docs/equipment/pheenix-alpha/: the four Pheenix Alpha electroforming flyers (2024: PASU silvering, PPPU pre-plating, PDPU dual-cell plating, PMPB passivation bench), renamed from their download hashes. docs/equipment/sibert/: the VSP, VSF and VSC technical specifications (2021), plus Sibert's 2008-09 optical-disc SPS literature and the 2008 Blu-ray stamper characteristics paper in sps-optical-disc-2009/. Two byte-identical duplicates in the download were dropped. New docs/equipment/galvanics.md, the metal-path counterpart to pressing-line.md: datasheet tables for both ranges and what they change. Pheenix is a second turnkey galvanics vendor next to Digital Matrix and can quote lacquer-to-record as one vendor; neither range includes water treatment. Utilities from the sheets (~27 kVA connected per line, DI water, 12-20 C cooling water, extraction sizes), ~5.6 m2 of footprint, and a cell count estimate (one PDPU at the low end, two at the high end). The Sibert machines are single-phase, 200/250/600 kg on castors, centre manually and list no data interface; the VSC locates on the punched hole; the finisher's water carries nickel. Weights, cycle times, prices and mould fit are listed as quote questions. Backlinks and small updates: README (bullet, layout tree, vendor list), roadmap items 6 and 23, vendor landscape, supplier map, exhibitor briefing (on-file notes, Sibert three-phase question answered), digital factory (Pheenix PLC data, Sibert data question, RFQ clause 5), quality automation (hardness on the centre slug, BD paper as the acceptance-spec model), sustainability (finisher water), total investment block label (numbers unchanged), scale (galvanics feeder note), crane weight table, process flow, pressing-line stamper-fit question, plant page detail lines.
403 lines
21 KiB
Markdown
403 lines
21 KiB
Markdown
# Overhead Crane, Maintenance Workshop and Visitor Corridor
|
||
|
||
Three additions to the building program, decided in October 2026:
|
||
|
||
1. **An overhead crane over the whole factory floor**, so machines can be
|
||
moved in, out and around without hiring a mobile crane or dragging
|
||
them on skates.
|
||
2. **A maintenance workshop** with a crane-served service bay, so a
|
||
machine can be lifted out of the line and serviced properly instead of
|
||
in place.
|
||
3. **A glazed visitor corridor at ground level through the factory**, so
|
||
guided tours see the whole process without being exposed to noise,
|
||
dust or plating chemistry, and without production having to stop or
|
||
escort people across the floor.
|
||
|
||
They are planned together because they collide with each other and with
|
||
the building: the crane decides where walls may go, the workshop sits
|
||
where the crane parks, and the corridor runs under the crane runway.
|
||
This page states what each one needs, what it changes in the
|
||
[construction RFQ](finance/phase1-construction-rfq.md), the
|
||
[zone table](scale.md) and [facility security](facility-security.md), and
|
||
what is still open. Every figure without a vendor or contractor behind it
|
||
is an estimate.
|
||
|
||
## 1. Overhead crane
|
||
|
||
### What it has to lift
|
||
|
||
| Item | Weight | Source |
|
||
|---|---|---|
|
||
| Newbilt press (HRP 12) | 1,350 kg | [Newbilt Duplex site requirements](equipment/newbilt/) |
|
||
| Newbilt extruder | 660 kg | same |
|
||
| Newbilt hydraulic aggregate (250 L tank, 50 L accumulator) | 600 kg | same, plus the [budgetary offer](equipment/newbilt/) |
|
||
| Pheenix AD12 automated press | **unknown**, ask Pheenix | not in any document yet |
|
||
| Sibert VSP punch / VSF finisher / VSC coiner | 200 / 250 / 600 kg, on castors | [Sibert specifications](equipment/sibert/) (2021) |
|
||
| Pheenix plating units (PPPU, PDPU), silvering unit, prep bench | unknown: dimensions published, weights not; each plating unit carries a 385 L tank, lifted empty | [Pheenix flyers](equipment/pheenix-alpha/), [galvanics and stamper prep](equipment/galvanics.md); ask with the quote |
|
||
| Water-treatment evaporator | unknown, lifted empty | to be asked with the quote |
|
||
|
||
**Planning capacity: 5 t safe working load** (estimate). It covers the
|
||
heaviest known lift with its lifting beam and slings at a wide margin and
|
||
leaves room for the automated presses until Pheenix states their weight.
