grabowski bbeaed7e87 Add loading dock, second gate, and phase 1 construction RFQ
Site model: two sealed dock positions on the north gable (depressed
12 m pit + 12 m ramp cut into ground and paving), water treatment
moved clear of the cooling tower, second car/staff gate on the NE
edge with access road to parking, guard house relocated between the
gates, perimeter wall rebuilt continuous on its 0.4 m inset line,
leftover door recesses filled on both envelopes, loading-apron
marking removed. Renders re-exported.

Docs: phase 1 contractor pricing request (PEB spec, PIR envelope,
dock, site works, exclusions, soil caveats).
2026-07-30 18:11:30 +07:00
grabowski e2ad342a1a Export site renders; pin the freecad-mcp MCP server
Nine 2400px views of the site model in docs/renders: an isometric, a
site plan, dimetric and trimetric, four aerial obliques from each corner,
a low approach view from the road, and two orthographic elevations.

Also hardens the freecad MCP entry added in the previous commit. It ran
"uvx freecad-mcp" unpinned, which resolves and executes whatever version
is current at every launch. Now pinned to 0.1.20 and marked optional, in
line with the ruv-swarm and flow-nexus entries alongside it.
2026-07-30 00:54:20 +07:00
grabowski c4d0e08c9f Add site massing model for the Mueang Chi candidate parcel
Models the plot and everything on it in FreeCAD, and writes up the
decisions the modelling forced.

Parcel geometry is traced from the DOL LandsMaps cadastral polygon and
reconciled against that portal's own measured edge lengths (40.86 + 26.61
/ 166.81 / 42.48 + 14.94 / 152.46 m), which the trace reproduces to within
about 1% with 1.67 m of closure error over a 444 m perimeter. Note the
mapped extent comes out near 9,570 sqm against a deed area of 8,266 sqm,
a ~16% gap that needs a surveyor before any offer.

On the site: 60x25 m production building on a 10 degree monopitch, a
45x38 m phase-2 building, roof and carport PV, fire and raw water tanks,
a detached boiler/chiller utility yard, perimeter wall and gate, guard
house, roofed staff parking, and the loading and fire-access roads.

Docs:
- scale.md: expansion headroom for a second building, and the detached
  utility yard, which frees ~126 sqm inside the main shed
- sustainability.md: roof orientation study (rotating the building for
  solar gains under 1 point and costs 4 m of clearance, so it stays
  aligned to the plot), and a new water supply section
- facility-security.md: fire water supply behind the existing
  suppression design

Figures marked as estimates are planning-grade, not engineering
calculations; the PV module spec is a generic placeholder, and zoning for
factory use on this plot is still unverified.