cnx_vinyl/docs/finance/revenue-model.md
T
grabowski 984ced2485
Deploy test site / deploy (push) Successful in 49s
Biomass steam in both plans, PV on the factory roof only
User, 17 Oct 2026: "only put solar on the factory, prepare the other
buildings for solar, option a and b should operate on biomass".

- Steam: two 500 kg/h biomass modules (Getabec class, 6M to 10M THB) plus
  a fuel store and handling block (1M to 2M, estimate) in both plans; the
  electric bank becomes the alternative. ~0.67M THB of fuel a year against
  ~4.9M for electric steam; grid demand ~264 kW instead of ~980 kW.
- Solar: ~520 kWp on the factory roof (the biomass-case optimum is ~500 to
  550 kWp, hourly sketch in sustainability.md "PV size with biomass
  steam"); office roof and parking canopies built PV-ready (~120 kWp
  later). ~87 % used on site, ~61 % of the plant's electricity.
- Calculator: biomass default, bFuel row, pvKWp 520, pvSelf 87, iso fills
  the factory roof first and shows the other roofs as PV-ready.
- Numbers: launch plant ~168M / 232M / 296M with contingency; Plan A
  ~182M (~2M above 180M: the Chinese-route lever priced only electric
  boilers; a Chinese biomass quote is the way back), Plan B ~217M (label
  ~215M), ~35M more. Calculator EBITDA A 2.17M, B 2.23M USD.
- CSV, total-investment, revenue-model, sustainability, scale, biomass,
  site-candidates, boi, steam-cooling, construction RFQ (canopies
  PV-ready), README, roadmap; business plan draft 0.3 rebuilt (A and B
  63 pages) with new renders.
2026-10-17 20:24:55 +07:00

847 lines
46 KiB
Markdown
Raw Blame History

This file contains ambiguous Unicode characters
This file contains Unicode characters that might be confused with other characters. If you think that this is intentional, you can safely ignore this warning. Use the Escape button to reveal them.
# Revenue and Profit per Record: Rough Model
A first-pass economic model at mature capacity. Most numbers here are
estimates from industry pricing norms and this repo's own cost research.
**One set of real market prices now exists** (see the next section), and
it does not agree with the model. The point is the shape of the economics
and which levers matter, not precision.
**Currency: USD and THB.** FX at 5 August 2026: **1 USD = 33 THB**.
Pricing benchmarks originally researched in EUR are converted at
**1 EUR = 1.155 USD**. Compiled July 2026.
## First market data point (August 2026)
Buy-side prices gathered from actual invoices, not industry norms. The
pressing and stamper figures come from comparing a **ResurRec** (Bangkok)
full-service invoice against a pressing-only invoice. Mastering is a
market range from multiple engineers.
| Item | THB | USD | Note |
|---|---|---|---|
| Audio mastering | 5,000 – 20,000 **per song** | 150 – 605 | Varies by engineer |
| Father / mother / silvering (stamper set) | ≤22,000 **per title** | ≤665 | **Residual** between the full-service and pressing-only invoices — see below |
| All-in per 12" record | 650 – 950 | 19.70 – 28.80 | Believed to cover pressing and stamper; whether mastering and jacket printing sit fully inside it is unresolved |
**The 22,000 THB is a residual, not a price.** It is the difference
between two invoices, and that difference carries everything the two
engagements did not share — lacquer cutting, test pressings, setup and
changeover, project management, and margin on the bundle — not only
metalwork. It is therefore an **upper bound** on the stamper component.
Every figure derived from it below inherits that, and the fix is cheap:
ask for a line-itemised full-service invoice.
These are domestic Thai prices with no separately-billed freight or
import duty, though the stamper component carries inbound freight inside
it. They are **one buyer's retail experience at one plant**, on a scope
that includes a printed jacket — indicative of the Thai price level, not
directly substitutable for what CNX would quote a label placing 2,000
units. **The 650–950 THB figure is the price at 300 units**; the full
volume ladder is in point 3.
## What the ResurRec factory tour showed (August 2026)
First-hand observation from a site visit, and it reframes the competitive
picture more than the invoices do:
- **The plant is essentially an apartment**, not an industrial building.
Floor area, floor loading and power are constrained accordingly.
- **No proper HVAC or air filtration** on the pressing floor — no
temperature, humidity or PM control.
- **Pressing only. They do not plate.** The stamper set behind the
22,000 THB differential is bought in and resold, not made in-house.
- **Two presses, both Newbilt**, identified on the tour as a **Classic
12" fully automatic** plus one **semi-automatic**. This is a real
capital fleet, not a hobby setup. The Classic 12" specification —
3-column hydraulic, built-in 15 kW extruder, automatic patty and label
handling, Siemens PLC, 28 s cycle — is from Newbilt's datasheet, not
from anything observed running. No nameplate was photographed and the
age or provenance of either machine is unknown.
Four things follow, and one of them corrects the read in the previous
section.
**We have found no evidence of plating capability in Thailand.** The one
plant we have seen does not plate, and buys its stampers in. That is one
observation, not a survey: it does not establish that no Thai title is
plated domestically, that ResurRec is the only Thai plant, or that no
electroforming capacity exists outside the record industry. **Run a desk
check of Thai electroforming and metal-finishing capacity before "a
genuine first" goes in front of an investor.** If it holds, it would make
in-house galvanics a capability rather than a cost saving, and the
turnaround advantage in
[production-timeline.md](../production-timeline.md) would be measured
against a competitor who cannot close the gap without building the same
line.
**The 22,000 THB is a resale price, not a plating cost.** It embeds
ResurRec's margin and inbound freight, so the underlying plating cost is
lower. That does not weaken the business case: 22,000 THB is what a Thai
buyer pays for a stamper set today, which is exactly the right basis for
what CNX could charge or avoid paying. But it should not be read as the
cost of running a galvanics line.