|
||
If the AD12 turns out under about 2.5 t, price a **3.2 t** crane as the
|
||
alternative: lighter runway and frame, and possibly a lighter inspection
|
||
regime. Thai cranes fall under the Ministry of Labour's 2021 Ministerial
|
||
Regulation on machinery, cranes and boilers (the same regulation that
|
||
covers the boiler); a crane-industry summary puts cranes above 3 t on an
|
||
engineer inspection every three months. Confirm the intervals against the
|
||
regulation text before choosing the capacity.
|
||
|
||
The crane does **not** serve the outdoor plant. Boiler, chiller, cooling
|
||
tower, transformer and the BESS enclosure sit outside the main building
|
||
and are set by mobile crane as normal.
|
||
|
||
### What kind of crane
|
||
|
||
- **Single-girder electric overhead travelling (EOT) crane** spanning the
|
||
building's full 25 m width (about 24 m between rail centres), with an
|
||
electric wire-rope hoist. This is the default factory crane in the Thai
|
||
market, where most bridge cranes are imported from China and installed
|
||
by local firms.
|
||
- **Inverter drives on hoist and travel** with a slow creep speed, because
|
||
the job is setting precision machines on levelling pads, not moving
|
||
steel. Radio remote control, so the operator walks beside the load.
|
||
- Overload limiter, hoist limit switches, warning horn and light, and
|
||
**protected zones** (a standard option on modern crane controls) so the
|
||
hook cannot carry a load over the visitor corridor or over enclosed
|
||
rooms.
|
||
- **Light duty class.** Machine moves are a few a year plus occasional
|
||
maintenance lifts, so a light class (around ISO 4301 M3 to M4, estimate)
|
||
is enough.
|
||
- **Clean running.** The crane travels over a press hall where dust in a
|
||
groove is an audible defect: enclosed gearboxes, lubrication-free wheels
|
||
and an enclosed conductor rail, and the crane **parks over the
|
||
workshop**, not over the presses.
|
||
|
||
### What "the whole factory" means in practice
|
||
|
||
The runway runs the full length of the **production compartment**, wall
|
||
to wall and end to end: press hall, material area, stamper prep,
|
||
finishing, the workshop and the machine bay. It stops at the fire wall
|
||
that separates production from the finished-goods warehouse
|
||
([RFQ §1a](finance/phase1-construction-rfq.md) requires that wall to be
|
||
rated EI 60 or EI 120, and a crane cannot run through a fire wall). The
|
||
warehouse is forklift territory with no heavy lifts, so nothing is lost.
|
||
With a 300 to 500 m² warehouse at the dock end, the runway is roughly 40
|
||
to 48 m of the 60 m building (estimate, set by the warehouse depth). If
|
||
the fire strategy ends up without that wall, the runway can run the full
|
||
60 m.
|
||
|
||
### What it changes in the building
|
||
|
||
This is where the cost is, and it has to go into the shell price before
|
||
the contractor quotes. The RFQ currently says **"no crane"**.
|
||
|
||
1. **Frame designed for crane loads.** Crane brackets or stepped columns,
|
||
runway beams and rails along both long walls, end stops, and a frame
|
||
sized for the wheel loads and braking forces. In a PEB this is a known
|
||
option, but it is a different frame from the one priced so far.
|
||
2. **Hook height under the 7.0 m low eave.** The roof falls across the
|
||
25 m width, so the low side governs. With a single-girder hoist the
|
||
rail would sit somewhere around 5.5 to 6 m and the hook around 5 m
|
||
(estimate; it depends on the haunch depth at the low eave). That is
|
||
enough to lift a press and carry it low along a clear aisle, which is
|
||
the right way to move a machine anyway, but not to carry it over other
|
||
machines or rooms. Ask the contractor for the achievable hook height at
|
||
7.0 m and price **+1.0 m on the low eave as an option**. The option
|
||
costs wall cladding and about 10% more conditioned volume, so take it
|
||
only if the quoted hook height falls short.
