Files
cnx_vinyl/docs/finance/total-investment.md
T
grabowski f1334f4756 OMS introduction letter and links, Sibert's answer (9 October 2026)
OMS (Lou Wullms) sent its introduction letter, filed in
docs/equipment/oms/: wet-room units with reference prices, two 4-cell
configurations (EUR 224,000 basic with two EFS2-200, EUR 311,000 advanced
with one AEFS4-250 and PLC; installation days extra), capacities of 24
and 32 shells in an 8-hour day, utilities, rooms, staffing, used
equipment, and five contacts for buying a cutting lathe. Recorded in
galvanics.md (tables, our reading: the advanced units add up to EUR
314,000, know-how transfer is left out of both totals although CNX has no
plating know-how, the basic set has no passivation unit), the exhibitor
follow-ups, vendor landscape (new section on used lathes and cutting-room
contacts, plus Lou's three websites), supplier map, roadmap items 6 and
13, total investment (basis note only, block unchanged) and the scale
people estimate. Open: forward the letter to Simona, as Lou asked.

Sibert (Ian Locke, 9 October): footprints and formal quotations when we
are ready; settle the pressing side first, hopefully with Pheenix, and
mention his recommendation if we do; impressed by the green-factory
plans (supplier feedback). Open: pass on the recommendation if Pheenix is
chosen.

CNX-01 in proplan: OMS basic and advanced added as options to D-002 with
their reference prices in THB; budget line 3 notes the OMS range.
2026-10-10 15:52:23 +07:00

6.9 KiB
Raw Blame History

Total Investment: Rough Picture

Everything priced or estimated so far, rolled into one view. Blocks marked "estimate" have no vendor confirmation; the rest trace to quotes or the researched ranges in this repo. Treat all figures as budgetary with a wide margin (plus or minus 30 to 50% on the estimates) until RFQs replace them.

Currency: USD and THB. FX at 5 August 2026: 1 USD = 33 THB. Vendor quotes issued in another currency are kept in that currency wherever they appear next to their source document, and converted here at 1 EUR = 1.155 USD and 1 GBP = 1.35 USD. Original figures compiled July 2026; the underlying THB estimates are unchanged, because EUR/THB at ~38 is where it was when they were made.

Full vision, all blocks

Block USD THB Basis
Newbilt semi-auto line, full Duplex 350k – 370k 11.5M – 12.2M 2024 quote EUR 200,500 (~USD 232k) + quoted 2nd press/extruder ~USD 115k; expired, needs re-quote
2 automated presses (Pheenix AD12) 580k – 920k 19.1M – 30.5M unverified ~USD 340k/press indicative + delivery and commissioning
Galvanics line (Digital Matrix or Pheenix Alpha) 320k – 650k 10.7M – 21.4M six-figure-USD turnkey inference from vendor research; the Pheenix range (2024 flyers, galvanics and stamper prep) is unpriced too; OMS's reference prices (letter, 9 October 2026) put a complete 4-cell wet room at EUR 224k basic to 311k advanced (~USD 259k to 359k; ~270k to 371k with know-how transfer), installation and water treatment extra: at or below this block's low end, kept until quotes exist
Zero-discharge water treatment (ZLD) 90k – 240k 3.0M – 8.0M utilities CSV option row
Stamper prep (Sibert VSP, VSF, VSC) 60k – 170k 1.9M – 5.7M estimate kept until the re-base; Sibert has since confirmed USD 250k for the three (its time, spares, shipping and travel extra), the difference is in the table below
Mastering and cutting room (Agnew or Sillitoe lathe system, cutter amps, console, room treatment) 290k – 580k 9.6M – 19.1M estimate, bespoke market; the Sillitoe SDMS lists at USD 125k for lathe, head, amplifier and automation (ex tax, shipping), which makes the low end reachable; band kept until both quotes exist
Metrology and QC stack (confocal, profiler, XRF, inline vision, audio station) 350k – 810k 11.5M – 26.7M estimate, phaseable
Utilities, solar, HVAC, racking baseline 730k – 1,270k 24.0M – 41.6M reviewed utilities CSV, THB-native
Building ~1,500 m² plus civil works 650k – 1,100k 21.4M – 36.2M estimate at 12,000–20,000 THB/m² Thai industrial construction plus ~20% site works
Land 6–8 rai, if purchased 360k – 970k 12.0M – 32.0M estimate at 2–4M THB/rai industrial; leasing cuts this to near zero upfront
Traceability and factory software 60k – 170k 1.9M – 5.7M estimate
Freight, installation, training (non-Newbilt equipment) 120k – 230k 3.8M – 7.6M estimate
Working capital, PVC stock, spares 120k – 230k 3.8M – 7.6M estimate
Subtotal ~4.1M – 7.7M ~135M – 254M
Contingency 15% ~0.6M – 1.2M ~20M – 38M
Total, full vision ~4.7M – 8.9M USD ~155M – 294M THB

