Plan the overhead crane, maintenance workshop and visitor corridor

New docs/crane-workshop-tours.md: a 5 t single-girder EOT crane over the
whole production compartment (stops at the warehouse fire wall), a
machine door and crane-served workshop/machine bay at the ramp end, and
a glazed ground-level visitor corridor along the car-park elevation with
stations in process order, its own air and acoustic glazing so tours
need no PPE. Covers what each changes in the shell (crane-ready frame,
hook height under the 7.0 m eave, no full-height cross walls in the
crane zone, room lids and crane hatches), safety, costs and open
decisions.

Propagated: construction RFQ (crane-ready frame, new section 1c, machine
door, accessible 1:12 entrance now required), scale zone table (+210 to
280 m2, total ~1,400 to 2,000 m2), facility security, worker safety,
roadmap items 9 and 15, total investment added-scope table, README.
This commit is contained in:
grabowski committed 2026-10-02 17:34:24 +02:00
1 parent 81185d8013
commit 917a3eb933
8 files changed
+491 -11

No files matched your search

+12 -1
View File
@@ -54,13 +54,24 @@ running the same machine.
| Packaging + finished goods warehouse | ~300 to 500 m² |
| Utility rooms (boiler, compressor, chiller, electrical) | ~100 to 150 m² |
| Offices, QC/listening, archive, IT, entrance | ~150 to 200 m² |
| Maintenance workshop and machine bay (crane-served) | ~100 to 150 m² |
| Visitor corridor (glazed, ground level) | ~110 to 130 m² |
| Circulation, walls, misc | ~150 to 250 m² |
| **Total under roof** | **~1,200 to 1,700 m²** |
| **Total under roof** | **~1,400 to 2,000 m²** |
The HVAC budget in the utilities CSV already assumes ~1,500 m² conditioned.
Single story throughout: all heavy equipment needs ground-slab floor
loading (multiple tons per m²).
The workshop and the visitor corridor were added in October 2026, together
with an overhead crane over the production compartment; what they need and
what they change in the shell is in
[crane, workshop and tours](crane-workshop-tours.md). They add ~210 to
280 m² to a program that already filled the 60 × 25 m footprint, which
settles the open question below in favour of growing the program into the
floor the utility yard frees: at the lower half of the table everything
fits; at the upper half, finished goods move to the phase 2 building.
### Detached utility yard, parking, and what that moves
The massing model puts the boiler and chiller in a **detached utility yard**