**On nameplate they out-class CNX's launch fleet by two to three times.**
Newbilt specifies a 28 s cycle for the Classic 12", which is ~128
records/hour with no stoppages — a vendor figure for a machine in
isolation, not a floor rate anyone measured — against 60–80/hour for the
semi-automatic. The pair nameplates at **~190–210/hour**.
Everything past that point is assumption. Their shift pattern, working
days, operator count, order book and maintenance regime were all
unobserved; the table below applies one 8-hour shift over 300 days at the
60–70% effectiveness this repo uses for its *own planned* fleet, which
could be wrong in either direction. Read it as installed capability, not
as output.
| | Nameplate × assumed OEE, records/yr — **not observed output** |
|---|---|
| ResurRec, assuming one shift over 300 days | ~275k – 355k |
| **CNX launch** (1 semi-auto, 1 shift) | **90k – 135k** |
| CNX Duplex (2 semi-auto, 1–2 shifts) | ~175k – 540k |
| CNX mature (4 semi + 1 automated, 2 shifts) | 1.0M – 1.5M |
All rows are on the same 300-day basis so they can be compared. CNX does
not overtake them on installed capability until the Duplex expansion, and
does not clearly lead until the mature fleet. The fleet is real and
should not be discounted, but nothing here is a measurement of what they
actually ship, and an unconditioned floor may not hold top-end
effectiveness through the wet season.
What remains true is the **quality and capability gap**, and it is where
the whole differentiation now sits: no plating, no climate control, no
metrology, no traceability. There is still no *industrial* vinyl plant in
Thailand, but the gap CNX is closing is capability, not capacity, and it
will be outgunned on presses for its first two phases.
### The incumbent is press-rich and metal-poor
With the fleet confirmed, the pricing behaviour in point 3 below stops
looking like three separate quirks and starts looking like one constraint.
A plant that can press 230,000–350,000 records a year:
- **turns away 150-unit orders** because they cost too much,
- discounts only **30% for a tenfold** increase in run size,
- and needs **two to four extra weeks** for anything over 3,000.
None of that is press capacity — 3,000 units is roughly three days of
pressing on that fleet. The most economical single explanation is the
**stamper being a purchased import**: it is the only cost that is both
large and volume-invariant, which would make small runs uneconomic, keep
the discount ladder flat, and — at 1,000–2,000 pressings per stamper —
mean a 3,000-unit run needs two or three sets and therefore another
overseas order.
**But that is a hypothesis, and it is not the only one that fits.** An
apartment-sized plant is constrained in several ways at once, and any of
these would shape a price list the same way:
- **Printed jackets.** Their price carries one, and a jacket print run
takes 10–20 working days from approved artwork. A 3,000-unit jacket
order is a bigger, slower print job, and this constraint **CNX would
share**, which would remove the competitive read entirely.
- **Floor space.** Storing, finishing and shipping 3,000 records is an
area problem before it is a metal problem.
- **Finishing labour**, which this repo separately calls labour-bound.
- **Lacquer cutting**, presumably also outsourced — a second overseas
dependency, distinct from plating.
- Deposit and cash-flow terms on a larger PVC and jacket buy.
The tour did not distinguish between these, and the 1,000–2,000
pressings-per-stamper figure the inference leans on is itself unsourced
in this repo. The stamper hypothesis is the one CNX can act on, which is
a reason to test it, not a reason to believe it. It is also a single
point of failure: the collaboration case, the "pull galvanics forward"
argument and the "their weakness at volume is structural" claim all rest
on it together.
It also reframes the collaboration, though more modestly than it first
appears. If the constraint is metalwork rather than machines, a CNX
galvanics line could sell stampers **into their existing spare press
capacity** — revenue against the galvanics capex before CNX presses
anything itself.
Sizing it honestly: 300 titles a year at their retail 22,000 THB would be
~6.6M THB (~200k USD) of revenue, but a competitor buys at wholesale, and
revenue is not contribution. On this page's own 25–35% marginal-cost
assumption, and at a wholesale price well below retail, 300 titles might
net **60–100k USD of contribution — a five-to-ten-year payback** on the
line from this customer alone, before galvanics opex, the building, the
clean room, ZLD or depreciation. It also assumes they would move their
entire stamper supply to a new entrant who is also their rival.
Treat it as a useful offset against the capex, not as a business case.
Which raises a sequencing question the roadmap does not currently ask:
**should galvanics come first rather than fifth?** It is a fraction of the
full capex, it addresses the market's actual bottleneck, it earns before
the press hall exists, and it is the one capability no one in the country
has. The counter-argument is real — galvanics still needs a building, a
clean room and zero-discharge water treatment, and it is the hardest skill
to hire, but the option deserves costing rather than assuming.
**The number that decides it is ResurRec's actual annual output and title
count**, which is not known. At 300 titles the stamper opportunity is
strong; at 100 it is marginal. Worth asking directly in the collaboration
talks.
**No HVAC turns the biggest cost line into the product.**
[facility-security.md](../facility-security.md) specifies whole-factory
climate control — 20–26 °C, 35–60% RH, PM filtration sized for
burning-season PM2.5, and the utilities budget treats it as overhead.
Against a competitor pressing in uncontrolled Bangkok air it is a quality
argument instead:
- Moisture in PVC compound causes bubbles, non-fill and surface defects;
humidity also drives cooling rate, and so flatness and warp.
- Airborne particulate embeds in the record surface. That is the classic
source of clicks and pops, and it is the complaint that gets a pressing
rejected by a label.
- Thailand's burning season makes this seasonal as well as chronic, so a
plant without filtration would be expected to produce different records
in March than in September.
These are the standard process arguments for climate control, not
measurements anyone has taken here — no records were tested. And the
obvious counter belongs next to them: **the incumbent sells commercially
from that room today**, which bounds how much the Thai market currently
penalises the absence of climate control. The quality case is real, but
it is a bet that buyers will pay for a difference they are not currently
demanding.
