** (B-1 with the launch press and Duplex
|
||
system 1, B-2 with system 2 and the Classic), 1,000 kg/h installed; a
|
||
third module for N+1 is an RFQ option, and the hall has a fourth position
|
||
for growth ([steam and cooling](steam-cooling.html)). The 2024 Newbilt quote's
|
||
~400 kg/h covers one Duplex system
|
||
- Chiller bank: up to **~650 kW** of cooling; proposed **three 250 kW
|
||
air-cooled modules** rated at 40 °C ambient, one per press stage, behind a
|
||
plate heat exchanger with warm and cold tanks (estimate); the compound's
|
||
fourth pad takes the N+1 module
|
||
- If biomass: **~350 to 400 t/yr** air-dry wood at ~1.0 to 1.1 million
|
||
records a year, up to **~550 t/yr** at the start fleet's full ~1.5
|
||
million (fuel follows records pressed, not presses installed); the 60 rai
|
||
coppice could supply **~80 to 135 t/yr**
|
||
- If LPG: a bulk tank on site sized with the boiler bank (the ~2.5 to 5 t
|
||
first estimated was for one Duplex; no gas pipeline in the North)
|
||
|
||
### Utility phasing: backbone once, modules with the presses
|
||
|
||
The plant starts with one press. Everything that is cheap to oversize now
|
||
and costly to change in a running plant is built for the five-press fleet
|
||
at launch; the machines that make steam, cold water and oil pressure are
|
||
bought in identical modules as presses arrive. Identical modules mean one
|
||
set of spares and one service routine, and N+1 later is one more module,
|
||
not a redesign.
|
||
|
||
| Stage | Steam | Cooling | Hydraulics and air |
|
||
|---|---|---|---|
|
||
| Launch: Newbilt Single 2.1, one press | Boiler hall for four modules; T-1, WT-1, P-1; steam main and condensate return with a valved, blanked branch at every press position; **B-1** | Compound with four pads; TK-2 and TK-3 at full size; HX-1 frame for ~650 kW with plates for the launch duty; P-2 to P-4 on VFDs; supply and return mains for ~540 l/min with a valved branch per position; **CH-1** | Plant room at full size; hydraulic and air ring mains along the service trench, sized for the fleet, with a valved, capped tee per position; the Single 2.1's own unit in the plant room as the first pump set on the manifold; one compressor |
|
||
| Duplex system 1 complete (second press, EX 35) | B-1 at 60 to 72 % load | CH-1 covers ~96 % of the hot-afternoon peak (~261 kW): the cold tank and cycle overlap carry the rest, or CH-2 comes forward if the hot season arrives first | Tap the ring main; the Single 2.1 unit is already sized for the second press |
|
||
| Duplex system 2 | **B-2** | **CH-2** | A pump set added on the manifold; a second compressor if the air demand needs it |
|
||
| Classic | Carried by B-1 and B-2 | **CH-3** | A pump set, if the Classic runs from the central plant (Newbilt re-quote) |
|
||
| Options | **B-3** (N+1); **B-4** for about three more presses; ACC-1 accumulator; ECON-1 on a fired bank | **CH-4** (N+1); TC-1 dry cooler; pads for the ~350 kW frame | A standby pump set, or the Single 2.1 unit as standby |
|
||
|
||
Also built at launch: one controller that sequences the boilers, chillers
|
||
and pump sets lead and lag from the first module, and switchboard space and
|
||
feeders for every later module. Beyond four modules, the ten optional
|
||
Classics (~2.3 to 2.7 t/h, ~1.9 MW) are a utility phase of their own, on
|
||
reserved ground with its own header connection.
|
||
|
||
Two things to watch early:
|
||
|
||
- A fired 500 kg/h boiler serving one press runs at ~30 to 36 % and cycles.
|
||
Newbilt's steam accumulator (ACC-1) steadies it; or the first module is
|
||
electric and biomass follows at the expansion ([biomass](biomass.md)),
|
||
at the price of the demand charge.
|
||
- One large boiler or chiller bought at launch would run poorly at part
|
||
load, tie up capital in unused capacity and stop the plant when it fails.
|
||
|
||
The hydraulic side and its re-quote questions are in
|
||
[pressing line](equipment/pressing-line.md); the plant diagram and its
|
||
operating cases in [steam and cooling](steam-cooling.html#phasing).
|
||
|
||
## People
|
||
|
||
Rough mature-operation headcount (estimate): 4 to 6 press/finishing
|
||
operators per shift, 2 to 3 galvanics, 1 to 2 mastering/cutting engineers,
|
||
1 to 2 QC, 2 maintenance, 3 to 5 admin/sales/logistics. Roughly **15 to 25
|
||
people** across shifts at maturity, fewer than half that at launch. For
|
||
galvanics, OMS's rule of thumb (one person runs about 20 stampers a day,
|
||
two from about 30) against the 8 to 20 parts a day at full capacity
|
||
points to one operator per shift
|
||
([galvanics and stamper prep](equipment/galvanics.md)).
|
||
|
||
## Money (cross-references)
|
||
|
||
Figures in USD and THB at 1 USD = 33 THB (5 August 2026); vendor quotes
|
||
keep their original currency alongside.
|
||
|
||
- Newbilt semi-auto line: **~USD 232k (~7.7M THB)**, from the June 2024
|
||
quote of EUR 200,500 — expired, in
|
||
[pressing-line](equipment/pressing-line.md)
|
||
- Thai-sourced utilities, HVAC, racking, solar, BESS baseline: **~30M to
|
||
51M THB (~USD 910k to 1.56M)** for the five-press fleet, detail in the
|
||
[utilities CSV](finance/utilities-investment.csv)
|
||
- Not yet priced: the second Duplex system and the Newbilt Classic
|
||
(estimates in [total investment](finance/total-investment.md)),
|
||
galvanics line, mastering/cutting room, metrology, building
|
||
construction/fit-out, land
|