Chinese suppliers for boilers, compressed air and hydraulics

Checked October 2026 on the investor's budget question. New
docs/suppliers/china-utilities.md: boiler makers (ZOZEN, Sitong,
Fangkuai, Taiguo, Yuanda, Yongxing, Taishan, Nobeth) with fit for 500
kg/h at 1.25 MPa, claimed certificates, Thai references and listing
prices; the Thai rules for an imported boiler (MR and MOI notification
B.E. 2549: ASME/JIS/EN or equivalent, certification-body verification,
once-through relief does not reach 10.5 bar, licensed controller, annual
inspection); compressor makers with Thai offices (Kaishan, Denair) and
sizing; hydraulic pump sets and accumulators (Huade, Yuci, Hengli, WMD,
Renowell, Inovance, NXQ makers), the shared-ring-main risks and Thai HPU
builders; duty and freight; open RFQs.

Result: about 2M THB at the midpoint (~2.5M with contingency), ~1 % of
the 216M target, mostly the boilers; Newbilt aggregates stay Newbilt's.
total-investment notes it and lists the uncosted central hydraulic
plant; utilities CSV gets the Chinese candidates and route estimates;
backlinks from equipment-suppliers, pressing-line, README.
This commit is contained in:
grabowski committed 2026-10-16 15:21:38 +07:00
1 parent 553b4a93d1
commit 7344f12dc8
6 files changed
+279 -7

No files matched your search

+16 -2
View File
@@ -67,8 +67,11 @@ on two shifts (estimate: the [scale](../scale.md) basis gives ~0.71 to
Not in the total: a **reserve for the ramp-up** (staff hired before first
revenue, overheads until volume covers them; ~10M to 20M THB, estimate),
CD replication, financing costs, currency moves, and the archive's mobile
shelving (to quote). The blocks are vendor prices without Thai duty or
CD replication, financing costs, currency moves, the archive's mobile
shelving (to quote), and the central hydraulic plant around the Newbilt
aggregates: standby pump set, accumulator station and ring main (not
costed yet; a Thai HPU builder quotes it,
[Chinese suppliers](../suppliers/china-utilities.md#hydraulics)). The blocks are vendor prices without Thai duty or
import VAT, so they assume BOI promotion: without it, ~5 % duty on ~2.3M
USD of imported machinery (~0.11M USD) comes on top, plus ~0.17M USD of
import VAT paid at the border and reclaimed later (estimates).
@@ -104,6 +107,17 @@ installations while the frame stays crane-ready (~3.7M THB) give ~185M
before the reserve, still above 180M, so 180M is a low-quote outcome, not
a plan.
Chinese suppliers for the boilers, compressed air and hydraulics were
checked in October 2026
([Chinese suppliers](../suppliers/china-utilities.md)): about 2M THB at
the midpoint, ~2.5M with its share of the contingency, mostly on the two
boiler modules (ASME-stamped 1.25 MPa units from makers with Thai
references, installed by a Thai contractor) and a little on the
compressor (a Chinese brand bought through its Thai office). That is
about 1 % of the target and does not change the answer; the Newbilt
hydraulic aggregates stay Newbilt's. Chinese chillers and HVAC, larger
blocks, are not checked yet.
