Payap model: Duplex cells at Newbilt sizes; fire water per facility-security

User, October 2026: the Duplex sketch is not to scale, check it against
the documents; the fire water tank is too small.

Model (changed live in the open FreeCAD 26.3 document):
- both Duplex cells rebuilt in the sketched arrangement at the documented
  sizes: presses 0.95 m square (0.9 m2) turned 45 deg, EX 50 0.5 x 1.0 m
  (0.5 m2), EX 35 0.4 x 0.8 m and trimmer 0.6 x 0.6 m (estimates),
  operator position marked; 0.6 to 0.8 m between machines;
- fire water: the ~25 m3 yard tank replaced by the facility-security
  planning tank, 9 m x 4 m (254 m3 gross, ~200 m3 usable), new params
  fw_dia, fw_h, fw_x, fw_y, at the front by the access road, outside the
  production yard, on a ring foundation, with a pump house (duty electric,
  standby diesel, jockey); the yard process water tank is now the 5 x 3 m
  raw water tank of the phase 1 RFQ.

Docs: site-candidates (cell, raw water, fire water bullet),
facility-security (the Payap model draws the tank; 6 m racking and twice
the floor area make ~200 m3 a floor there).
This commit is contained in:
grabowski committed 2026-10-10 17:43:09 +07:00
1 parent 7da64088ce
commit 90697c8cac
5 files changed
+18 -3

No files matched your search

+6 -1
View File
@@ -136,7 +136,12 @@ sprinkler demand, so the site carries its own reserve and pumps.
**Warehouse racking height drives the real number.** If finished-goods
storage goes above roughly 3.7 m, the commodity classification and sprinkler
design change, and the stored volume grows with them. Fix the racking height
before the fire design is frozen, not after.
before the fire design is frozen, not after. The
[Payap scenario model](site-candidates.md#payap-scenario-model-october-2026)
draws the 9 m × 4 m tank with its pump house at the front. It also draws
6 m warehouse racking and about twice the floor area this figure was
based on, a paper store among it, so treat ~200 m³ as a floor there,
not as the answer.
The property insurer will drive much of the final specification, so involve
them before the design is fixed. The archive gas system and the BESS