|
||
3. **No full-height cross walls inside the crane zone.** A wall across
|
||
the building would stop the bridge. Partitions inside the zone stop
|
||
below the bridge, and where a load has to pass (press hall to
|
||
workshop), the partition has a **full-height opening closed by a
|
||
high-speed door**, because the hoist rope comes down from above and
|
||
needs a slot all the way up. Separation between zones is then by air
|
||
pressure, not by a sealed wall (see the workshop below).
|
||
4. **Rooms inside the crane zone are boxes with lids.** Galvanics, stamper
|
||
prep and any other enclosed room in the zone are built room-in-room
|
||
with their own ceilings below the bridge. Where heavy kit has to go in
|
||
(electroforming cells, the water-treatment evaporator), the ceiling
|
||
gets a **removable crane hatch**. The bridge passes over the lids;
|
||
loads do not (protected zones).
|
||
5. **The roof space belongs to the crane first.** HVAC ducts, sprinkler
|
||
mains, cable trays and lighting run above the crane envelope or along
|
||
the walls, never through the band the bridge travels in. Sprinkler
|
||
coverage under the bridge is an item for the fire designer.
|
||
6. **Vibration and the cutting room.** The crane runs on the building
|
||
frame. Keep the mastering and cutting room outside the crane zone (it
|
||
belongs at the quiet front of the building with the offices and
|
||
archive anyway), on a slab isolated from the frame columns, and do not
|
||
run the crane during a cutting session.
|
||
|
||
### Machine door: how machines get in and out
|
||
|
||
The vehicle ramp in the RFQ (10.5 m at 1:10, 4.5 m wide) already sits at
|
||
the far end of the building, opposite the loading docks. That end gets
|
||
the **machine door** and the **machine bay**:
|
||
|
||
- An insulated sectional door of about **4.5 m wide × 5.0 m high**
|
||
(estimate) with full seals. It opens only for machine moves, a few
|
||
times a year, so it does not undermine the airtight envelope the HVAC
|
||
and the burning-season PM design depend on; schedule moves outside
|
||
February to April where possible.
|
||
- The crane runway runs right up to the inside face of the door.
|
||
- **Method:** a rigid truck reverses up the ramp and through the door
|
||
into the machine bay, and the crane lifts the machine off the bed
|
||
inside the building. Three checks for the contractor: the ramp
|
||
transitions against the truck's ground clearance, door headroom for the
|
||
truck, and the machine-bay slab rated for **truck wheel loads**, which
|
||
are point loads and not covered by the 30 kN/m² distributed rating.
|
||
- **Fallback:** a truck-mounted crane sets the machine on skates at the
|
||
door threshold and the overhead crane takes it from there.
|
||
|
||
### Rough cost (estimate)
|
||
|
||
| Item | THB | USD |
|
||
|---|---|---|
|
||
| 5 t × ~24 m single-girder EOT crane, supplied and installed | 1.0M – 2.5M | 30k – 76k |
|
||
| Runway beams, rails, end stops, conductor rail, ~2 × 45 m | 0.8M – 1.6M | 24k – 48k |
|
||
| Frame premium for crane loads (brackets, heavier columns) | 1.0M – 2.5M | 30k – 76k |
|
||
| Machine door and truck-rated slab in the machine bay | 0.4M – 0.9M | 12k – 27k |
|
||
| **Crane total** | **~3.2M – 7.5M** | **~97k – 227k** |
|
||
|
||
## 2. Maintenance workshop and machine bay
|
||
|
||
### Where
|
||
|
||
At the ramp end, inside the crane zone, between the machine door and the
|
||
press hall. One space does two jobs:
|
||
|
||
- **Machine bay**: new machines land here, are unpacked, inspected and
|
||
documented before they go to the floor; machines leaving for vendor
|
||
repair are crated here.
|
||
- **Workshop**: a machine is disconnected, lifted out of the line with
|
||
the crane, set down on the service bay and worked on properly, with
|
||
tools, light and space around it.
|
||
|
||
The crane's parking position is above it, which keeps the idle crane off
|
||
the press hall.
