Commit Graph
22 Commits
Author SHA1 Message Date
grabowski 475623e9f2 Archive the father as well as the mother; how many represses a mother carries
Decided (October 2026): the plant keeps the father and the mother of every
side. production-timeline.md (repress section) records the decision and the
rule of thumb with sources: about 10 stamper sets per mother before it
degrades (Third Man Pressing FAQ, a Nashville plater via WPLN), fewer in
quality-minded sources (5 VinyLab, 6 to 8 Stereo Review 1962); a father
grows about 5 to 10 mothers. So a mother covers roughly ten represses
(10,000 to 20,000 records a side) and a worn one is replaced from the
archived father without a new cut. galvanics.md: 4 archived parts per
title, ~1,200 to 2,400 a year; new open question to all galvanics
candidates (sets per mother, mothers per father, storage).
artist-platform.md repress paragraph.

Demos: make-a-record and artist-order say father and mother are archived;
factory console archives the father on represses too, counts stamper sets
per mother (shown in the genealogy and the customer's metal card), and the
metal archive counts fathers and mothers.
2026-10-16 11:17:13 +07:00
grabowski e49abf89d3 Utilities: build the backbone once, add modules with the presses; four-module boiler hall and chiller compound
Deploy test site / deploy (push) Successful in 57s
Phased build list for steam, cooling and hydraulics (launch, Duplex 1,
Duplex 2, Classic, options): everything cheap to oversize and costly to
retrofit (rooms, pads, headers and ring mains with a valved branch per
press position, tanks, HX frame, feeders, one sequencer) is built for the
five-press fleet at launch; boilers, chillers and hydraulic pump sets come
in identical modules as presses arrive. The Single 2.1 aggregate is
proposed as the first central pump set; per-branch isolation and filters.

Rooms sized for four modules each (user decision, estimates until vendor
footprints): boiler hall ~18 x 9 m for four 500 kg/h positions (fired case,
AIX DZL0.5 body), open screened chiller compound ~12.5 x 10.8 m with four
pads (250 kW at 40 C ~ Carrier 30RB 080-090), ~40 m2 pump and HX room; the
cooling tower pad of the water-cooled concept is dropped. Yard 178 -> ~379
m2. Four boilers carry ~8 presses with N+1; four 250 kW chillers carry the
five presses with CH-4 as reserve and no growth position unless the pads
take the ~350 kW frame (RFQ option).

- scale.md: yard table and basis, utility phasing section
- pressing-line.md: hydraulics phasing and re-quote questions
- steam-cooling.html: B-4 position, phasing and rooms card, details, RFQ
  questions (pw_sc_check clean)
- construction RFQ: yard table, sealed area 6,549 m2 (68 %)
- total-investment: added-scope row +73k to +122k USD (building rate on
  the ~200 m2 the yard grows by)
- Payap parts model: yard rebuilt from Params (blr_n, blr_inst, ch_*,
  bh_*, cy_*, pr_*), renders updated
2026-10-14 21:02:30 +07:00
grabowski 7af5d89dd0 Steam and cooling plant for the five-press fleet; utilities re-based
Deploy test site / deploy (push) Successful in 44s
New page docs/steam-cooling.html (site /demos/steam-cooling/): the
utility plant as a clickable process diagram. Steam side: raw water,
softener and dosing, feed tank with heat-pump feedwater recovery, feed
pumps, a bank of two 500 kg/h boilers (third for N+1 as an option),
separator and metering, optional accumulator, blowdown, the 10 bar
header with a valved, metered branch and trap per press, drip legs and
condensate return. Cooling side: Newbilt's press outlets are open (max.
2 bar), so returns drain to a warm tank, pass the heat pump, an optional
dry cooler and a plate heat exchanger to a cold buffer tank, and VFD
pumps feed the 20 to 25 C header at ~10 bar to every press, the
extruders and the central hydraulic oil cooler; the chiller loop
(three 250 kW air-cooled modules at 40 C ambient, fourth as option) stays
closed and clean. Galvanics cooling (12 to 20 C) is a separate circuit.
Operating cases (launch, Duplex system 1, five presses, one module down)
show demand against installed capacity; design basis with sources,
equipment schedule, RFQ questions. Static SVG, no per-frame work.

