grabowski bbeaed7e87 Add loading dock, second gate, and phase 1 construction RFQ
Site model: two sealed dock positions on the north gable (depressed
12 m pit + 12 m ramp cut into ground and paving), water treatment
moved clear of the cooling tower, second car/staff gate on the NE
edge with access road to parking, guard house relocated between the
gates, perimeter wall rebuilt continuous on its 0.4 m inset line,
leftover door recesses filled on both envelopes, loading-apron
marking removed. Renders re-exported.

Docs: phase 1 contractor pricing request (PEB spec, PIR envelope,
dock, site works, exclusions, soil caveats).
2026-07-30 18:11:30 +07:00
grabowski 195dbff1f4 Add revenue model: 3.2M-5.9M EUR/yr at full capacity, per-record economics
Blended pressing price, direct cost breakdown, margin, EBITDA and payback
bands; all arithmetic reviewer-recomputed; adverse payback corner stated
honestly alongside mid assumptions
2026-07-17 17:56:23 +07:00
grabowski 89da2af9c3 Add total investment roll-up: 4M-7.7M EUR full vision, 1.5M-2.5M EUR phased entry
All sums and conversions reviewer-recomputed; every block carries its
basis (quote, researched range, or marked estimate)
2026-07-17 17:46:27 +07:00
grabowski 6648eb00b2 Add Thai utilities investment CSV with supplier candidates and budgetary ranges
Steam, compressed air, cooling, water treatment, racking, HVAC, solar EPC
and BESS; baseline total 23.98M-41.63M THB, options priced separately;
all figures budgetary +/- 30%, basis marked per row
2026-07-17 16:39:46 +07:00
grabowski 5622ab2821 Initial commit: planning documents
- docs/: Newbilt equipment offer, site requirements, process schematic,
  service rates, project cost overview, PVC supplier list, consultancy overview
- .gitignore excluding local tooling config and runtime state
2026-07-17 11:47:47 +07:00