Added at the user's request (October 2026): LPI Rack Range (Thailand)
Corp., Ltd., Bangkok head office, plants in Bangplee Industrial Estate
and Bangpla (Samut Prakan); office mobile shelving for documents, pallet
racking (selective, drive-in, mobile, shuttle, pallet flow), picking
shelves and mezzanines, mould-and-die racking, mini-load AS/RS; no specs
or prices published (lpi.co.th, checked October 2026).
equipment-suppliers.md section 8 entry; the Thai supplier the archive
shelving is quoted against (facility-security.md open points, supplier
map archive line); racking candidate in the utilities CSV.
New page docs/steam-cooling.html (site /demos/steam-cooling/): the
utility plant as a clickable process diagram. Steam side: raw water,
softener and dosing, feed tank with heat-pump feedwater recovery, feed
pumps, a bank of two 500 kg/h boilers (third for N+1 as an option),
separator and metering, optional accumulator, blowdown, the 10 bar
header with a valved, metered branch and trap per press, drip legs and
condensate return. Cooling side: Newbilt's press outlets are open (max.
2 bar), so returns drain to a warm tank, pass the heat pump, an optional
dry cooler and a plate heat exchanger to a cold buffer tank, and VFD
pumps feed the 20 to 25 C header at ~10 bar to every press, the
extruders and the central hydraulic oil cooler; the chiller loop
(three 250 kW air-cooled modules at 40 C ambient, fourth as option) stays
closed and clean. Galvanics cooling (12 to 20 C) is a separate circuit.
Operating cases (launch, Duplex system 1, five presses, one module down)
show demand against installed capacity; design basis with sources,
equipment schedule, RFQ questions. Static SVG, no per-frame work.
Design basis at Newbilt's per-machine figures: steam 750 to 900 kg/h,
cooling 652.5 kW (625 presses, 15 extruders, 12.5 hydraulics), 305 to
540 l/min circulating. Also found: Newbilt's 53 l/min at ~60 C out is
~140 kW, above its 125 kW peak; listed as a re-quote question.
Re-based in the same commit:
- scale.md: electrical table (chiller bank ~210 to 325 kW electrical,
plant peak ~430 to 700 kW, ~950 to 1,330 kW with electric steam),
grid 800 to 1,000 kVA (1,250 to 1,600 with electric steam, Schedule
4 past 1,000 kW), tariff 4.5M to 6.8M THB/yr, battery ~1 h of chiller
peak, boiler and chiller banks, biomass up to ~550 t/yr at 1.5 M
records, utilities money line.
- sustainability.md, biomass.md: same figures; electric steam 5.2M to
6.0M THB/yr mature, 1.6M to 1.8M early; fuel saving 4.0M to 5.4M.
- utilities CSV: boiler bank, chiller bank with HX and tanks, softener
and loop treatment re-sized; baseline 23.98M-41.63M -> 30.07M-51.33M.
- total-investment.md: re-size as an added-scope row (+185k / +294k
USD); headline 4.7M to 8.9M unchanged until the investment re-base.
- pressing-line, equipment-suppliers, facility-security, fleet
calculator (boiler 1000 kg/h, chiller 750 kW), plant page detail
texts; README, landing page, build.sh.
PEA tariff schedule (May 2023 onward, still current) filed under
docs/finance/pea/; Ft 0.1623 THB/kWh for Sep-Dec 2026 from the PEA Ft page.
The plant falls under Schedule 3.2.2 (Medium General Service, TOU, 22 kV).
New section in sustainability.md: blended ~3.81 THB/kWh for two-shift
production plus 132.93 THB/kW demand charge; electric steam ~4.7M-5.5M
THB/yr at maturity against ~0.35M-0.8M of biomass fuel; self-consumed PV
worth ~3.7 THB/kWh (~4.5-7 yr payback); solar thermal not recommended;
the battery earns little from TOU arbitrage or peak shaving. biomass.md,
scale.md, the utilities CSV note and the README follow.
Steam, compressed air, cooling, water treatment, racking, HVAC, solar EPC
and BESS; baseline total 23.98M-41.63M THB, options priced separately;
all figures budgetary +/- 30%, basis marked per row