Design basis at Newbilt's per-machine figures: steam 750 to 900 kg/h,
cooling 652.5 kW (625 presses, 15 extruders, 12.5 hydraulics), 305 to
540 l/min circulating. Also found: Newbilt's 53 l/min at ~60 C out is
~140 kW, above its 125 kW peak; listed as a re-quote question.

Re-based in the same commit:
- scale.md: electrical table (chiller bank ~210 to 325 kW electrical,
  plant peak ~430 to 700 kW, ~950 to 1,330 kW with electric steam),
  grid 800 to 1,000 kVA (1,250 to 1,600 with electric steam, Schedule
  4 past 1,000 kW), tariff 4.5M to 6.8M THB/yr, battery ~1 h of chiller
  peak, boiler and chiller banks, biomass up to ~550 t/yr at 1.5 M
  records, utilities money line.
- sustainability.md, biomass.md: same figures; electric steam 5.2M to
  6.0M THB/yr mature, 1.6M to 1.8M early; fuel saving 4.0M to 5.4M.
- utilities CSV: boiler bank, chiller bank with HX and tanks, softener
  and loop treatment re-sized; baseline 23.98M-41.63M -> 30.07M-51.33M.
- total-investment.md: re-size as an added-scope row (+185k / +294k
  USD); headline 4.7M to 8.9M unchanged until the investment re-base.
- pressing-line, equipment-suppliers, facility-security, fleet
  calculator (boiler 1000 kg/h, chiller 750 kW), plant page detail
  texts; README, landing page, build.sh.
2026-10-14 09:58:27 +07:00
grabowski c6bec71442 Press fleet calculator: target output and specials share to fleet mix and needs
Deploy test site / deploy (push) Successful in 37s
User, October 2026: calculations for the later business plan, starting
from 2 Duplex + 1 Classic at 3 records a minute per Duplex and 2 per
Classic, as an interactive tool on the website: pick the yearly output
and the share of splatter/specials, get the machine mix and all the
requirements (people, hydraulics, power, ...).

docs/fleet-calculator.html (single static page, no dependencies):
- target mode sizes the fleet (specials only on Duplex with its EX 35;
  grow with Classics or with Duplex systems; start fleet as the floor);
  fleet mode takes a fleet and gives its output at the specials share;
- output, capacity, utilisation and the mix bar per machine type;
- needs: people per shift and in total, galvanics operators, machines,
  connected kVA and average kW, MWh/yr, central hydraulics (flow, motor,
  oil, accumulator), steam, cooling and cooling water, compressed air,
  press floor, room climate, compound, trim, titles, electroformed parts
  and plating units; checks against the 400 kg/h boiler, 250 kW chiller
  and the 870 m2 Payap press hall;
- ladder from the start fleet to a full Payap press hall, click to load;
- every assumption editable with its source (Newbilt Duplex site
  requirements V14 and offer 240620-04, scale.md, galvanics.md, revenue
  model, Payap model; estimates labelled), shareable link via the hash.
The Classic counts as one HRP 12 press plus one extruder until Newbilt
states figures (Toolex Alpha leaflet as a cross-check).

Site: DEMOS entry (/demos/fleet-calculator/) and landing-page entry.
README bullet and layout line; backlinks from scale.md (capacity) and
pressing-line.md (current plan).
2026-10-10 18:21:47 +07:00
grabowski 7da64088ce Duplex cell layout: one operator, presses turned towards him
User sketch, October 2026 (filed as docs/equipment/
duplex-cell-layout-sketch.png; arrangement only, the user notes it is not
to scale): operator in the middle, the two presses either side turned 45
degrees towards him, EX 50 and EX 35 side by side behind him, one trimmer
per cell in front on the left.

Sized from the Newbilt site requirements p. 10 (press ~0.9 m2, extruder
~0.5 m2, hydraulic aggregate ~1.0 m2, walk-around space, >= 60 cm to
walls, room height >= 2.5 m): cell ~5 x 3 m, 0.6 to 0.8 m between
machines; EX 35 and trimmer footprints are estimates. The layout drawing
the site requirements refer to on p. 11 is missing from our copy: ask
for it with the re-quote. README layout line for the sketch.
2026-10-10 17:43:00 +07:00
grabowski d9f3a4b88e Compound storage for tens of colours; stamper prep open to galvanics
User, October 2026: special designs will need tens of colours, so the
compound store needs far more space, with maybe a few silos for black and
the standard colours; and the wall between stamper prep and galvanics is
to go.

