Files
cnx_vinyl/docs/finance/total-investment.md
T
grabowski 89da2af9c3 Add total investment roll-up: 4M-7.7M EUR full vision, 1.5M-2.5M EUR phased entry
All sums and conversions reviewer-recomputed; every block carries its
basis (quote, researched range, or marked estimate)
2026-07-17 17:46:27 +07:00

3.4 KiB

Total Investment: Rough Picture

Everything priced or estimated so far, rolled into one view. Blocks marked "estimate" have no vendor confirmation; the rest trace to quotes or the researched ranges in this repo. Treat all figures as budgetary with a wide margin (plus or minus 30 to 50% on the estimates) until RFQs replace them. FX: ~38 THB/EUR. Compiled July 2026.

Full vision, all blocks

Block Low (EUR) High (EUR) Basis
Newbilt semi-auto line, full Duplex 300,000 320,000 2024 quote 200,500 + quoted 2nd press/extruder ~100,000; expired, needs re-quote
2 automated presses (Pheenix AD12) 500,000 800,000 unverified ~$340k/press indicative + delivery and commissioning
Galvanics line (Digital Matrix) 280,000 560,000 six-figure-USD turnkey inference from vendor research
Zero-discharge water treatment (ZLD) 80,000 210,000 utilities CSV option row, 3-8M THB
Stamper prep (Sibert VSP, VSF, VSC) 50,000 150,000 estimate, pricing unpublished
Mastering and cutting room (Agnew lathe and head, cutter amps, console, room treatment) 250,000 500,000 estimate, bespoke market
Metrology and QC stack (confocal, profiler, XRF, inline vision, audio station) 300,000 700,000 estimate, phaseable
Utilities, solar, HVAC, racking baseline 630,000 1,100,000 reviewed utilities CSV, 23.98-41.63M THB
Building ~1,500 m² plus civil works 560,000 950,000 estimate at 12,000-20,000 THB/m² Thai industrial construction plus ~20% site works
Land 6-8 rai, if purchased 315,000 840,000 estimate at 2-4M THB/rai industrial; leasing cuts this to near zero upfront
Traceability and factory software 50,000 150,000 estimate
Freight, installation, training (non-Newbilt equipment) 100,000 200,000 estimate
Working capital, PVC stock, spares 100,000 200,000 estimate
Subtotal ~3,500,000 ~6,700,000
Contingency 15% ~500,000 ~1,000,000
Total, full vision ~4,000,000 ~7,700,000 ~150M to 290M THB

Phased entry

A credible launch phase is far smaller, roughly 1.5M to 2.5M EUR:

  • Newbilt Single system (not Duplex yet)
  • Bridge stampers from Stamper Discs, so no galvanics line at launch
  • Basic QC (microscope, benchtop PVC lab, sampled listening), full metrology deferred
  • Leased building instead of purchase, modest first solar array
  • Galvanics, automated presses, full metrology, and the biomass boiler follow as revenue-funded or second-round expansions

The planning already supports this: the Duplex-ready hydraulics, the bridge-supplier role for Stamper Discs, the staged electric-to-biomass steam path, and the phaseable metrology stack are all documented for exactly this reason.

What moves the number

  • BOI: machinery duty exemption applies across most of the equipment blocks, and the solar and automation spend converts into CIT-exemption headroom; the application precedes every purchase order (see boi.md)
  • Buy vs lease on land and building swings roughly 0.9M to 1.8M EUR of upfront capital
  • Biggest uncertainty bands: metrology (partly a choice of ambition), the mastering/cutting room (bespoke vendor, no public pricing), the automated presses (single unverified price point), and land
  • Every band narrows only with RFQs; the supplier map in equipment-suppliers.md lists who to ask