Utilities: build the backbone once, add modules with the presses; four-module boiler hall and chiller compound
Phased build list for steam, cooling and hydraulics (launch, Duplex 1,
Duplex 2, Classic, options): everything cheap to oversize and costly to
retrofit (rooms, pads, headers and ring mains with a valved branch per
press position, tanks, HX frame, feeders, one sequencer) is built for the
five-press fleet at launch; boilers, chillers and hydraulic pump sets come
in identical modules as presses arrive. The Single 2.1 aggregate is
proposed as the first central pump set; per-branch isolation and filters.

Rooms sized for four modules each (user decision, estimates until vendor
footprints): boiler hall ~18 x 9 m for four 500 kg/h positions (fired case,
AIX DZL0.5 body), open screened chiller compound ~12.5 x 10.8 m with four
pads (250 kW at 40 C ~ Carrier 30RB 080-090), ~40 m2 pump and HX room; the
cooling tower pad of the water-cooled concept is dropped. Yard 178 -> ~379
m2. Four boilers carry ~8 presses with N+1; four 250 kW chillers carry the
five presses with CH-4 as reserve and no growth position unless the pads
take the ~350 kW frame (RFQ option).

- scale.md: yard table and basis, utility phasing section
- pressing-line.md: hydraulics phasing and re-quote questions
- steam-cooling.html: B-4 position, phasing and rooms card, details, RFQ
  questions (pw_sc_check clean)
- construction RFQ: yard table, sealed area 6,549 m2 (68 %)
- total-investment: added-scope row +73k to +122k USD (building rate on
  the ~200 m2 the yard grows by)
- Payap parts model: yard rebuilt from Params (blr_n, blr_inst, ch_*,
  bh_*, cy_*, pr_*), renders updated