Checked October 2026 on the investor's budget question. New docs/suppliers/china-utilities.md: boiler makers (ZOZEN, Sitong, Fangkuai, Taiguo, Yuanda, Yongxing, Taishan, Nobeth) with fit for 500 kg/h at 1.25 MPa, claimed certificates, Thai references and listing prices; the Thai rules for an imported boiler (MR and MOI notification B.E. 2549: ASME/JIS/EN or equivalent, certification-body verification, once-through relief does not reach 10.5 bar, licensed controller, annual inspection); compressor makers with Thai offices (Kaishan, Denair) and sizing; hydraulic pump sets and accumulators (Huade, Yuci, Hengli, WMD, Renowell, Inovance, NXQ makers), the shared-ring-main risks and Thai HPU builders; duty and freight; open RFQs. Result: about 2M THB at the midpoint (~2.5M with contingency), ~1 % of the 216M target, mostly the boilers; Newbilt aggregates stay Newbilt's. total-investment notes it and lists the uncosted central hydraulic plant; utilities CSV gets the Chinese candidates and route estimates; backlinks from equipment-suppliers, pressing-line, README.
This commit is contained in:
1 parent
553b4a93d1
commit
7344f12dc8
6 files changed
+279
-7
No files matched your search
@@ -67,8 +67,11 @@ on two shifts (estimate: the [scale](../scale.md) basis gives ~0.71 to
|
||||
|
||||
Not in the total: a **reserve for the ramp-up** (staff hired before first
|
||||
revenue, overheads until volume covers them; ~10M to 20M THB, estimate),
|
||||
CD replication, financing costs, currency moves, and the archive's mobile
|
||||
shelving (to quote). The blocks are vendor prices without Thai duty or
|
||||
CD replication, financing costs, currency moves, the archive's mobile
|
||||
shelving (to quote), and the central hydraulic plant around the Newbilt
|
||||
aggregates: standby pump set, accumulator station and ring main (not
|
||||
costed yet; a Thai HPU builder quotes it,
|
||||
[Chinese suppliers](../suppliers/china-utilities.md#hydraulics)). The blocks are vendor prices without Thai duty or
|
||||
import VAT, so they assume BOI promotion: without it, ~5 % duty on ~2.3M
|
||||
USD of imported machinery (~0.11M USD) comes on top, plus ~0.17M USD of
|
||||
import VAT paid at the border and reclaimed later (estimates).
|
||||
@@ -104,6 +107,17 @@ installations while the frame stays crane-ready (~3.7M THB) give ~185M
|
||||
before the reserve, still above 180M, so 180M is a low-quote outcome, not
|
||||
a plan.
|
||||
|
||||
Chinese suppliers for the boilers, compressed air and hydraulics were
|
||||
checked in October 2026
|
||||
([Chinese suppliers](../suppliers/china-utilities.md)): about 2M THB at
|
||||
the midpoint, ~2.5M with its share of the contingency, mostly on the two
|
||||
boiler modules (ASME-stamped 1.25 MPa units from makers with Thai
|
||||
references, installed by a Thai contractor) and a little on the
|
||||
compressor (a Chinese brand bought through its Thai office). That is
|
||||
about 1 % of the target and does not change the answer; the Newbilt
|
||||
hydraulic aggregates stay Newbilt's. Chinese chillers and HVAC, larger
|
||||
blocks, are not checked yet.
|
||||
|
||||
What decides it: the two largest machine lines have no price at all (the
|
||||
Classic and the Pheenix galvanics line), and the building depends on the
|
||||
soil. Four requests settle most of the band: the Newbilt re-quote for the
|
||||
|
||||