Plan the overhead crane, maintenance workshop and visitor corridor
New docs/crane-workshop-tours.md: a 5 t single-girder EOT crane over the whole production compartment (stops at the warehouse fire wall), a machine door and crane-served workshop/machine bay at the ramp end, and a glazed ground-level visitor corridor along the car-park elevation with stations in process order, its own air and acoustic glazing so tours need no PPE. Covers what each changes in the shell (crane-ready frame, hook height under the 7.0 m eave, no full-height cross walls in the crane zone, room lids and crane hatches), safety, costs and open decisions. Propagated: construction RFQ (crane-ready frame, new section 1c, machine door, accessible 1:12 entrance now required), scale zone table (+210 to 280 m2, total ~1,400 to 2,000 m2), facility security, worker safety, roadmap items 9 and 15, total investment added-scope table, README.
This commit is contained in:
1 parent
81185d8013
commit
917a3eb933
8 files changed
+491
-11
No files matched your search
+9
-3
@@ -50,8 +50,10 @@ These three run in parallel and gate everything downstream:
|
||||
9. **Site selection**: candidate buildings/plots in Lamphun and Lampang
|
||||
(Northern Region Industrial Estate first for its shared effluent
|
||||
treatment and licensing simplicity), screened against the
|
||||
[scale requirements](scale.md): 6 to 8 rai, 1,200 to 1,700 m² single
|
||||
story, multiple tons per m² slab, 500 to 1,000 kVA connection
|
||||
[scale requirements](scale.md): 6 to 8 rai, 1,400 to 2,000 m² single
|
||||
story (including the workshop and visitor corridor), multiple tons per
|
||||
m² slab, 500 to 1,000 kVA connection, and a frame able to carry an
|
||||
overhead crane
|
||||
|
||||
## Phase 2: Commit (after BOI certificate and validated pricing)
|
||||
|
||||
@@ -71,7 +73,11 @@ These three run in parallel and gate everything downstream:
|
||||
|
||||
15. Building fit-out: slab verification, HVAC, clean zones, utilities,
|
||||
solar and BESS installation, security systems per
|
||||
[facility-security.md](facility-security.md)
|
||||
[facility-security.md](facility-security.md), and the overhead crane,
|
||||
maintenance workshop and visitor corridor per
|
||||
[crane-workshop-tours.md](crane-workshop-tours.md) (the crane-ready
|
||||
frame itself is in the construction RFQ, so it is decided before the
|
||||
shell is ordered)
|
||||
16. Machinery installation and vendor commissioning (Newbilt on-site
|
||||
commissioning is mandatory for warranty; budget per the service rate
|
||||
card)
|
||||
|
||||