|
||
|
||
### What is in it
|
||
|
||
| Area | Contents | Size (estimate) |
|
||
|---|---|---|
|
||
| Service bay | Clear crane-served floor for one press-sized machine with about 1.5 m working space all round (a Newbilt press stands on under 1 m², an AD12 on about 3.25 m²); bunded drip-tray floor; 400 V three-phase and 230 V outlets; compressed air drop; task lighting | ~60 m² |
|
||
| Bench area | Workbenches and vices, pillar drill, hydraulic hose crimper (the press hydraulics run at 180 to 200 bar and hoses are a routine spare), closed-loop parts washer, mould and platen bench, optionally a small lathe and mill for brackets and one-off parts | ~40 m² |
|
||
| Spares store | Lockable, shelved; every part tracked in the factory application (stock, minimum level, which machine it fits) | ~20 – 30 m² |
|
||
| Hot-work corner | Welding screen and fume extractor; hot-work permit, because paper, cartons and hydraulic oil share the building | ~10 m² |
|
||
| **Total** | | **~100 – 150 m²** |
|
||
|
||
**Spares are the uptime lever.** Newbilt service comes from Germany and
|
||
Pheenix from Sweden; the northern-dispatch service question in the
|
||
[supplier map](suppliers/equipment-suppliers.md) only partly closes that
|
||
gap. A press down for a seal or a heater should be back the same day from
|
||
the shelf, not after a courier.
|
||
|
||
### Keeping the workshop's dirt out of the press hall
|
||
|
||
Grinding dust, welding fume and oil mist must not reach the presses. Since
|
||
the crane zone rules out a sealed full-height wall (section 1), the
|
||
workshop is held at **negative pressure** to the press hall: local
|
||
extraction at the welding and grinding positions, an exhaust that keeps
|
||
air flowing from the hall into the workshop over the top of the partition
|
||
and through the high-speed door, never the other way. The HVAC zoning in
|
||
[facility security](facility-security.md) gains the workshop as a zone
|
||
below the press hall in the pressure cascade.
|
||
|
||
### Oil, waste and water
|
||
|
||
- Hydraulic oil drums on spill pallets, spill kits at the service bay,
|
||
used oil and oily rags collected by a licensed waste contractor under
|
||
DIW manifests.
|
||
- **No floor drain.** A dry workshop keeps the zero contaminated water
|
||
commitment in [sustainability](sustainability.md) simple: spills are
|
||
absorbed and collected, never washed down.
|
||
|
||
### Safety
|
||
|
||
- **Isolation before lifting.** Before a machine is disconnected:
|
||
electrical lockout, steam isolated and vented, and the hydraulics
|
||
depressurised, including the aggregate's 50 L gas-loaded accumulator,
|
||
which holds pressure after the pump stops. Written lockout/tagout per
|
||
machine.
|
||
- **A lift plan for every machine move**, a trained crane operator and a
|
||
trained slinger, and nobody under the load.
|
||
- **Warranty.** Newbilt's offer requires every installation to be
|
||
commissioned by an engineer trained on Newbilt machinery, the first one
|
||
by Newbilt itself, and ties warranty claims to that. Ask Newbilt in
|
||
writing whether lifting a press into the workshop and back counts as a
|
||
re-installation during the warranty period.
|
||
|
||
### Rough cost (estimate)
|
||
|
||
Workshop fit-out (benches, hand and power tools, hose crimper, parts
|
||
washer, welding set and fume extractor, shelving, spill equipment, small
|
||
machine tools if wanted): **1.0M to 2.5M THB (~30k to 76k USD)**. The
|
||
first spares stock sits in the existing working-capital line in
|
||
[total investment](finance/total-investment.md).
|
||
|
||
## 3. Visitor corridor
|
||
|
||
### What it is for
|
||
|
||
Guided tours for artists, labels, investors, schools and the public that
|
||
show the whole chain from lacquer to packed record, while visitors:
|
||
|
||
- hear nothing louder than conversation, so no hearing protection;
|
||
- breathe the corridor's own filtered air, never press hall or galvanics
|
||
air;
|
||
- need **no PPE** at all, which turns a tour from an escorted, kitted-out
|
||
floor walk into something that can run several times a day;
|
||
- cannot touch anything, distract an operator or bring dust onto the
|
||
floor. The glass protects production as much as it protects visitors.
