Add Payap University land as a site candidate

Payap University (Chiang Mai) is interested in leasing land to the
project; a pharmaceutical facility is under construction on the same land.

New docs/site-candidates.md puts the three options side by side (Mueang
Chi lease, Northern Region Industrial Estate, Payap) with the public facts
on Payap (Mae Khao campus on the Chiang Mai-Lampang superhighway, bought
as low-lying land, ~275 acres; Faculty of Pharmacy cosmetics production
facility tendered July 2024; RPAH cannabis/herbal bioreactor centre), why
it is attractive (5 km from the old city, a university partner with music,
pharmacy and labs, production already being built there) and the checks
that could rule it out, in order: zoning for pressing, boiler and later
electroplating; whether the university can lease to a company; the GMP
neighbour's sensitivity to our emissions (argues against biomass steam
there); flooding; plot fit; galvanics consent. Questions for the next
meeting listed. Nothing re-sited: model, RFQ and site code stay on
Mueang Chi until a plot is known.

README (intro, bullet, layout), roadmap item 9 and the lease fork in
project-timeline link to it.
This commit is contained in:
grabowski committed 2026-10-03 21:31:25 +02:00
1 parent 81f3279efd
commit 31d89faf03
4 files changed
+121 -5

No files matched your search

+10 -4
View File
@@ -1,10 +1,11 @@
# CNX Vinyl / Poy Records # CNX Vinyl / Poy Records
A vinyl record factory in planning for the Chiang Mai area of northern A vinyl record factory in planning for the Chiang Mai area of northern
Thailand (site candidates include Lamphun and Lampang provinces). This Thailand (site candidates include Lamphun and Lampang provinces and, since
repository is the source of truth for the project: planning documents and October 2026, Payap University land in Chiang Mai). This repository is
cost data today. As the factory takes shape it will also hold the data and the source of truth for the project: planning documents and cost data
software used to run it. today. As the factory takes shape it will also hold the data and software
used to run it.
## Team ## Team
@@ -139,6 +140,10 @@ The detail lives in dedicated documents:
- [Project timeline](docs/project-timeline.md): the calendar from today to - [Project timeline](docs/project-timeline.md): the calendar from today to
first paying release, the BOI-to-machinery critical path, and where the first paying release, the BOI-to-machinery critical path, and where the
float actually sits float actually sits
- [Site candidates](docs/site-candidates.md): the land options side by
side (the Mueang Chi lease, the Northern Region Industrial Estate, and
Payap University's offer of land next to a pharmaceutical facility under
construction) and what has to be checked before any of them is chosen
- [Project scale](docs/scale.md): rough numbers for everything on one page: - [Project scale](docs/scale.md): rough numbers for everything on one page:
output capacity, building area, land, electrical demand, solar and output capacity, building area, land, electrical demand, solar and
storage, steam and fuel, headcount, and money cross-references storage, steam and fuel, headcount, and money cross-references
@@ -191,6 +196,7 @@ docs/
├── quality-automation.md Stamper metrology and layered record QC ├── quality-automation.md Stamper metrology and layered record QC
├── roadmap.md Next steps in dependency order ├── roadmap.md Next steps in dependency order
├── scale.md Rough project sizing on one page ├── scale.md Rough project sizing on one page
├── site-candidates.md Land options and the checks before choosing
├── sustainability.md Energy, water, materials commitments ├── sustainability.md Energy, water, materials commitments
├── traceability.md Process logging and per-order traceability ├── traceability.md Process logging and per-order traceability
└── worker-safety.md Training, clean rooms, PPE └── worker-safety.md Training, clean rooms, PPE
+5
View File
@@ -208,6 +208,11 @@ galvanics option alive.
resolving before more design effort goes into the parametric model, resolving before more design effort goes into the parametric model,
because the model is only useful on one side of it. because the model is only useful on one side of it.
A further lease option arrived in October 2026: Payap University offers
land in Chiang Mai next to a pharmaceutical facility under construction
([site candidates](site-candidates.md)). Its zoning is as unverified as
Mueang Chi's, so it adds a candidate without moving the critical path.
## The investor's CD and cassette request ## The investor's CD and cassette request
Adding CD and cassette to the plant has been raised by the main Adding CD and cassette to the plant has been raised by the main
+3 -1
View File
@@ -57,7 +57,9 @@ These three run in parallel and gate everything downstream:
confirm the EPC (Solar Nicolo or other) warrants a mixed-vendor DC bus confirm the EPC (Solar Nicolo or other) warrants a mixed-vendor DC bus
9. **Site selection**: candidate buildings/plots in Lamphun and Lampang 9. **Site selection**: candidate buildings/plots in Lamphun and Lampang
(Northern Region Industrial Estate first for its shared effluent (Northern Region Industrial Estate first for its shared effluent
treatment and licensing simplicity), screened against the treatment and licensing simplicity) and, since October 2026, Payap
University land in Chiang Mai ([site candidates](site-candidates.md)),
screened against the
[scale requirements](scale.md): 6 to 8 rai, 1,400 to 2,000 m² single [scale requirements](scale.md): 6 to 8 rai, 1,400 to 2,000 m² single
story (including the workshop and visitor corridor), multiple tons per story (including the workshop and visitor corridor), multiple tons per
m² slab, 500 to 1,000 kVA connection, and a frame able to carry an m² slab, 500 to 1,000 kVA connection, and a frame able to carry an
+103
View File
@@ -0,0 +1,103 @@
# Site Candidates
The site strategy is a long lease of raw land on which the purpose-built
plant is constructed (business plan section 6.1, built from
