grabowski f1334f4756 OMS introduction letter and links, Sibert's answer (9 October 2026)
OMS (Lou Wullms) sent its introduction letter, filed in
docs/equipment/oms/: wet-room units with reference prices, two 4-cell
configurations (EUR 224,000 basic with two EFS2-200, EUR 311,000 advanced
with one AEFS4-250 and PLC; installation days extra), capacities of 24
and 32 shells in an 8-hour day, utilities, rooms, staffing, used
equipment, and five contacts for buying a cutting lathe. Recorded in
galvanics.md (tables, our reading: the advanced units add up to EUR
314,000, know-how transfer is left out of both totals although CNX has no
plating know-how, the basic set has no passivation unit), the exhibitor
follow-ups, vendor landscape (new section on used lathes and cutting-room
contacts, plus Lou's three websites), supplier map, roadmap items 6 and
13, total investment (basis note only, block unchanged) and the scale
people estimate. Open: forward the letter to Simona, as Lou asked.

Sibert (Ian Locke, 9 October): footprints and formal quotations when we
are ready; settle the pressing side first, hopefully with Pheenix, and
mention his recommendation if we do; impressed by the green-factory
plans (supplier feedback). Open: pass on the recommendation if Pheenix is
chosen.

CNX-01 in proplan: OMS basic and advanced added as options to D-002 with
their reference prices in THB; budget line 3 notes the OMS range.
2026-10-10 15:52:23 +07:00