- pressing-line: "Compound storage" bullet (colour store with pallet
  racking, ~100 positions in the Payap model, estimate; outdoor silos
  proposed; compound stays on the ground floor, ~160 to 270 t a year at
  the mature fleet; sacks vs big bags decides the silo filling).
- galvanics: stamper prep open to galvanics, one clean zone.
2026-10-10 17:21:33 +07:00
grabowski 4263fbbd9b Payap model v2: bigger factory, shared plant room, separate water treatment
User, October 2026: the factory is too small and needs room to grow
(possibly ten more Classics), one shared hydraulic and air supply, water
treatment perhaps in a separate building connected to the galvanics lab,
and a fully equipped workshop (maintenance tools, 3D printers, maybe a
lathe and a small CNC mill).

Model (rebuilt live in FreeCAD 26.3, BIM objects, Params-driven,
parametric check plot 135->145 m and factory 112->120 m passed):
- plot 135 m (11.4 rai) with a reserve; factory 112 x 25 m, 16 bays,
  82 m visitor corridor, fire wall at 90 m;
- press hall ~870 m2: two Duplex systems (EX 50 + EX 35), the Classic,
  ten future Classic positions in two rows on a service trench;
- central hydraulics and compressed-air plant room (~62 m2);
- water treatment building 12 x 10 m behind galvanics: buried duct
  (gravity from the +1.2 m floor), covered crossing 6 m clear;
- workshop ~200 m2 with benches, tool cabinets, 3D printers, lathe,
  small CNC mill, drill, saw, welding bay, press, washer, measuring table.

Docs: galvanics (water treatment building, proposed), crane doc (workshop
fit-out; lathe and CNC mill not yet priced; corridor now 82 m),
site-candidates Payap section rewritten, README bullet.
2026-10-10 16:47:44 +07:00
grabowski 9e0c5d4045 Fleet: one shared hydraulic and air supply; room for ten more Classics
User, October 2026: the presses run from one shared hydraulic supply
and one compressed-air supply, and the plant may add up to ten more
Newbilt Classics at some point.

- pressing-line: fleet table and intro (shared central supply), new
  bullets on the shared supply and the expansion option, re-quote point
  (central supply for the whole fleet, extendable, can the Classic run
  from it), Hydraulics bullet now the plan.
- scale: "Expansion (option)" capacity row, ~4.7 to 5.8M records/yr on
  the same basis, explicitly outside revenue model and investment;
  utilities note: fifteen presses would need ~2.3 to 2.7 t/h steam and
  up to ~1.9 MW cooling, a utility phase of its own.
2026-10-10 16:47:34 +07:00
grabowski 3a758fcffb Fleet: each Duplex has an EX 50 main and an EX 35 colour extruder
Correction from the user: the two Duplex systems are not in the
two-extruder configuration. Each runs two HRP 12 presses from an EX 50
main extruder with an EX 35 auxiliary extruder beside it for a second
colour; the Classic stays. Fleet still five presses. Updated in
pressing-line (table, phasing, re-quote: EX 50 vs the VEX 50 of the 2024
quote, and whether one EX 50 keeps both presses at full rate), scale,
total investment (wording; estimates unchanged), roadmap item 4, README.
2026-10-10 16:11:46 +07:00
grabowski c50417668b Press fleet: two Newbilt Duplex systems with an extruder per press, plus a Classic
The current plan (user decision, October 2026) replaces the 50/50 target
(two semi-automatic presses and two Pheenix AD12s) with an all-Newbilt
fleet of five presses: two Duplex systems in Newbilt's two-extruder
configuration (two HRP 12 presses, an extruder each, one hydraulic unit)
and one Classic fully automatic press.

- pressing-line.md: new "Current plan" section (fleet table, what it
  means, phasing from the Single 2.1 as the first half of system 1,
  re-quote questions); site requirements per Duplex system.
- scale.md: capacity table and basis (368 to 448 records/h, ~1.06 to 1.5M
  a year on two shifts, same range as before); pressing electrical row;
  steam and cooling flagged, not re-based: five presses draw ~750 to 900
  kg/h of steam and up to ~625 kW of cooling at Newbilt's per-press
  figures, against the 400 kg/h / 250 kW sized for one Duplex.
- total-investment.md: fleet change as an added-scope row (system 2
  ~230k-300k and the Classic ~290k-460k, estimates; -60k / -160k against
  the two blocks it replaces); headline unchanged until the re-base.
- roadmap items 4, 5 and 24, revenue model mature row, crane doc (the
  Classic's weight now decides 5 t or 3.2 t), vendor landscape (AD12 is
  the comparison for the Classic), README.