Added scope, not yet in the roll-up

Decided, or re-priced by a vendor, after the roll-up above was compiled; carried here until the next re-base folds them into the blocks (the building, software and stamper prep lines, and the contingency on top).

Block USD THB Basis
Overhead crane, runway, frame premium, machine door 97k – 227k 3.2M – 7.5M estimate, crane, workshop and tours
Maintenance workshop and machine bay fit-out 30k – 76k 1.0M – 2.5M estimate, same
Visitor corridor and accessible entrance 67k – 148k 2.2M – 4.9M estimate, same
Artist platform, public side (calculator, campaigns, payments) 40k – 90k 1.3M – 3.0M estimate, artist platform
PVC material lab, day-one tier (incl. plaque press and sample conditioning) 55k – 150k 1.8M – 5.0M estimate, quality automation; not costed in the metrology block above. The mature tier (torque rheometer, DSC, FTIR, ~120k – 240k) is deferred, with partner labs in between
Stamper prep re-priced: USD 250k for VSP, VSF and VSC against the 60k – 170k block above +190k (low case) / +80k (high case) +6.3M / +2.6M Sibert's budget confirmation, email of 5 October 2026 (galvanics and stamper prep); itemised quotation to follow. Its time, spare parts, shipping and travel are extra and fall into the freight/installation and spares blocks above
Added so far ~480k – 770k ~15.8M – 25.5M about 10 to 12% on the full-vision subtotal

Phased entry

A credible launch phase is far smaller, roughly 1.7M to 2.9M USD (~57M to 95M THB):

  • Newbilt Single system (not Duplex yet)
  • Bridge stampers from Stamper Discs, so no galvanics line at launch
  • Basic QC (microscope, benchtop PVC lab, sampled listening), full metrology deferred; the PVC lab's day-one tier is the added-scope row above
  • Leased building instead of purchase, modest first solar array
  • Galvanics, automated presses, full metrology, and the biomass boiler follow as revenue-funded or second-round expansions

The planning already supports this: the Duplex-ready hydraulics, the bridge-supplier role for Stamper Discs, the staged electric-to-biomass steam path, and the phaseable metrology stack are all documented for exactly this reason.

What moves the number

  • BOI: machinery duty exemption applies across most of the equipment blocks, and the solar and automation spend converts into CIT-exemption headroom; the application precedes every purchase order (see boi.md)
  • Buy vs lease on land and building swings roughly 1.0M to 2.1M USD (~34M to 69M THB) of upfront capital, and also moves the launch date by about three quarters — see project-timeline.md
  • Biggest uncertainty bands: metrology (partly a choice of ambition), the mastering/cutting room (bespoke vendor, no public pricing), the automated presses (single unverified price point), and land
  • Currency exposure is real and is not modelled here. Revenue is mostly USD/EUR from export customers, the cost base is mostly THB, and the largest single equipment block is EUR-denominated and unhedged against an order that will not be placed for roughly a year (see project-timeline.md). A 10% move in EUR/THB between now and the Newbilt order is worth ~USD 25–35k on that line alone. Ask for the re-quote to state its currency and validity period.
  • Every band narrows only with RFQs; the supplier map in equipment-suppliers.md lists who to ask