- README reduced to overview with linked document index - docs/equipment/pressing-line.md: fleet strategy, Newbilt plan, site reqs - docs/suppliers/vendor-landscape.md: researched vendor narratives - docs/sustainability.md: solar, zero-discharge water, materials - docs/worker-safety.md: training, clean rooms, PPE - docs/facility-security.md: access control, CCTV, archive/audio protection, fire and life safety, plant monitoring, Thai compliance anchors
45 lines
2.2 KiB
Markdown
45 lines
2.2 KiB
Markdown
# Pressing Line: Equipment Plan
|
|
|
|
The target press fleet is a **50/50 split between fully automated and
|
|
semi-automatic presses**: automated presses for standard production volume,
|
|
and semi-automatic presses for splatter and other color effects, special
|
|
editions, and small runs, where an operator working the mold directly is an
|
|
advantage rather than a cost. The semi-automatic side is covered by the
|
|
Newbilt evaluation below; a fully automated press line is an open
|
|
procurement item (see the [vendor landscape](../suppliers/vendor-landscape.md)
|
|
for the Pheenix Alpha candidate).
|
|
|
|
## Semi-automatic line: Newbilt
|
|
|
|
The core semi-automatic machinery under evaluation comes from
|
|
**Newbilt machinery GmbH** (Alsdorf, Germany):
|
|
|
|
- **Newbilt Single 2.1 system**: one VEX 50 extruder feeding one HRP 12
|
|
hydraulic press (~150 t press force), pressing 12" records at 140 or 180 g
|
|
with a Newbilt book mold set. A Vario trimmer handles 12" cuttings, with
|
|
a 7"/10" upgrade path.
|
|
- **Duplex upgrade path**: the hydraulic aggregate is already sized for a
|
|
second press, and an additional press and extruder are quoted options, so
|
|
the plant can scale from Single to Duplex without replacing infrastructure.
|
|
- **Supporting equipment**: label dry oven, shrink wrapper, PVC grinder
|
|
(scrap feeds back as the ~20% recycled share of the feedstock), 7" center
|
|
label punch, buffer spindles and separator plates.
|
|
|
|
The June 2024 Newbilt quotation totals **≈ €200,500** including freight from
|
|
Alsdorf to Thailand and seaworthy packaging. Two major utility systems are
|
|
deliberately excluded and will be **sourced and installed locally in
|
|
Thailand**: a ~400 kg/h steam generator (with water treatment) and a ~250 kW
|
|
cooling water system. The quotation has passed its validity date and will need
|
|
re-confirmation before ordering.
|
|
|
|
## Site requirements
|
|
|
|
Site planning for the semi-automatic line works from Newbilt's Duplex
|
|
requirements: roughly 200 m² of production floor, 32 kVA connected
|
|
electrical load, saturated steam at 10 bar, and compressed air and cooling
|
|
water circuits, plus side rooms for materials, compressor, chiller, and
|
|
finished goods.
|
|
|
|
Source documents live in [`newbilt/`](newbilt/): the budgetary offer, the
|
|
Duplex site requirements, the process schematic, and the service rate card.
|