The business plan docx is not regenerated.
2026-10-10 16:05:27 +07:00
grabowski f1334f4756 OMS introduction letter and links, Sibert's answer (9 October 2026)
OMS (Lou Wullms) sent its introduction letter, filed in
docs/equipment/oms/: wet-room units with reference prices, two 4-cell
configurations (EUR 224,000 basic with two EFS2-200, EUR 311,000 advanced
with one AEFS4-250 and PLC; installation days extra), capacities of 24
and 32 shells in an 8-hour day, utilities, rooms, staffing, used
equipment, and five contacts for buying a cutting lathe. Recorded in
galvanics.md (tables, our reading: the advanced units add up to EUR
314,000, know-how transfer is left out of both totals although CNX has no
plating know-how, the basic set has no passivation unit), the exhibitor
follow-ups, vendor landscape (new section on used lathes and cutting-room
contacts, plus Lou's three websites), supplier map, roadmap items 6 and
13, total investment (basis note only, block unchanged) and the scale
people estimate. Open: forward the letter to Simona, as Lou asked.

Sibert (Ian Locke, 9 October): footprints and formal quotations when we
are ready; settle the pressing side first, hopefully with Pheenix, and
mention his recommendation if we do; impressed by the green-factory
plans (supplier feedback). Open: pass on the recommendation if Pheenix is
chosen.

CNX-01 in proplan: OMS basic and advanced added as options to D-002 with
their reference prices in THB; budget line 3 notes the OMS range.
2026-10-10 15:52:23 +07:00
grabowski 90d8a3778a Record the replies to Sibert and OMS
- Sibert: back in Thailand, investor meeting in preparation, his OMS/Pheenix
  advice noted; itemised quotation not yet requested.
- OMS: met in Haarlem; role split given to Lou (Simona management and audio,
  Alexander technical); waiting for his calculation material.
- README: team roles, investor meeting in the status list.
2026-10-09 12:14:59 +07:00
grabowski 21419145f8 Replies sent to Sibert (Ian Locke) and OMS (Lou Wullms)
OMS confirmation is done; next is the calculation material from Lou
Wullms. Sibert itemised quotation still open.
2026-10-09 12:08:07 +07:00
grabowski 4fec258f15 After Haarlem: Pheenix CEO follow-up, OMS first contact, SST
- Pheenix Alpha (Robert Gunnarsson, 5 Oct; Simona's reply 9 Oct): offers
  a Teams call, reference clients and a factory visit near Stockholm;
  300+ presses (vendor figure); we call once questions are concrete,
  next Europe trip planned for February 2027. CEO contact and Marsta
  address added.
- OMS (Lou Wullms, 7 Oct): first email contact, company data, contacts
  (Lou Wullms technical, Wilma Peeters accounting/logistics); open: reply
  to confirm, then OMS sends material to calculate from.
- SST Frankfurt (Daniel Krieger, 7 Oct): cut the lacquers for POY003,
  005, 006 and 013; on good terms with ResurRec; offered help. New cutting
  service entry in the supplier map and vendor landscape; corrected the
  briefing, which had SST as DMM (its site lists lacquer and dubplates).
- Roadmap items 5, 6 and 14 and the production timeline launch basis
  updated accordingly.
2026-10-09 06:38:52 +02:00
grabowski 6888abe602 Sibert follow-up: USD 250k budget, current VS specs, OMS as galvanics option
Deploy test site / deploy (push) Successful in 41s
Ian Locke's email of 5 October 2026 after Making Vinyl Europe:

- Budget of USD 250k for VSP, VSF and VSC confirmed; his time, spares,
  shipping and travel extra; itemised quotation on request. The
  total-investment block keeps its estimate until the re-base, the
  difference (+190k low case / +80k high case) goes into the
  not-yet-rolled-up table.
- Current specifications filed (VSF and VSC 2022, VSP 2023) plus the
  VSF/VSP/VSC line-up drawing (4958 x 833 mm); the 2021 issues move to
  sibert/specs-2021/. VSC is now 1000 kg with split OD hydraulic / ID
  pneumatic forming; VSF 0-30 psi, 4-station head. Crane table, supplier
  map, vendor landscape and the plant page details updated.
- Fully automatic VSPa exists; Sibert offers to move features to the VSP.
- Electroforming: OMS (Optical Media Services, Lou Wullms) named next to
  Pheenix; added as a third galvanics candidate with open questions.
- Sequencing advice (presses, boilers, operators and live feedback loops
  first) recorded in the exhibitor briefing, roadmap item 23, and as
  digital-factory design decision 9 (operators see the data first).
2026-10-07 09:24:11 +02:00
grabowski b672c58e34 Plant page: mature fleet at real cycle times
Deploy test site / deploy (push) Successful in 34s
Rebuild docs/plant-operation.html from the single P1 press into the mature
plant: Newbilt Duplex (two HRP 12 on a VEX 50, EX 35 for splatter), two
Newbilt Classic automatic presses with edge trimmers, label punch and
Granulator 400; Pheenix Alpha PASU, PPPU, two PDPU and PMPB; Sibert VSF,
VSP and VSC in that order; father and mother archive and the stamper rack.

Time runs at 1x real time with speeds up to 3600x. Press cycles are
Newbilt's (Classic 28 s, Duplex ~30 s), plating follows Faraday's law at
the PDPU current, and the operator steps use the galvanics.md table, with
unpublished times marked as estimates. Titles flow through the three artist
gates in days; test pressings unmount and the presses run approved work
meanwhile; worn stampers and represses come from the archived mothers.
Two shifts, unplanned press stops sized to scale.md's 60 to 70 %
effectiveness, and demos for a steam dip, a new PVC lot and a repress.

The boiler and chiller are shown at 800 kg/h and 500 kW (estimates) and
the detail panels flag that scale.md's 400 kg/h and 250 kW are Duplex
figures; scale.md itself is unchanged.

Also commits the galvanics.md cycle-time table the page runs on (one PDPU
covers demand, the second is redundancy) and updates the README and the
test-site descriptions.
2026-10-03 22:47:57 +02:00
grabowski 81f3279efd Add Pheenix galvanics flyers and Sibert stamper prep specs
Deploy test site / deploy (push) Successful in 45s
docs/equipment/pheenix-alpha/: the four Pheenix Alpha electroforming flyers
(2024: PASU silvering, PPPU pre-plating, PDPU dual-cell plating, PMPB
passivation bench), renamed from their download hashes.
docs/equipment/sibert/: the VSP, VSF and VSC technical specifications
(2021), plus Sibert's 2008-09 optical-disc SPS literature and the 2008
Blu-ray stamper characteristics paper in sps-optical-disc-2009/. Two
byte-identical duplicates in the download were dropped.

New docs/equipment/galvanics.md, the metal-path counterpart to
pressing-line.md: datasheet tables for both ranges and what they change.
Pheenix is a second turnkey galvanics vendor next to Digital Matrix and
can quote lacquer-to-record as one vendor; neither range includes water
treatment. Utilities from the sheets (~27 kVA connected per line, DI water,
12-20 C cooling water, extraction sizes), ~5.6 m2 of footprint, and a cell
count estimate (one PDPU at the low end, two at the high end). The Sibert
machines are single-phase, 200/250/600 kg on castors, centre manually and
list no data interface; the VSC locates on the punched hole; the finisher's
water carries nickel. Weights, cycle times, prices and mould fit are listed
as quote questions.

Backlinks and small updates: README (bullet, layout tree, vendor list),
roadmap items 6 and 23, vendor landscape, supplier map, exhibitor briefing
(on-file notes, Sibert three-phase question answered), digital factory
(Pheenix PLC data, Sibert data question, RFQ clause 5), quality automation
(hardness on the centre slug, BD paper as the acceptance-spec model),
sustainability (finisher water), total investment block label (numbers
unchanged), scale (galvanics feeder note), crane weight table, process
flow, pressing-line stamper-fit question, plant page detail lines.
2026-10-03 21:05:00 +02:00
grabowski 725f0cc9d1 Add the Newbilt flyers from Making Vinyl Europe 2026
Deploy test site / deploy (push) Successful in 35s
docs/equipment/newbilt/flyers-2026/: the six 2026 product flyers
(Classic, Duplex, EX 35, Edge Trimmer, Granulator 400, Label Punch) and
the 2024 Classic print flyer, collected at the booth in Haarlem.

pressing-line.md gets a range table with the flyer figures and what they
change: Classic and Duplex share inserts (one mould family for a
Newbilt-only fleet, Classic now named as automated candidate next to the
Pheenix AD12), edge trim of 20 to 40 g per 12" 180 g record brackets the
~20 % regrind share, the Granulator 400 runs in batches, central
hydraulics is an option, and the EX 35 is not in the 2024 quote.