**There is a Newbilt install base in Thailand, which is worth a phone
call.** Seeing two Newbilt presses in a room establishes that they exist
there — not their age, provenance, downtime, spares availability or
service history, and not that they were bought new from Newbilt rather
than used or through an agent. If they were bought new, somebody has
already walked the import, commissioning and spares path CNX is about to
walk. Two things to ask on the back of it, both free: ask **Newbilt** for
their Thai
install base and a service-response precedent — the northern-dispatch SLA
question in [equipment-suppliers.md](../suppliers/equipment-suppliers.md)
is much easier to answer with an in-country reference, and, if the
collaboration talks progress, ask **ResurRec** directly what commissioning
and support actually cost them.
The corollary is a pricing one. CNX cannot win a price war at 200-unit
runs against an operator with apartment rent and no HVAC load, and should
not try. Nor is capacity the wedge — they can already press volume. It
competes on what an unconditioned, non-plating shop cannot offer at any
run size: export-grade QC and traceability, titles needing plating,
consistent output through burning season, and the regional labels
currently shipping to Europe, the US or Japan.
### What the invoices say about the model
**1. The galvanics saving may be bigger than modelled, but it is being
measured against the wrong supplier.** The model credits in-house
galvanics with removing 175–460 USD per title of external stamper cost.
The ResurRec residual is **≤665 USD**.
Two problems with treating that as the saving. First, **CNX's launch plan
does not buy stampers in Thailand** — it buys from Stamper Discs in
Sheffield, so CNX's avoided cost is the Stamper Discs price, which is
nowhere in this repo. Second, neither 175–460 nor 665 has a source: the
first is an industry-norm estimate, the second is a residual carrying
cutting and setup. Until a Stamper Discs quote exists, the honest
statement is that the saving lies **somewhere between 175 and 665 USD per
title**, and getting that quote is the cheap way to narrow it.
The table below takes the optimistic end. On a galvanics line at
320k–650k USD, and assuming in-house marginal cost (nickel, silver
nitrate, chemistry, labour, QC, water treatment) runs 25–35% of the
external price — an assumption with no basis stated — the net saving
would be 430–500 USD per title:
| Titles/yr | Annual saving | Payback on 320k | on 650k |
|---|---|---|---|
| 300 | ~130–150k USD | ~2.1 yr | ~4.3 yr |
| 600 | ~260–300k USD | ~1.1 yr | ~2.2 yr |
Every cell above divides capex by the **top** of the saving range. At the
bottom the same table gives 2.5 and 5.0 years at 300 titles, 1.2 and 2.5
at 600, so the honest span is **one to five years**, and the adverse
corner stretches past six once the ±30–50% band that
[total-investment.md](total-investment.md) puts on the galvanics capex is
applied. It is nonetheless driven by **title count, not record volume**,
which is a real argument for pulling galvanics earlier than its current
Phase 5 slot in [roadmap.md](../roadmap.md) — on a benchmark that still
needs the Stamper Discs quote behind it.
**2. Per-title services may be understated by up to 3–4×, but the
evidence is internally inconsistent.** The model
bundles mastering, cutting, stampers and test pressings into 19,000–57,000
THB per title. At observed market rates a ten-track album masters at
50,000–200,000 THB *before* the 22,000 THB stamper set, so the real
per-title value is more like **72,000–222,000 THB (2,180–6,730 USD)**.
At 300–600 titles/yr that is **0.65M to 4.0M USD/yr of title services**,
against the 0.17M–0.69M in the table below. Two things cap it, and both
are real:
- **Mastering is labour-bound.** An engineer masters perhaps 2–4 songs a
day — 500–1,000 songs, or 50–100 ten-track albums, over a 250-day year.
The 300–600 titles/yr in this model would therefore need anywhere from
**3 to 12 mastering engineers** depending which corner you take;
[scale.md](../scale.md) currently plans for 1 to 2. Even the friendly
corner is short.
- The upper bound above rests on a ten-track album at the 20,000 THB/song
top rate. That is a figure this page doubts further down, so the 4.0M
USD end of the range should be treated as an artefact rather than a
forecast.
- CNX would not necessarily capture full boutique retail rates as a plant
rather than a studio.
**3. The volume ladder, and what it gives away.** The 650–950 THB price is
for **300 units**. The published discounts:
| Run | Discount | THB/unit | USD/unit |
|---|---|---|---|
| 150 (stated minimum) | - | rarely accepted, "cost is way too high" | |
| **300 (reference)** | - | **650 – 950** | 19.70 – 28.80 |
| 500 | −5% | 618 – 903 | 18.70 – 27.35 |
| 1,000 – 3,000 | −15% | 553 – 808 | 16.75 – 24.45 |
| >3,000 | −30% | 455 – 665 | 13.80 – 20.15 |
| | | *+2 weeks to 1 month lead time* | |
**The curve is remarkably flat.** A tenfold increase in run size buys only
30% off. Whatever the exact split, that shape means a large per-title
fixed cost that does not fall with volume, and it is the shape, not any
solved number, that is informative.
Solving the first three tiers as a fixed-plus-variable structure gives
roughly 34,000–50,000 THB fixed and 535–780 THB variable, **but that
answer should not be leaned on**. Three reasons:
- The 1,000–3,000 tier is a flat band, so the second solve point is an
arbitrary choice inside it. Taking 1,000 instead of 3,000 moves the
fixed component from ~32,500 to ~41,800 THB on the low ladder alone.
- Two parameters fitted to three points has one degree of freedom, so a
small residual is guaranteed by construction and validates nothing.
- These are not three observations. They are published discount
percentages off a single reference price; only the 300-unit tier is a
transaction anyone has seen. Fitting a line to a discount schedule
recovers the schedule, not the supplier's cost structure.
Two readings still fall out of the shape, and both matter.
