Site model: two sealed dock positions on the north gable (depressed
12 m pit + 12 m ramp cut into ground and paving), water treatment
moved clear of the cooling tower, second car/staff gate on the NE
edge with access road to parking, guard house relocated between the
gates, perimeter wall rebuilt continuous on its 0.4 m inset line,
leftover door recesses filled on both envelopes, loading-apron
marking removed. Renders re-exported.
Docs: phase 1 contractor pricing request (PEB spec, PIR envelope,
dock, site works, exclusions, soil caveats).
Steam, compressed air, cooling, water treatment, racking, HVAC, solar EPC
and BESS; baseline total 23.98M-41.63M THB, options priced separately;
all figures budgetary +/- 30%, basis marked per row
- docs/: Newbilt equipment offer, site requirements, process schematic,
service rates, project cost overview, PVC supplier list, consultancy overview
- .gitignore excluding local tooling config and runtime state