A separate FreeCAD 26.3 model (the Mueang Chi model is untouched) sites
the plant on a 110 m square placeholder plot of Payap land, built from
BIM objects (Arch Site, Buildings and Levels, walls, slabs, columns,
beams, a ramp, Spaces with computed areas, Equipment). Every object sits
on an expression-driven base, so the Params sheet drives plot, setbacks,
floor level, building sizes, fire wall line and office gap (checked:
plot 110 to 120 m and factory 84 to 90 m, everything followed).
- Factory 84 x 25 m, production only, in process order along a 54 m
glazed corridor; press hall 465 m2 with the October fleet (two Duplex
systems, each EX 50 + EX 35, and the Classic); crane to the fire wall;
machine door and 12 m ramp at the north-west corner.
- Office building 24 x 15 m, 12 m away on its own slab with a covered
link: reception, offices, meeting/training, mastering and cutting,
listening, IT, archive. Resolves the crane-zone conflict of the old
sketch.
- Utility yard behind the press hall (boiler and chiller flagged for
re-sizing), gate, truck apron, car park, service road.
- site-candidates: new section and plot-fit note; crane doc: conflict
resolved, 54 m corridor; README bullet and layout lines; the old
sketch is labelled as Mueang Chi with the earlier fleet.
Payap also wants to work closely with the project on new student
programmes: audio engineering (mastering, lathe cutting), IT, business
administration and more.
New docs/payap-partnership.md: why it fits (mastering/cutting engineers
are the hardest hires; Payap has music, IT, business, communication arts,
an English-language International College and pharmacy labs; the plant has
a lathe, production data and a real factory application), programme areas
mapped to the docs they draw on, and what it changes: a reason to bring
the cutting room (roadmap item 27) forward, a cutting engineer before the
students, lacquer and stylus cost of teaching, pre-release security for
customer audio, student access and safety, IT work on staging only, the
link to the Payap land, BOI R&D merit. Suggested form: MOU, internships,
short certificate courses first, degree tracks later; what to settle in
writing and questions for the next meeting.
Links from README (bullet, layout), site-candidates, roadmap item 27, the
supplier map's open training item and the BOI open items.
Payap University (Chiang Mai) is interested in leasing land to the
project; a pharmaceutical facility is under construction on the same land.
New docs/site-candidates.md puts the three options side by side (Mueang
Chi lease, Northern Region Industrial Estate, Payap) with the public facts
on Payap (Mae Khao campus on the Chiang Mai-Lampang superhighway, bought
as low-lying land, ~275 acres; Faculty of Pharmacy cosmetics production
facility tendered July 2024; RPAH cannabis/herbal bioreactor centre), why
it is attractive (5 km from the old city, a university partner with music,
pharmacy and labs, production already being built there) and the checks
that could rule it out, in order: zoning for pressing, boiler and later
electroplating; whether the university can lease to a company; the GMP
neighbour's sensitivity to our emissions (argues against biomass steam
there); flooding; plot fit; galvanics consent. Questions for the next
meeting listed. Nothing re-sited: model, RFQ and site code stay on
Mueang Chi until a plot is known.
README (intro, bullet, layout), roadmap item 9 and the lease fork in
project-timeline link to it.