**The variable price is roughly three-and-a-half to seven times the
model's assumption.** This
model prices a record at 115–150 THB (3.50–4.60 USD) blended. The Thai
domestic market pays **535–780 THB** for the same per-unit scope, and even
at the deepest >3,000 discount never drops below ~455 THB. Some of that
gap is scope: their figure carries a printed jacket where this model
passes packaging through separately. But a jacket, inner sleeve and
shrink at retail is on the order of 100–150 THB, which does not close a
gap of roughly 400 THB.
Two readings remain, and they **pull in opposite directions**:
- The pricing assumption here is too low for this market, and there is
genuine willingness to pay.
- ResurRec is holding an import-parity ceiling that only a sole domestic
supplier can hold — in which case **CNX's own entry is what compresses
it**, and the headroom evaporates on arrival.
Nothing in one supplier's price list separates those. It suggests more
headroom in domestic pricing than this model assumes, from a single
published list in a market with one supplier. It is the finding most
worth testing next, not the finding most worth relying on.
**The fixed component looks small against the stated inputs.** At
34,000–50,000 THB it barely covers a ≤22,000 THB stamper set plus one to
three songs of mastering, though at the other end of the solve range
(~41,800 THB low ladder) the tension eases, so this may be an artefact of
the endpoint chosen rather than a real gap. Either the 650–950 THB does
not fully carry album mastering, or albums are mastered far below the
5,000–20,000 THB per-song headline. Worth resolving: it is the difference
between point 2 above being a 3–4× understatement or a much smaller one.
**The >3,000 lead-time penalty is probably a stamper problem, not a press
problem.** At nameplate the two presses clear 3,000 units in about two
days, so a two-to-four-week extension cannot be press time. The likely
cause is in the numbers already in this repo: a stamper is good for
**1,000–2,000 pressings**, so a 3,000-unit run needs **two to three
stamper sets**, and with no plating in-house, every additional set is an
overseas order. "Blocking out the entire factory" reads like scheduling
around an imported-metalwork wait.
If that inference holds it would be the sharpest competitive finding yet:
the incumbent's lead time degrading with run size *because* they cannot
plate, while a plant with in-house galvanics pulls a fresh stamper off an
archived mother in a day or two (see the repress path in
[production-timeline.md](../production-timeline.md)). But see the
alternatives listed earlier — jacket print runs in particular would
produce the same symptom and would constrain CNX equally. Confirm the
cause before treating their weakness at volume as structural.
**And the floor of the market is unserved.** A 150-unit minimum that is
"rarely accepted because the cost is way too high" means sub-300 runs are
effectively unavailable in Thailand. That floor exists because per-title
cost — an imported stamper set plus outsourced mastering — is irreducible
for them. In-house cutting and plating collapses it, which makes short
runs viable for CNX in a way they structurally are not for ResurRec.
The channel planned for that segment is the
[artist platform](../artist-platform.md): a transparent price calculator
and fan-funded campaigns that press only when enough fans have
pre-ordered.
**What it does to the volume-versus-boutique question.** The model assumes
1.0–1.5M records/yr across 300–600 titles, an average of 1,700–5,000 units
per title. The market evidence says the reference order is 300 units and
that 3,000+ is disruptive enough to need special handling. Those two
pictures still do not fit together, and the earlier back-calculation of a
200–400 unit typical run was right. But the resolution is now clearer than
"pick one": the volume tiers exist and are priced, so larger runs are not
absent from the market — they are **rationed by a metalwork bottleneck**
that CNX would not have.
### What is still missing
- **What else sits in the 22,000 THB differential besides metalwork?**
Ask for a line-itemised full-service invoice. This is the highest-value
question on the list: the residual is the base of the galvanics case.
- Is the stamper set for a complete 12" (both sides), or per stamper?
This drives the two-to-three-sets inference above.
- Does the >3,000 lead-time extension come from stamper supply, press
scheduling, jacket printing, floor space or PVC procurement? It decides
whether their constraint is one CNX escapes or one CNX shares.
- What is ResurRec's actual annual output and title count? The
collaboration sizing is guesswork without it.
- What does the Stamper Discs quote say? It, not the Thai resale price,
is CNX's real avoided cost at launch.
Two standing caveats on this whole section. **The evidence is one buyer,
one plant and one afternoon** — the invoices and tour notes are not
archived anywhere in this repo, only summarised here, and for an
investor-facing document they should be. And **ResurRec is a competitor**:
every collaboration scenario above assumes they would buy a critical
input from a new entrant, which they may simply decline to do, and which
would also accelerate a rival.
- Does 650–950 THB include jacket printing, or is packaging billed
separately?
- Is the 5,000–20,000 THB/song mastering rate for general audio mastering,
or vinyl-specific mastering? Lacquer cutting is a separate service again
and is not obviously in either figure.
- Is there album-rate pricing for mastering, or is it strictly per song?
Ten tracks at the 20,000 THB top end would be 200,000 THB, which seems
high for an indie release and suggests album rates exist.
One further consequence worth naming: [README](../../README.md) records a
collaboration with ResurRec as "under discussion", and the tour makes that
look more like complementarity than rivalry. They press, they do not
plate, and they cannot scale inside an apartment. A plating and mastering
relationship — CNX supplying stampers and cut lacquers into their pressing
capacity — is a plausible shape for it, and it would put revenue against
the galvanics line from day one rather than waiting on CNX's own title
count.
## Pricing assumptions (what a pressing plant charges)
Typical Western pressing-service prices run roughly **2.90 to 5.80+ USD**
per 12" record at volume for standard black, with premiums for
color/splatter (+0.60 to 1.70), 180 g, and small runs; full-service with
printed jacket lands around **4.60 to 9.20 USD** per unit. Per-title
service fees come on top: mastering, lacquer cutting, stamper sets, test
pressings, setup.
