# BOI Investment Promotion
|
|
|
|
The project will apply for promotion by the Thailand Board of Investment.
|
|
Research snapshot from July 2026, based on the BOI Investment Promotion
|
|
Guide 2025/2026 and advisory sources; BOI revises its measures roughly
|
|
annually, so every scheme cited here must be reconfirmed at filing time.
|
|
The exact activity sub-code needs confirmation by a BOI-registered
|
|
consultant before the application.
|
|
|
|
## The strategic picture
|
|
|
|
Vinyl pressing is, in BOI terms, basic plastic consumer-goods manufacturing
|
|
(Category 6, chemicals/paper/plastics), which lands in **incentive Group B**:
|
|
no corporate income tax holiday on the core pressing activity, but the full
|
|
non-tax package and machinery duty exemption. The tax value is engineered on
|
|
top through the upgrade measures, where this project happens to be strong:
|
|
|
|
- **Solar and battery**: the alternative-energy measure (Announcement
|
|
2/2568, April 2025, under the Smart and Sustainable Industry framework)
|
|
grants CIT exemption based on the solar investment. Eligible spend
|
|
explicitly includes PV modules, inverters, BESS and BESS inverters, and
|
|
mounting structures, capped at THB 12M/30M/40M of investment value per MW
|
|
depending on investment type. The planned Deye + Gobel installation
|
|
converts directly into CIT-exemption headroom.
|
|
- **Automation and metrology**: the Smart and Sustainable Industry upgrade
|
|
measure (Announcement 15/2565, refreshed July 2025) rewards automation,
|
|
smart machinery, and energy efficiency, typically 3 years of CIT
|
|
exemption capped around 50% of the qualifying upgrade investment. The
|
|
automated presses, inline optical inspection, and stamper metrology are
|
|
the natural fit.
|
|
- **R&D merit**: investing at least 1% of revenue in Thai R&D adds 1 to 3
|
|
CIT-exemption years and can lift the exemption cap. In-house mastering,
|
|
galvanics process development, and recycled-PVC work could be framed as
|
|
qualifying development.
|
|
|
|
So the application is pitched on solar, automation, and technology content,
|
|
not on "we press plastic discs."
|
|
|
|
## What Group B still delivers (the core value)
|
|
|
|
- **Machinery import duty exemption**: significant with the entire equipment
|
|
list imported (Germany, Sweden, USA, Japan)
|
|
- **100% foreign ownership** of the promoted manufacturing company,
|
|
overriding Foreign Business Act restrictions for the promoted activity
|
|
- **Land ownership** for the promoted operation despite foreign
|
|
shareholding, plus a small allowance for office/residential use; note the
|
|
privilege is tied to the promotion, which matters for the buy-vs-lease
|
|
decision
|
|
- **Visas and work permits** via the One Stop Service, without the usual
|
|
four-Thai-employees-per-permit rule; relevant for foreign commissioning
|
|
engineers and the technical consultant
|
|
- **Raw material duty relief**: exemption for export production (1 to 5
|
|
years, renewable) and up to 90% reduction for domestic-sale production
|
|
|
|
## Requirements
|
|
|
|
- Minimum investment THB 1,000,000 excluding land and working capital
|
|
(comfortably cleared by the first pressing line alone)
|
|
- Debt-to-equity ratio no higher than 3:1, maintained for the life of the
|
|
privileges; plan the equity/loan mix for the machinery and solar capex
|
|
accordingly
|
|
- Modern machinery and process expected; ISO/environmental compliance for
|
|
larger projects
|
|
- BOI promotion does not replace the factory license (Ror.Ngor. 4),
|
|
hazardous substance registration, or wastewater permitting; the galvanics
|
|
effluent is the most likely regulatory friction point regardless of BOI
|
|
status
|
|
|
|
## Regional angle: Northern Thailand
|
|
|
|
Chiang Mai, Lamphun, and Lampang sit in the **Northern Economic Corridor**,
|
|
which BOI promotes as a creative-economy base; a vinyl/music manufacturing
|
|
story fits that narrative. Locating in the **Northern Region Industrial
|
|
Estate in Lamphun** simplifies factory licensing and land questions and
|
|
provides shared central effluent treatment, which helps the galvanics
|
|
permitting. Legacy "Zone 3" incentive tables still found online are
|
|
outdated; the current area-based add-ons for Lamphun/Lampang must be
|
|
confirmed with BOI directly.
|
|
|
|
## Process and timeline
|
|
|
|
1. File via the BOI e-Investment system, then present the project at an
|
|
analyst meeting
|
|
2. Decision: about 40 working days for projects under THB 200M (60 to 90
|
|
working days for larger tiers); roughly 4 to 6 months end to end to the
|
|
promotion certificate in practice
|
|
3. Incorporate the company (if not yet done) and accept the certificate
|
|
4. Import machinery within the duty-exemption window, commonly 30 months
|
|
from certificate issuance (extendable); the Newbilt/Pheenix delivery
|
|
schedule must fit inside it
|
|
5. Reach full operation by the certificate deadline (typically about 36
|
|
months), with progress reporting, annual reports, machinery lists, and
|
|
the 3:1 debt-to-equity ratio maintained throughout
|
|
|
|
## Sequencing consequence
|
|
|
|
BOI approval comes **before** company incorporation is finalized and before
|
|
any machinery purchase orders: duty exemption does not apply retroactively
|
|
to equipment already imported, and the certificate defines the import
|
|
window. The BOI application is therefore a dependency at the top of the
|
|
project timeline, ahead of equipment contracts.
|
|
|
|
## Open items
|
|
|
|
- Confirm the exact activity sub-code and tier for vinyl/PVC consumer-goods
|
|
pressing (Group B assumption is well supported but not code-verified)
|
|
- Confirm the live versions and per-MW caps of the solar and
|
|
smart-and-sustainable measures at filing time
|
|
- Confirm current NEC/Lamphun area add-ons
|
|
- Engage a BOI-registered consultant to structure the application so the
|
|
solar, automation, and R&D measures stack on the base promotion
|
|
- Keep any future label/content/retail arm in a separate entity: media and
|
|
service activities carry different (and sometimes Thai-ownership)
|
|
conditions, and mixing them muddies a clean manufacturing application
|