`business-plan/build/`). What any site has to offer is unchanged: ~4 rai
minimum and 6 to 8 rai with expansion, truck access and turning, room for
the cooling tower and a separated battery enclosure, a 500 to 1,000 kVA
medium-voltage connection, a slab rated 3 t/m² and a frame able to carry
the overhead crane ([scale](scale.md),
[crane, workshop and tours](crane-workshop-tours.md)), factory permission
for pressing with a steam boiler, and, for Phase 5, permission for an
electroplating line ([galvanics and stamper prep](equipment/galvanics.md)).
## The three candidates
| | Mueang Chi, Lamphun | Northern Region Industrial Estate, Lamphun | Payap University land, Chiang Mai |
|---|---|---|---|
| Status | Working candidate: the massing model, PV roof design and [construction RFQ](finance/phase1-construction-rfq.md) are sited here | Fallback | New lead (October 2026): the university approached the project and is interested in leasing land to us |
| Lessor | Private owner | IEAT | Payap University (private, non-profit, founded by the Foundation of the Church of Christ in Thailand) |
| Plot | 5-0-66.5 rai, 18.4708 N, 98.9642 E, narrow and skewed | Leased estate plots | Not yet identified. The main (Mae Khao) campus is at 18.795 N, 99.033 E |
| Distance to Chiang Mai old city | ~35 km | Lamphun valley | ~5 km east, on the Chiang Mai–Lampang superhighway |
| Zoning for factory use | Unverified (agricultural land) | Industrial estate; licensing through the estate | Unverified |
| Galvanics effluent | Ours to permit; zero discharge | Shared central effluent treatment | Needs the lessor's consent on top of the permit |
| Neighbours | Agricultural | Industrial | A pharmaceutical facility under construction on the same land |
## Payap University (new lead, October 2026)
**What we know from the conversation:** Payap University is interested in
leasing land to the project, and a pharmaceutical facility is under
construction on the same land. The plot, its size, the title, the term and
the rent are not known yet.
**Public facts.** Payap's main campus, Mae Khao, is at 272 Moo 2, San
Phranet, San Sai district, on the Chiang Mai–Lampang superhighway. The
university bought it in 1974 as about 120 acres of low-lying land and has
since grown it to about 275 acres (~700 rai) with purchases across the ring
road (Payap's own history page). Its Faculty of Pharmacy put the
construction of a cosmetics production facility and co-working space out to
tender in July 2024, and the university has announced a centre for
producing active compounds from cannabis and medicinal plants by bioreactor
(RPAH) with an industry sponsor. Whether either of these is the
pharmaceutical facility on the offered land is to be confirmed.
**Why it is worth pursuing.**
- **Location.** About 5 km from the old city and 25 to 30 km nearer the
team, customers and the airport than Mueang Chi. The
[visitor corridor](crane-workshop-tours.md), the
[artist platform](artist-platform.md) and hiring all work better in town.
- **A partner, not only a landlord.** Payap has a College of Music,
communication arts and business faculties (artists, mastering and
cutting trainees, the platform's first users) and a Faculty of Pharmacy
with analytical labs that could back the PVC material lab
([quality automation](quality-automation.md)). A formal university
collaboration is also the kind of R&D and skills cooperation the
[BOI](boi.md) merit measures reward; confirm which measure applies.
- **Production is already being built there.** If the pharmaceutical
facility has factory permission, the land may already have a path
through licensing and a medium-voltage supply nearby. Shared
infrastructure (MV connection, RO water, effluent treatment) is worth
asking about.
**What could rule it out** (check in this order, before any design work):
1. **Zoning.** The plot's colour in the Chiang Mai comprehensive city plan
and whether it allows a record-pressing factory with a steam boiler and,
later, electroplating. A pharmaceutical or cosmetics plant and an
electroplating line are different factory classes, so the neighbour's
permit proves little. Ask the provincial public works and town planning
office, as for Mueang Chi.
2. **Can the university lease to a company?** Title type (Chanote needed),
university council approval, and whether campus land of a private
higher-education institution carries restrictions on commercial leases.
This is a question for Thai counsel, together with the lease terms the
business plan already requires (registered 30-year lease with renewal,
building ownership, mortgageable).
3. **The pharmaceutical neighbour.** A GMP facility is sensitive to dust,
smoke and fumes. Ours: the boiler stack (biomass smoke next to a
pharmaceutical plant in town would be a hard sell, which favours
electric or LPG steam; see [biomass](biomass.md)), galvanics extraction,
PVC extrusion fumes, press noise and truck traffic. Agree emission and
buffer rules in the lease rather than after the first complaint.
4. **Flooding.** Payap describes the Mae Khao land as low-lying when bought.
Check the plot against the 2024 flood extents; the design's floor, 1.2 m
above ground for the loading docks, helps but is not a flood
assessment.
5. **Plot fit.** Shape and size against the 60 × 25 m building, the
detached utility yard and the phase 2 footprint (6 to 8 rai).
6. **Galvanics on a campus.** Phase 5 electroplating needs the lessor's
written consent; the zero-discharge design
([sustainability](sustainability.md)) becomes a lease condition, not
only a commitment.
**Questions for the next meeting with Payap:** which plot (map, size,
title deed number), its zoning and current use; what the pharmaceutical
facility is, who operates it and when it opens; what utilities it brings
(MV, water, wastewater); lease term, rent, renewal and building ownership;
what collaboration the university wants in return.
Nothing has been re-sited. The parametric model, PV roof study, RFQ and
the fleet site code `lpn` in the [digital factory](digital-factory.md)
stay on Mueang Chi until a Payap plot is known and has passed checks 1
and 2.