Working assumptions for CNX at mature volume, blended across run sizes and
standard/color mix:
- **Blended pressing price: ~3.50 to 4.60 USD per record**
(~115 to 150 THB) — pressing, labels, inner sleeve, assembly into
customer-supplied or locally-made jacket; deluxe packaging passed
through at cost plus margin. That blend holds at ~20 % specials
(standard 3.40 / 3.80 / 4.25 USD plus the 0.60 / 1.15 / 1.70 colour and
splatter premium on a fifth of the records).
- **Specials share: 60 % and more (decided October 2026).** The plant
focuses on special prints (splatter, marble, colour effects), not mono
colours, so the plan takes 60 % specials: the blend rises to **~3.76 /
4.49 / 5.27 USD** (adverse / central / favourable). Specials run only
on the Duplex systems (the Classic has one built-in extruder), which
makes the Duplex the launch plant's bottleneck (below). The direct cost
table does not yet carry what specials cost extra (coloured compound,
colour-change purge, trim that only goes back into black), so the gain
is an upper bound until the compound quotes arrive
- **Per-title services: ~580 to 1,730 USD per title** (~19,000 to 57,000
THB) for mastering, cutting, stampers, test pressings, at roughly 300
to 600 titles/yr at full capacity
- Dropshipping/fulfillment fees per parcel on top, not modeled here
**These two assumptions are the ones the market data contradicts most
sharply.** Domestic Thai pricing runs 535–780 THB per unit on the variable
scope against the 115–150 THB assumed here, and per-title services look
understated as well. The figures above are deliberately left at the
conservative Western-benchmark level until a second data point exists:
re-basing the whole model on one supplier's price list, in a market with
one supplier, would be worse than leaving it low. Test it at Making Vinyl,
then re-base.
### Second Western data point: Record Industry's calculator (October 2026)
Record Industry (Haarlem, NL) publishes an online calculator
(https://www.recordindustry.com/calculator/, checked October 2026; ex 21 %
Dutch VAT, ex freight, 20 copies over the order included). A 12" 140 g
black LP, cut from a digital master with stampers, 5 test pressings,
printed labels, white paper inner sleeve, printed 3 mm jacket on 300 gsm
board, shrink wrap:
| Copies | Order total | Per copy | Per copy, USD | Per copy, THB |
|---|---|---|---|---|
| 200 | 1,494.68 EUR | 7.47 EUR | 8.63 | ~285 |
| 300 | 1,721.22 EUR | 5.74 EUR | 6.63 | ~219 |
| 500 | 2,098.12 EUR | 4.20 EUR | 4.85 | ~160 |
| 1,000 | 3,169.78 EUR | 3.17 EUR | 3.66 | ~121 |
At 1 EUR = 1.155 USD and 1 USD = 33 THB. How it is built: an order
set-up fee of 60 EUR plus a small-run charge (60 EUR under 300, 40 under
500); cutting with stampers 470 EUR a title (570 from tape, 240 to plate
a supplied lacquer); black vinyl 1.49 EUR a record; colour +35 EUR
set-up and +0.14 EUR a record, two-colour splatter +85 EUR and +0.99 EUR
a record, press cleaning 60 EUR; the printed jacket steps down with the
print run (1.93 EUR a copy at 200, 0.64 at 1,000).
What it says about the assumptions above:
- **Per title**, its set-up, small-run charge, cutting, stampers and test
pressings come to about 580 to 600 EUR (~670 to 690 USD, ~22,000 to
23,000 THB): the low end of the 580 to 1,730 USD assumption.
- **Per copy** at 300, everything but the per-title items comes to about
3.81 EUR (~4.40 USD, ~145 THB), and black pressing with printed labels
and a paper inner sleeve to about 2.43 USD (2.09 USD at 1,000): below
the 2.90 to 5.80 USD range, which looks high for black at this plant.
- **The Thai market price** of 650 to 950 THB a copy at 300 is about 3 to
4.3 times this plant's ex-works price (before freight, Thai import duty
and VAT, which the Thai buyer pays on an import).
- The artist ordering demos (price list demo-0.1) come to about 343 THB a
copy at 300 with vinyl mastering, 310 THB without: above this plant's
ex-works price and well below the Thai market. Both price levels are
open until roadmap item 1; this is a benchmark, not a re-base.
## Revenue at full capacity
| Scenario | Records/yr | Pressing revenue | Title services | Total USD | Total THB |
|---|---|---|---|---|---|
| Mature, low | 1.0M | ~3.5M | ~0.17M | **~3.7M/yr** | **~122M/yr** |
| Mature, high | 1.5M | ~6.1M | ~0.69M | **~6.8M/yr** | **~224M/yr** |
(Low: 1.0M x 3.50 USD + 300 titles x 580 USD. High: 1.5M x 4.05 USD + 600
titles x 1,155 USD. A pure-volume plant runs at the low per-title end; a
boutique-heavy mix pushes the title line up and the volume down.)
## Direct cost per record (estimates)
| Cost element | USD/record | THB/record | Basis |
|---|---|---|---|
| PVC compound | 0.29 to 0.46 | 9.6 to 15.2 | ~150 to 160 g effective virgin per record at 1.75 to 2.90 USD/kg record-grade; regrind loop covers scrap |
| Labels | 0.03 to 0.09 | 1.1 to 3.0 | printed pairs, volume |
| Inner sleeve | 0.09 to 0.17 | 3.0 to 5.7 | poly-lined |
| Jacket (standard) | 0.40 to 0.92 | 13.3 to 30.4 | local carton partners; pass-through-ish |
| Shrink wrap | 0.02 to 0.03 | 0.8 to 1.1 | film |
| Energy | 0.12 to 0.23 | 3.8 to 7.6 | ~1.5 to 2 kWh blended per record at grid/solar mix |
| Production labor | 0.08 to 0.16 | 2.6 to 5.4 | Built up below from 13–19 direct staff at northern Thai rates, over 1.0–1.5M records |
| Stamper amortization | 0.03 to 0.12 | 1.0 to 4.0 | in-house three-generation set at ~60–150 USD marginal cost over 1,000 to 2,000 pressings |
| Maintenance, spares, consumables | 0.12 to 0.23 | 3.8 to 7.6 | estimate |
| Reject allowance | 0.12 to 0.17 | 3.8 to 5.7 | 5 to 10% reject rate carried by good units |
| **Total direct cost** | **~1.30 to 2.58** | **~43 to 85** | |
**Labour build-up.** The previous 0.23–0.40 USD/record implied 44,000 to
63,000 THB per head per month, far above northern Thai production rates.
