@@ -198,9 +198,10 @@ item that is not on the critical path does not move the end date. Leasing
only advances the launch if the **press order** also moves forward, which
is the BOI question above; the two are one lever, not two. The cost is a
building that probably compromises on the two hardest requirements (floor
loading and power) and may block the Phase 5 galvanics line entirely. Locating in the Northern Region
Industrial Estate, which [boi.md](boi.md) already favours for its shared
central effluent treatment, is the version of leasing that keeps the
loading and power) and may block the Phase 5 galvanics line entirely.
Locating in the Northern Region Industrial Estate, which
[boi.md](boi.md) already favours for its shared central effluent
treatment, is the version of leasing that keeps the
galvanics option alive.
**This is an unresolved fork, not a decision I can make.** It is worth