|
||
|
||
### Route
|
||
|
||
At ground level along **one long wall, the car-park elevation**, which is
|
||
where the RFQ already places the main entrance and a second exit at the
|
||
far end of the same wall ([RFQ §1b](finance/phase1-construction-rfq.md)).
|
||
The tour starts at reception and leaves by the far exit, or loops back.
|
||
|
||
Along a wall rather than down the middle, for three reasons:
|
||
|
||
- it does not cut the production floor in two, so forklift routes and
|
||
crane moves never cross it;
|
||
- the strip under the crane runway is where the hook reaches least well
|
||
anyway, so the corridor uses the least valuable floor;
|
||
- both ends already have exits.
|
||
|
||
**Stations follow the process order**, which means the process layout has
|
||
to run along the corridor:
|
||
|
||
1. Mastering and cutting (window into the cutting room)
|
||
2. Galvanics (fixed, sealed window in the clean room wall; no opening, no
|
||
shared air)
|
||
3. Stamper prep
|
||
4. Material lab and PVC handling
|
||
5. **Press hall**, the long glazed stretch and the centre of the tour
|
||
6. Trimming and 100% optical inspection
|
||
7. QC and listening, with a headphone listening point
|
||
8. Finishing and packaging, where the records leave production
|
||
|
||
Finished goods sit behind the fire wall and are shown from a fire-rated
|
||
window or not at all. The concept drawing
|
||
[facility-layout.drawio](facility-layout.drawio) predates this corridor
|
||
and the detached utility yard and does not yet follow this order; it
|
||
needs redrawing at the next layout pass.
|
||
|
||
### How it is built
|
||
|
||
- **Room-in-room**: a glazed wall on the production side, a solid roof at
|
||
about 3.0 m (an acoustic lid and protection from anything dropped),
|
||
floor on the slab.
|
||
- **Clear width about 2.4 m** (estimate): a group of about 15 with a guide,
|
||
and room for a wheelchair to pass.
|
||
- **Length about 45 to 55 m**, so roughly **110 to 130 m²** of floor and
|
||
**~150 m²** of glazing (estimate).
|
||
- **Acoustics.** Press halls typically run 80 to 90 dB(A) near the
|
||
presses (to be measured on this plant). Laminated acoustic double
|
||
glazing in the Rw 40 to 45 dB class (estimate) brings that down to
|
||
roughly 40 to 50 dB(A), so a guide can talk without a headset system.
|
||
Seals, penetrations and door gaskets decide whether that is achieved,
|
||
more than the glass does.
|
||
- **Air.** Its own HVAC zone with filtered supply at slight positive
|
||
pressure to the press hall, so any leak runs from the corridor into the
|
||
hall. It is the cleanest-air space a visitor enters, which matters in
|
||
burning season.
|
||
- **Glass safety.** Toughened laminated glass; a kerb or steel barrier on
|
||
the production side wherever forklifts run; the crane's protected zone
|
||
over the whole corridor.
|
||
- **Fire and escape.** The corridor is an escape route with exits at both
|
||
ends. Where it runs along a fire compartment wall or the galvanics room,
|
||
that stretch of glazing must be fire-rated (EI), which costs several
|
||
times standard glazing, so keep those stretches short.
|
||
- **Viewing.** Light the production side brighter than the corridor and
|
||
use low-reflection glass, or the visitors mostly see themselves.
|
||
|
||
### Step-free access is now required
|
||
|
||
The building floor sits at **+1.2 m** and the RFQ's only ramp is the 1:10
|
||
vehicle ramp, which it notes is not an accessible gradient and asked to
|
||
be told now if a step-free entrance is wanted. Public tours make it a
|
||
requirement: a **1:12 ramp at the main entrance**, about 14.4 m of run
|
||
for the 1.2 m rise plus intermediate landings, with handrails both sides.
|
||
|
||
### Running tours
|
||
|
||
- **Visitor screens** at the stations showing live, non-confidential
|
||
plant data: a read-only visitor view of the factory application in the
|
||
style of the [plant operation page](plant-operation.html), on kiosk
|
||
displays wired like the station kiosks. The visitors' own phones stay
|
||
on the guest Wi-Fi, which reaches the internet only (VLAN plan in
|
||
[digital factory](digital-factory.md)).