Rebuilt from headcount and wages, fully loaded at ×1.3 for social
security, overtime, bonus and PPE:
| Role | Heads | THB/month each, loaded |
|---|---|---|
| Press and finishing operators | 8–12 | ~19,500 |
| Galvanics | 2–3 | ~32,500 |
| QC | 1–2 | ~26,000 |
| Maintenance | 2 | ~32,500 |
| **Direct production payroll** | **13–19** | **~312,000 – 449,000/month** |
That is 3.7M–5.4M THB/yr (113k–163k USD), or **0.08–0.16 USD per record**
over 1.0–1.5M records. Mastering and cutting engineers are excluded —
they are title-services labour, not per-record, and admin, sales and
logistics sit in overheads below. A cutting engineer earns about
**50,000 THB a month** base salary (team figure, October 2026).
**On top of the ×1.3 (October 2026):** the company gives every member of
staff, office included, group health insurance and a yearly check-up,
plus the occupational checks the law requires for risk-factor work (see
[worker safety](../worker-safety.md)): about 17,500 THB a head a year at
planning prices, ~20 people at the start fleet, so ~0.35M THB a year. The
×1.3 itself is roughly the employer's social security (5 % up to a 17,500
THB ceiling since January 2026) plus ~25 % for overtime, bonus and PPE.
Unified Engelbert Strauss workwear for all staff adds ~0.3M THB a year
(kit, prices and import in [worker safety](../worker-safety.md)).
The [press fleet calculator](../fleet-calculator.html) costs labour from
base salaries in that way.
## Margin per record
- Blended price 3.50–4.60 USD minus direct cost 1.45–2.75 USD gives a
**gross margin of ~2.11 USD per record at the midpoint (~70 THB, ~52%)**
- The spread is wide and worth stating rather than hiding in a range: the
adverse corner — low price meeting high cost — leaves **0.92 USD
(26%)**, and the favourable corner **3.30 USD (72%)**. Neither extreme
is likely, but price realisation and cost control each move the margin
by more than a third on their own
## Operating picture of the launch plant (October 2026)
The plant now launches with one Newbilt Duplex system and one Classic,
with cutting and galvanics in-house from the start
([total investment](total-investment.md#launch-plant-october-2026)). Three
presses make ~0.71 to 0.97 million records a year on two shifts at the
earlier ~20 % specials share ([scale](../scale.md#production-capacity)),
against 1.0 to 1.5 million for the five-press fleet the full-capacity
table below was built for. Re-based on **60 % specials** (October 2026),
same method and the same three cases, with these changes (all estimates):
- **Volume 0.58M / 0.74M / 0.90M records a year.** Specials run only on
the Duplex system, so at 60 % its two presses (60 to 80 records an hour
each, estimate) set the output: 120 to 160 specials an hour carry 80 to
107 standard records on the Classic, which then runs at about two
thirds of its ~128 an hour. At the team's planning rate (3 a minute per
Duplex system) the launch plant stays balanced at ~0.94 million, which
is what the [calculator](../fleet-calculator.html) shows.
- **Blended price** 3.76 / 4.49 / 5.27 USD: standard 3.40 / 3.80 / 4.25
plus the specials premium 0.60 / 1.15 / 1.70 on 60 % of the records.
- **Direct payroll** stays at 3.7M to 5.4M THB a year (two shifts still
need the press, finishing, galvanics, QC and maintenance crews), so
labour per record rises to 0.13 / 0.19 / 0.28 USD and the direct cost to
1.35 / 2.00 / 2.70 USD, with no extra cost for specials yet (see the
pricing assumptions).
- **Title services**: 200 / 300 / 400 titles at 580 / 1,155 / 1,730 USD,
60 to 70 % contribution after lacquers, styli and nickel. The middle
price is the per-title fee of the artist demos (37,836 THB).
- **Depreciation** on the launch plant: 8.9M USD over 10 years (adverse),
the 216M THB target (~6.55M USD) over 12.5 years (central), 4.9M USD
over 15 years (favourable).
- **Cash overheads** unchanged at 0.20M to 0.45M USD, paired high to
adverse.
| USD/yr | Adverse | Central | Favourable |
|---|---|---|---|
| Records | 0.58M | 0.74M | 0.90M |
| Blended price (60 % specials) | 3.76 | 4.49 | 5.27 |
| Direct cost | 2.70 | 2.00 | 1.35 |
| Contribution per record | 1.06 | 2.49 | 3.92 |
| Pressing contribution | 0.61M | 1.83M | 3.51M |
| Title-services contribution | 0.07M | 0.23M | 0.48M |
| **Total contribution** | **0.68M** | **2.06M** | **3.99M** |
| Cash overheads | 0.45M | 0.33M | 0.20M |
| **EBITDA** | **0.23M** | **1.73M** | **3.79M** |
| Depreciation | 0.89M | 0.52M | 0.33M |
| **Operating profit** | **-0.66M** | **1.21M** | **3.46M** |
| Revenue | 2.28M (~75M THB) | 3.65M (~120M THB) | 5.41M (~179M THB) |
| Payback on the launch capital (EBITDA, mature year) | never | ~3.8 yr (2.8 to 5.1 on 4.9M to 8.9M) | ~1.3 yr |
At the earlier ~20 % specials share the same table read 0.71 / 0.84 /
0.97M records, revenue 2.60 / 3.75 / 5.15M and EBITDA 0.22 / 1.63 /
3.45M: more specials earn a higher price on fewer records, and the
central EBITDA gains ~0.1M USD a year (more if the Duplex presses run
faster than 60 to 80 an hour, less once specials carry their extra
cost).
