diff --git a/docs/project-timeline.md b/docs/project-timeline.md index dac9c1c..ea14d03 100644 --- a/docs/project-timeline.md +++ b/docs/project-timeline.md @@ -198,9 +198,10 @@ item that is not on the critical path does not move the end date. Leasing only advances the launch if the **press order** also moves forward, which is the BOI question above; the two are one lever, not two. The cost is a building that probably compromises on the two hardest requirements (floor -loading and power) and may block the Phase 5 galvanics line entirely. Locating in the Northern Region -Industrial Estate, which [boi.md](boi.md) already favours for its shared -central effluent treatment, is the version of leasing that keeps the +loading and power) and may block the Phase 5 galvanics line entirely. +Locating in the Northern Region Industrial Estate, which +[boi.md](boi.md) already favours for its shared central effluent +treatment, is the version of leasing that keeps the galvanics option alive. **This is an unresolved fork, not a decision I can make.** It is worth