What decides it: the two largest machine lines have no price at all (the
Classic and the Pheenix galvanics line), and the building depends on the
soil. Four requests settle most of the band: the Newbilt re-quote for the
+2 -2
View File
@@ -1,8 +1,8 @@
category,item,spec_summary,candidate_thai_suppliers,cost_low_thb,cost_high_thb,cost_basis,notes
steam,Electric/gas once-through boiler bank,"2 x 500 kg/h modules at 10.5 bar / 180 C, lead/lag, shared feed tank, feed pumps, economizer, installed",Miura Thailand (Chachoengsao); Bangkok Industrial Boilers; STE Thailand,4500000,7000000,engineering estimate,"Launch plant (October 2026): one Duplex system and one Classic, 450-540 kg/h at Newbilt's 150-180 kg/h per press, so B-1 and B-2 both at launch; the boiler hall is built for four modules (scale.md utility phasing); a third module for N+1 is an RFQ option; Miura-class modular once-through; service is Bangkok-centric, confirm northern dispatch SLA"
steam,Electric/gas once-through boiler bank,"2 x 500 kg/h modules at 10.5 bar / 180 C, lead/lag, shared feed tank, feed pumps, economizer, installed","Miura Thailand (Chachoengsao); Bangkok Industrial Boilers; STE Thailand; Chinese route (October 2026): ZOZEN, Sitong, Fangkuai, Taiguo (ASME claimed, Thai references, no Thai service partner), see suppliers/china-utilities.md",4500000,7000000,engineering estimate,"Launch plant (October 2026): one Duplex system and one Classic, 450-540 kg/h at Newbilt's 150-180 kg/h per press, so B-1 and B-2 both at launch; the boiler hall is built for four modules (scale.md utility phasing); a third module for N+1 is an RFQ option; Miura-class modular once-through; service is Bangkok-centric, confirm northern dispatch SLA; Chinese route estimate 2.8M-5.5M THB installed (two ASME-stamped 1.25 MPa bodies USD 15k-35k each, inspection and certification, freight, Thai contractor balance of plant), about 1.6M THB less at the midpoint; imported boilers need DIW certification-body verification either way"
steam,Biomass/wood-fired boiler package (option),"~1 t/h solid fuel (wood chips/pellets/rice husk) incl. fuel feed, grate, dust control, softener, installed",Getabec PCL (Thai fabrication and service),6000000,10000000,engineering estimate,"Sized for the five-press fleet (was ~0.5 t/h for one Duplex); sustainability path matching Deepgrooves NL precedent; higher capex, lower fuel opex in the North; NOT included in baseline total"
steam,Steam balance of plant,"Traps, accumulator, condensate return",Forbes Marshall Thailand,0,0,included,Largely included in boiler package rows; line kept for RFQ completeness
compressed_air,Screw compressor skid (oil-injected),"~7.5 kW VSD screw + refrigerated dryer (3 C PDP) + coalescing filters + ~500 L receiver, installed",Atlas Copco Thailand; Kaeser Thailand (SM-T/Aircenter); Ingersoll Rand Thailand,350000,600000,engineering estimate,14-30 m3/h demand is small (5-10 hp class); oil-injected + filter train meets 5 micron / 3 C spec
compressed_air,Screw compressor skid (oil-injected),"~7.5 kW VSD screw + refrigerated dryer (3 C PDP) + coalescing filters + ~500 L receiver, installed","Atlas Copco Thailand; Kaeser Thailand (SM-T/Aircenter); Ingersoll Rand Thailand; Chinese brands with Thai offices (October 2026): Kaishan Compressor (Thailand), Denair Thailand, see suppliers/china-utilities.md",350000,600000,engineering estimate,"14-30 m3/h demand is small (5-10 hp class); oil-injected + filter train meets 5 micron / 3 C spec; Chinese route estimate 0.15M-0.3M THB installed (PM VSD 11 kW class USD 2k-5k, dryer, receiver, filters, installation)"
compressed_air,True oil-free class-0 (option),Same duty in oil-free class-0,Atlas Copco (ZR/ZT); Kaeser,1200000,1800000,engineering estimate,Only if air contacts product stream; NOT included in baseline total
cooling,Process chiller bank 2 x 250 kW,"2 x ~71 RT air-cooled screw/scroll chillers rated at 40 C ambient (CH-1, CH-2) + primary pumps + plate HX + warm and cold tanks + VFD supply pumps + controls, backbone (HX frame, tanks, pumps, mains) sized for four modules, installed",Trane Thailand; Carrier Thailand; Daikin Applied Thailand; Hitachi Thailand,4900000,7900000,engineering estimate,"Launch plant (October 2026): Duplex system ~261 kW hot-afternoon peak (scale.md) plus the Classic up to ~125 kW (Newbilt per press), ~390 kW against 500 kW installed; was 3 x 250 kW at 6.5-10.5M for five presses, less one module at ~1.6-2.6M THB (estimate); CH-3 and CH-4 come with the growth options; 3 x 350 kW frame pads stay the alternative (steam-cooling.html)"