What it says:
- **The central case works on 216M THB**: EBITDA ~1.7M USD (~57M THB) a
year and operating profit ~1.2M USD (~40M THB) once the plant runs at
volume, and it breaks even on operating profit at about **0.25 million
records a year, about a third of its output**.
- **The adverse corner cannot pay for itself at any volume the three
presses make**: it would need ~1.1 million records to cover
depreciation. It stacks the low price, the high cost, the high capital
and the high overheads at once; at the central cost and volume the
price that covers depreciation is only ~2.7 to 3.0 USD (~90 to 98 THB)
a record, below the low price assumed.
- **The caveats of the full-capacity table hold here too**: the central
EBITDA margin (~47 %) is far above the 15 to 25 % pressing plants earn,
because the direct cost table leaves out indirect labour, freight,
scrap above the allowance and commissions. Price realisation and
utilisation decide the result, and the ramp year is not in this table
(the ramp-up reserve in the investment covers it).
- Not modelled: cassette and CD-R lines, stamper supply to other
pressing plants, dropshipping fees. The solar PPA lever in the
investment would add its power price to the energy line instead of
capital.
## Operating pictures of Plan A and Plan B (October 2026)
The business plan comes in two versions
([total investment](total-investment.md#two-plans-a-at-180m-thb-and-b-at-215m-thb-october-2026)):
**Plan A** (~182M THB, the launch plant with six cost levers) and
**Plan B** (~217M THB, the same launch plant with everything in), both
priced without contingency and with the ramp-up reserve, both on biomass
steam with PV on the factory roof (October 2026). Both run the
same three presses, so volume, price, direct cost, title services and
overheads are those of the launch-plant table above; only the
depreciation follows each plan's capital (estimates):
- **Plan A**: the high end of its blocks (6.44M USD) over 10 years, the
midpoint (5.06M USD) over 12.5, the low end (3.68M USD) over 15. The
solar PPA adds its power price to the energy line (~0.06M USD a year in
the calculator for the ~520 kWp factory roof), not shown here.
- **Plan B**: 7.79M USD over 10 years, 6.11M over 12.5, 4.42M over 15.
Its owned solar (~520 kWp on the factory roof) saves the PPA power bill; cassette and CD-R sales, tours
and the Payap programmes it opens from the start are not modelled.
- **Payback** is counted on the whole plan price including the ramp-up
reserve (Plan A 3.99M / 5.52M / 7.05M USD, Plan B 4.73M / 6.56M /
8.40M USD from the low to the high end).
| USD/yr | A adverse | A central | A favourable | B adverse | B central | B favourable |
|---|---|---|---|---|---|---|
| Records | 0.58M | 0.74M | 0.90M | 0.58M | 0.74M | 0.90M |
| Blended price (60 % specials) | 3.76 | 4.49 | 5.27 | 3.76 | 4.49 | 5.27 |
| Direct cost | 2.70 | 2.00 | 1.35 | 2.70 | 2.00 | 1.35 |
| Pressing contribution | 0.61M | 1.83M | 3.51M | 0.61M | 1.83M | 3.51M |
| Title-services contribution | 0.07M | 0.23M | 0.48M | 0.07M | 0.23M | 0.48M |
| Cash overheads | 0.45M | 0.33M | 0.20M | 0.45M | 0.33M | 0.20M |
| **EBITDA** | **0.23M** | **1.73M** | **3.79M** | **0.23M** | **1.73M** | **3.79M** |
| Depreciation | 0.64M | 0.40M | 0.25M | 0.78M | 0.49M | 0.29M |
| **Operating profit** | **-0.41M** | **1.33M** | **3.54M** | **-0.55M** | **1.24M** | **3.50M** |
| Revenue | 2.28M (~75M THB) | 3.65M (~120M THB) | 5.41M (~179M THB) | 2.28M (~75M THB) | 3.65M (~120M THB) | 5.41M (~179M THB) |
| Payback on the plan price (EBITDA, mature year) | ~31 yr | ~3.2 yr (2.3 to 4.1) | ~1.1 yr | ~37 yr | ~3.8 yr (2.7 to 4.9) | ~1.2 yr |
What it says:
- **Plan A** breaks even on operating profit at **~0.2 million records a
year**; its adverse corner still loses money, because it would need
~1.0 million records to cover depreciation and the three presses make
0.58 million at that rate.
- **Plan B** breaks even at **~0.24 million records**, and its adverse
corner loses more (~1.1 million records needed to cover depreciation).
At the central cost and volume the price that covers its depreciation
is ~2.8 USD (~92 THB) a record.
- **On these numbers Plan B's extra ~35M THB earns little**: the same
EBITDA here (the calculator, which splits energy by plan, puts it ~0.06M
USD a year ahead for the PPA bill the owned array avoids), more
depreciation and a longer payback. Its case rests on what
the table leaves out: the PPA power bill it avoids (the BOI no longer
promotes solar installations since July 2025), full stamper metrology from the first
release, tours, the Payap programmes, and cassette and CD-R sales.
- **The caveats above hold for both:** a central EBITDA margin of ~47 %
is far above the 15 to 25 % pressing plants earn, the cost of specials
is not in the direct cost yet, and neither plan carries a contingency.
Treat the adverse columns as the honest ones.
The [calculator](../fleet-calculator.html) presets, at the team's
planning rates (3 records a minute per Duplex system) and its own cost
build-up, give at 850k records: **Plan A** EBITDA 2.17M USD, payback 2.3
years on the investment, cash payback in year ~3.8 and ~26 % IRR over ten
years with the reserve in year 0; **Plan B** EBITDA 2.23M USD, payback 2.7
years, cash payback in year ~4.2 and ~22 % IRR (pre-tax, pre-financing,
estimates). Both rose ~0.11M to 0.12M USD a year when steam moved from electric to
biomass (~4.2M THB a year less energy); the table above does not split
energy by fuel, so it does not show that saving.