Sources disagree on the Classic's panel (two 21" vs one 10"), extruder
power (7.5 kW drive in the 2024 flyer vs 15 kW noted earlier) and 10"
support; recorded as re-quote points instead of picking one. Supplier
table and exhibitor briefing corrected to match and given Erwin Neubauer
as a second contact; plant page grinder detail cites the flyer figures.
2026-10-02 21:53:45 +02:00
grabowski 20c8d283d5 Rebase costs on USD/THB; add timelines and first market data
Currency
- Base currency moves from EUR to USD and THB throughout. Rates at
  5 Aug 2026: 1 USD = 33 THB, 1 EUR = 1.155 USD, 1 GBP = 1.35 USD.
  EUR/THB lands at ~38, so existing THB research needed no change.
- Vendor quotes keep their original currency with a USD/THB equivalent
  alongside, so they stay checkable against the source PDFs.
- Full vision ~4.7-8.9M USD; phased entry ~1.7-2.9M USD.

New documents
- production-timeline.md: order turnaround stage by stage. Launch
  8-14 weeks, mature 5-10, repress 2-3. Quantifies the in-house
  galvanics turnaround claim the repo had asserted without a number,
  and flags artwork as an unmodelled fourth approval gate.
- project-timeline.md: calendar to first paying release, ~Q4 2028.
  Critical path is BOI certificate to press order to build to
  commissioning. Two findings: Newbilt build time is absent from the
  repo yet carries ~40% of the schedule, and the BOI rule may be
  over-serialised since duty exemption attaches at importation rather
  than at contract signature.

First market data (ResurRec, Bangkok)
- Invoice-derived prices, a factory tour, and a confirmed fleet of one
  Newbilt Classic 12" automatic plus one semi-automatic.
- Price ladder recorded at 300/500/1000-3000/3000+ units. Decomposes
  to roughly 34-50k THB fixed per title and 535-780 THB variable per
  unit, which is 4-7x the price this model assumes.
- The incumbent presses 230-350k records/yr but buys every stamper as
  an import. That single constraint plausibly explains their 150-unit
  floor, their flat discount ladder and their large-run lead time, and
  it is what an in-house galvanics line attacks. Logged as an open
  question on whether galvanics should move from phase 5 to phase 1.
- Inferences are marked as inferences; the whole set is one buyer and
  one plant, and the model is deliberately left unrebased until a
  second data point exists.

Corrections
- Gross margin arithmetic did not follow from its own inputs. Restated
  as ~1.95 USD at the midpoint with the 0.75-3.15 spread shown; the
  previous "40 to 55%" was not supported.
- Direct cost low total 1.50 to 1.45 USD; contingency THB high 40M
  to 38M.
- README indexes the construction RFQ, which was missing.
2026-08-06 12:22:40 +07:00
grabowski 11b7df3be4 Add end-to-end process flow document and diagram; floor loading criterion
- docs/process-flow.md: mermaid chart plus stage table of every check and
  the three artist approval gates, from audio intake to fulfillment
- docs/process-flow.drawio with PNG and PDF exports
- pressing-line.md: floor must carry multiple tons per m2 in machine areas
- README: process-flow entry in document index and layout tree
2026-07-17 15:48:48 +07:00
grabowski 0a4f47a5cc Split README into topic documents
- README reduced to overview with linked document index
- docs/equipment/pressing-line.md: fleet strategy, Newbilt plan, site reqs
- docs/suppliers/vendor-landscape.md: researched vendor narratives
- docs/sustainability.md: solar, zero-discharge water, materials
- docs/worker-safety.md: training, clean rooms, PPE
- docs/facility-security.md: access control, CCTV, archive/audio protection,
  fire and life safety, plant monitoring, Thai compliance anchors
2026-07-17 12:51:04 +07:00
grabowski 5622ab2821 Initial commit: planning documents
- docs/: Newbilt equipment offer, site requirements, process schematic,
  service rates, project cost overview, PVC supplier list, consultancy overview
- .gitignore excluding local tooling config and runtime state