cooling,Cooling tower + HX loop (alternative),Dry cooler or FRP tower ~650-750 kW reject + plate HX + pumps + tanks + water treatment,"Liang Chi Thailand (tower, large service org); Process Cooling Solutions; Tasaki (integrators)",2000000,3500000,engineering estimate,Cheaper capex but wet-bulb-limited; hybrid tower + trim chiller is the efficiency-optimal design; NOT included in baseline total
1 category item spec_summary candidate_thai_suppliers cost_low_thb cost_high_thb cost_basis notes
2 steam Electric/gas once-through boiler bank 2 x 500 kg/h modules at 10.5 bar / 180 C, lead/lag, shared feed tank, feed pumps, economizer, installed Miura Thailand (Chachoengsao); Bangkok Industrial Boilers; STE Thailand Miura Thailand (Chachoengsao); Bangkok Industrial Boilers; STE Thailand; Chinese route (October 2026): ZOZEN, Sitong, Fangkuai, Taiguo (ASME claimed, Thai references, no Thai service partner), see suppliers/china-utilities.md 4500000 7000000 engineering estimate Launch plant (October 2026): one Duplex system and one Classic, 450-540 kg/h at Newbilt's 150-180 kg/h per press, so B-1 and B-2 both at launch; the boiler hall is built for four modules (scale.md utility phasing); a third module for N+1 is an RFQ option; Miura-class modular once-through; service is Bangkok-centric, confirm northern dispatch SLA Launch plant (October 2026): one Duplex system and one Classic, 450-540 kg/h at Newbilt's 150-180 kg/h per press, so B-1 and B-2 both at launch; the boiler hall is built for four modules (scale.md utility phasing); a third module for N+1 is an RFQ option; Miura-class modular once-through; service is Bangkok-centric, confirm northern dispatch SLA; Chinese route estimate 2.8M-5.5M THB installed (two ASME-stamped 1.25 MPa bodies USD 15k-35k each, inspection and certification, freight, Thai contractor balance of plant), about 1.6M THB less at the midpoint; imported boilers need DIW certification-body verification either way
3 steam Biomass/wood-fired boiler package (option) ~1 t/h solid fuel (wood chips/pellets/rice husk) incl. fuel feed, grate, dust control, softener, installed Getabec PCL (Thai fabrication and service) 6000000 10000000 engineering estimate Sized for the five-press fleet (was ~0.5 t/h for one Duplex); sustainability path matching Deepgrooves NL precedent; higher capex, lower fuel opex in the North; NOT included in baseline total
4 steam Steam balance of plant Traps, accumulator, condensate return Forbes Marshall Thailand 0 0 included Largely included in boiler package rows; line kept for RFQ completeness
5 compressed_air Screw compressor skid (oil-injected) ~7.5 kW VSD screw + refrigerated dryer (3 C PDP) + coalescing filters + ~500 L receiver, installed Atlas Copco Thailand; Kaeser Thailand (SM-T/Aircenter); Ingersoll Rand Thailand Atlas Copco Thailand; Kaeser Thailand (SM-T/Aircenter); Ingersoll Rand Thailand; Chinese brands with Thai offices (October 2026): Kaishan Compressor (Thailand), Denair Thailand, see suppliers/china-utilities.md 350000 600000 engineering estimate 14-30 m3/h demand is small (5-10 hp class); oil-injected + filter train meets 5 micron / 3 C spec 14-30 m3/h demand is small (5-10 hp class); oil-injected + filter train meets 5 micron / 3 C spec; Chinese route estimate 0.15M-0.3M THB installed (PM VSD 11 kW class USD 2k-5k, dryer, receiver, filters, installation)
6 compressed_air True oil-free class-0 (option) Same duty in oil-free class-0 Atlas Copco (ZR/ZT); Kaeser 1200000 1800000 engineering estimate Only if air contacts product stream; NOT included in baseline total
7 cooling Process chiller bank 2 x 250 kW 2 x ~71 RT air-cooled screw/scroll chillers rated at 40 C ambient (CH-1, CH-2) + primary pumps + plate HX + warm and cold tanks + VFD supply pumps + controls, backbone (HX frame, tanks, pumps, mains) sized for four modules, installed Trane Thailand; Carrier Thailand; Daikin Applied Thailand; Hitachi Thailand 4900000 7900000 engineering estimate Launch plant (October 2026): Duplex system ~261 kW hot-afternoon peak (scale.md) plus the Classic up to ~125 kW (Newbilt per press), ~390 kW against 500 kW installed; was 3 x 250 kW at 6.5-10.5M for five presses, less one module at ~1.6-2.6M THB (estimate); CH-3 and CH-4 come with the growth options; 3 x 350 kW frame pads stay the alternative (steam-cooling.html)
8 cooling Cooling tower + HX loop (alternative) Dry cooler or FRP tower ~650-750 kW reject + plate HX + pumps + tanks + water treatment Liang Chi Thailand (tower, large service org); Process Cooling Solutions; Tasaki (integrators) 2000000 3500000 engineering estimate Cheaper capex but wet-bulb-limited; hybrid tower + trim chiller is the efficiency-optimal design; NOT included in baseline total