|
||
- **Confidentiality.** Unreleased artwork and labels are visible on the
|
||
floor, and some clients will not want that. Options: schedule tours
|
||
around confidential runs, a no-photography rule, or switchable privacy
|
||
glass at the label and packaging stations (extra cost, estimate on
|
||
request).
|
||
- **CCTV notice** at the corridor entrance; footage of visitors falls
|
||
under PDPA like staff footage.
|
||
- **The tour ends where people can buy records.** A small shop or
|
||
pick-up counter at the exit fits the
|
||
[artist platform](artist-platform.md) idea of fans collecting their
|
||
copy at the plant.
|
||
- **Access control.** The corridor is its own zone. No door leads from it
|
||
onto the production floor except, if the fire strategy needs one, an
|
||
access-controlled staff door.
|
||
|
||
### Rough cost (estimate)
|
||
|
||
| Item | THB | USD |
|
||
|---|---|---|
|
||
| Acoustic laminated glazing, ~150 m² at 6,000 – 15,000 THB/m² | 0.9M – 2.3M | 27k – 70k |
|
||
| Structure, roof, finishes, HVAC zone, lighting, screens | 1.0M – 2.0M | 30k – 61k |
|
||
| 1:12 accessible entrance ramp with landings and handrails | 0.3M – 0.6M | 9k – 18k |
|
||
| **Corridor total** | **~2.2M – 4.9M** | **~67k – 148k** |
|
||
|
||
## What the three add up to
|
||
|
||
| | Area | THB | USD |
|
||
|---|---|---|---|
|
||
| Overhead crane and machine door | (in the shell) | 3.2M – 7.5M | 97k – 227k |
|
||
| Workshop and machine bay | 100 – 150 m² | 1.0M – 2.5M | 30k – 76k |
|
||
| Visitor corridor and accessible entrance | 110 – 130 m² | 2.2M – 4.9M | 67k – 148k |
|
||
| **Total** | **~210 – 280 m²** | **~6.4M – 14.9M** | **~195k – 450k** |
|
||
|
||
All estimates, not yet in the roll-up in
|
||
[total investment](finance/total-investment.md); that page lists them as
|
||
added scope until the next re-base.
|
||
|
||
**On area**: the 1,500 m² phase 1 footprint was already tight for the
|
||
zone table in [scale](scale.md). Moving the boiler and chiller into the
|
||
detached utility yard freed about 126 m² there, and scale.md left open
|
||
whether to shrink the building or grow the program into it. These
|
||
additions answer that: the program grows into it. At the lower half of
|
||
the zone table everything still fits; at the upper half it does not, and
|
||
the release valve is the one scale.md already names, moving finished
|
||
goods into the phase 2 building.
|
||
|
||
## Changes made elsewhere
|
||
|
||
- [Construction RFQ](finance/phase1-construction-rfq.md): frame type
|
||
changed from "no crane" to crane-ready, a new section for the crane and
|
||
the machine door, the accessible entrance ramp made a requirement.
|
||
- [Scale](scale.md): workshop and corridor added to the zone table.
|
||
- [Facility security](facility-security.md): visitor management and
|
||
access zones updated for corridor tours.
|
||
- [Worker safety](worker-safety.md): lifting operations and the workshop.
|
||
- [Roadmap](roadmap.md): item 15 (building fit-out).
|
||
|
||
## Open decisions
|
||
|
||
1. **Crane capacity**: 5 t or 3.2 t, once Pheenix states the AD12 weight
|
||
and the inspection intervals are confirmed.
|
||
2. **Low eave**: keep 7.0 m or raise to 8.0 m, once the contractor states
|
||
the achievable hook height.
|
||
3. **Runway length**: stop at the warehouse fire wall (recommended) or run
|
||
the full 60 m if the fire strategy drops the wall.
|
||
4. **Process layout along the corridor**: the stations above need the
|
||
layout redrawn in process order along the car-park elevation.
|
||
5. **Fire-rated glazing extent**, from the fire strategy.
|
||
6. **Tour policy**: who tours, how often, and the confidentiality rule
|
||
for client work on the floor.
|