Plan the overhead crane, maintenance workshop and visitor corridor
New docs/crane-workshop-tours.md: a 5 t single-girder EOT crane over the whole production compartment (stops at the warehouse fire wall), a machine door and crane-served workshop/machine bay at the ramp end, and a glazed ground-level visitor corridor along the car-park elevation with stations in process order, its own air and acoustic glazing so tours need no PPE. Covers what each changes in the shell (crane-ready frame, hook height under the 7.0 m eave, no full-height cross walls in the crane zone, room lids and crane hatches), safety, costs and open decisions. Propagated: construction RFQ (crane-ready frame, new section 1c, machine door, accessible 1:12 entrance now required), scale zone table (+210 to 280 m2, total ~1,400 to 2,000 m2), facility security, worker safety, roadmap items 9 and 15, total investment added-scope table, README.
This commit is contained in:
1 parent
81185d8013
commit
917a3eb933
8 files changed
+491
-11
No files matched your search
@@ -33,6 +33,19 @@ July 2026; the underlying THB estimates are unchanged, because EUR/THB at
|
||||
| Contingency 15% | ~0.6M – 1.2M | ~20M – 38M | |
|
||||
| **Total, full vision** | **~4.7M – 8.9M USD** | **~155M – 294M THB** | |
|
||||
|
||||
### Added scope, not yet in the roll-up
|
||||
|
||||
Decided after the roll-up above was compiled; carried here as estimates
|
||||
until the next re-base folds them into the blocks (the building and
|
||||
software lines, and the contingency on top).
|
||||
|
||||
| Block | USD | THB | Basis |
|
||||
|---|---|---|---|
|
||||
| Overhead crane, runway, frame premium, machine door | 97k – 227k | 3.2M – 7.5M | estimate, [crane, workshop and tours](../crane-workshop-tours.md) |
|
||||
| Maintenance workshop and machine bay fit-out | 30k – 76k | 1.0M – 2.5M | estimate, same |
|
||||
| Visitor corridor and accessible entrance | 67k – 148k | 2.2M – 4.9M | estimate, same |
|
||||
| **Added so far** | **~195k – 450k** | **~6.4M – 14.9M** | about 5 to 6% on the full-vision subtotal |
|
||||
|
||||
## Phased entry
|
||||
|
||||
A credible launch phase is far smaller, roughly **1.7M to 2.9M USD
|
||||
|
||||