## Operating picture at full capacity (five-press fleet)
The fleet this table describes (two Duplex systems and a Classic) is now
a growth option; the launch plant is in the section above. This table
keeps the earlier ~20 % specials share and the earlier capex; it is not
re-based (at 60 % specials the five presses are not Duplex-limited, so
the volume holds and the blend rises as in the launch table).
Built from the components above rather than asserted. The
[press fleet calculator](../fleet-calculator.html) runs the same P&L for
any fleet, output and specials share, with energy and headcount computed
from the fleet and these three cases as presets. Three scenarios,
each internally consistent: adverse pairs low volume with the low price
and high cost, favourable does the opposite, central takes midpoints.
Title-services contribution assumes 60–70% after lacquer blanks, styli
and nickel; a lacquer blank costs about **70 EUR** (team figure, October
2026), one per side, so ~160 USD a two-sided title before recuts. Cash overheads (admin, sales, insurance, facility running,
IT, professional fees, marketing) are estimated at **200–450k USD/yr**
and deliberately paired high-to-adverse. Depreciation is the 4.7–8.9M
capex of the earlier full vision over 10–15 years.
| USD/yr | Adverse | Central | Favourable |
|---|---|---|---|
| Records | 1.0M | 1.25M | 1.5M |
| Blended price | 3.50 | 4.05 | 4.60 |
| Direct cost | 2.58 | 1.94 | 1.30 |
| Contribution per record | 0.92 | 2.11 | 3.30 |
| Pressing contribution | 0.92M | 2.64M | 4.95M |
| Title-services contribution | 0.10M | 0.28M | 0.48M |
| **Total contribution** | **1.02M** | **2.92M** | **5.43M** |
| Cash overheads | 0.45M | 0.33M | 0.20M |
| **EBITDA** | **0.57M** | **2.59M** | **5.23M** |
| Depreciation | 0.89M | 0.55M | 0.31M |
| **Operating profit** | **−0.32M** | **2.04M** | **4.92M** |
| Payback on 4.7–8.9M capex | never | 2.3–4.4 yr | 1.0–1.8 yr |
Two things this makes visible that the previous figures hid.
**The adverse case loses money.** At 1.0M records, the low price, the
high cost and the high capex, the plant is EBITDA-positive but does not
cover depreciation. The old roll-up quoted operating profit of 0.6–1.2M
and never showed a loss anywhere. Utilisation and price realisation are
not upside levers here — they decide solvency.
**The favourable case is not credible, and that is a finding about the
cost table, not the business.** A 69% EBITDA margin is roughly triple
what pressing plants earn; even the central case at 47% is well above
industry norms of 15–25%. The direct cost table almost certainly
understates, because it counts only per-record consumables and direct
payroll. Missing at minimum: indirect production labour (supervision,
planning, warehouse), consumables beyond those listed, scrap and rework
above the reject allowance, water and effluent, inbound freight on
materials, inventory carrying cost, and sales commission. **Treat the
adverse column as the honest one until those lines exist.**
So this table is a sensitivity, not a forecast. The BOI CIT exemptions
(solar, automation, and any merit measures) shield part of early-year
profits where there are any; see [boi.md](../boi.md).
## What moves the model
- **Utilization decides solvency, not just upside**: the cost structure is
mostly fixed, so profit swings almost linearly with volume sold. 60%
utilisation at mature fleet size cuts operating profit by more than
half from the central case, and the adverse column above is already
loss-making at full volume
- **Mix**: color/splatter and boutique runs carry 20 to 50% price premiums
and suit the semi-automatic line; the title-services line (mastering,
cutting, stampers) has software-like margins once the rooms exist. At
the planned 60 %+ specials the Duplex presses' real rate decides the
volume: each extra record an hour on the Duplex adds about 1.7 to the
plant's hourly output at that share
- **Regional position**: an Asia-Pacific full-service plant competes on
turnaround and freight against EU/US plants for regional labels; pricing
power there is unproven and is the single biggest assumption in this
model. The turnaround claim is quantified in
[production-timeline.md](../production-timeline.md)
- **In-house galvanics** removes **somewhere between 175 and 665 USD** per
title of external stamper cost — the low end an industry-norm estimate,
the high end an upper-bound residual from a Thai reseller who is not
CNX's actual supplier — plus 1.5 to 5 weeks of turnaround. **Get the
Stamper Discs quote before this number is used for anything**
- **Energy**: solar plus heat recovery pushes the energy line toward the
low end and hedges Thai tariff rises
- **The currency mismatch is a live exposure.** Revenue is quoted to
export customers in USD or EUR while roughly two-thirds of the direct
cost base (labor, energy, local cartons, maintenance) is incurred in
THB. A stronger baht compresses margin directly: a 10% THB appreciation
takes roughly 0.09 to 0.17 USD off the gross margin per record without
a single operational change — enough to move the adverse case further
under water. Worth deciding early whether to quote regional customers
in THB.
## Honest caveats
- Still no signed customers and no seller-side validation. The August 2026
data point above is buy-side, from one plant and one buyer, and it
contradicts the model on per-title services and probably on run size.
The Making Vinyl trip and early conversations should test the 3.50 to
4.60 USD blended assumption, and the run-size question — before either
anchors a financing case
- Demand risk is real: vinyl demand is cyclical and capacity has been
added globally; the model assumes the plant can sell what it presses
- The reject allowance assumes the QC investment holds rejects at or below
industry norms; early production will run worse before it runs better
- FX is a snapshot. Every figure here restates research done at ~38
THB/EUR and ~33 THB/USD; the ranges are wider than the FX noise, but the
totals should be re-based, not just re-converted, if rates move much