New docs/crane-workshop-tours.md: a 5 t single-girder EOT crane over the whole production compartment (stops at the warehouse fire wall), a machine door and crane-served workshop/machine bay at the ramp end, and a glazed ground-level visitor corridor along the car-park elevation with stations in process order, its own air and acoustic glazing so tours need no PPE. Covers what each changes in the shell (crane-ready frame, hook height under the 7.0 m eave, no full-height cross walls in the crane zone, room lids and crane hatches), safety, costs and open decisions. Propagated: construction RFQ (crane-ready frame, new section 1c, machine door, accessible 1:12 entrance now required), scale zone table (+210 to 280 m2, total ~1,400 to 2,000 m2), facility security, worker safety, roadmap items 9 and 15, total investment added-scope table, README.
32 lines
1.7 KiB
Markdown
32 lines
1.7 KiB
Markdown
# Worker Safety
|
|
|
|
Worker safety is a founding priority, on equal footing with the environmental
|
|
commitments:
|
|
|
|
- **Safety training**: proper, structured training for all operators and
|
|
maintenance staff, starting with the vendor-led commissioning training and
|
|
extending into an ongoing in-house program. The pressing line combines
|
|
hydraulics (~180 bar), saturated steam (10 bar / 180 °C), and hot PVC, and
|
|
every one of these demands trained, deliberate handling.
|
|
- **Clean rooms for galvanics**: silvering and stamper electroforming will
|
|
run in dedicated clean rooms with controlled access, proper ventilation and
|
|
exhaust, and decontamination procedures for people and equipment leaving
|
|
the area. Plating chemistry stays inside its containment.
|
|
- **Personal protective equipment**: appropriate PPE (overalls, gloves,
|
|
goggles, and process-specific protection) is mandatory per work area, in
|
|
line with the equipment vendor's site requirements (exhaust work benches,
|
|
fire protection) and local regulations.
|
|
- **Lifting and machine service**: the overhead crane needs trained
|
|
operators and slingers, a lift plan for every machine move, and the
|
|
periodic engineer inspections Thai law sets for cranes. A machine is
|
|
only disconnected and lifted after lockout: electrical isolation, steam
|
|
vented, hydraulics depressurised including the accumulator. Welding and
|
|
grinding stay in the workshop's hot-work corner under a permit. Detail
|
|
in [crane, workshop and tours](crane-workshop-tours.md).
|
|
- **Visitors** never share the floor's hazards: tours run in a glazed
|
|
corridor with its own air and no PPE requirement.
|
|
|
|
Safety infrastructure (training program, clean-room specification,
|
|
decontamination workflow) will be planned alongside the equipment, not after
|
|
it.
|