grabowski 81f3279efd Add Pheenix galvanics flyers and Sibert stamper prep specs
Deploy test site / deploy (push) Successful in 45s
docs/equipment/pheenix-alpha/: the four Pheenix Alpha electroforming flyers
(2024: PASU silvering, PPPU pre-plating, PDPU dual-cell plating, PMPB
passivation bench), renamed from their download hashes.
docs/equipment/sibert/: the VSP, VSF and VSC technical specifications
(2021), plus Sibert's 2008-09 optical-disc SPS literature and the 2008
Blu-ray stamper characteristics paper in sps-optical-disc-2009/. Two
byte-identical duplicates in the download were dropped.

New docs/equipment/galvanics.md, the metal-path counterpart to
pressing-line.md: datasheet tables for both ranges and what they change.
Pheenix is a second turnkey galvanics vendor next to Digital Matrix and
can quote lacquer-to-record as one vendor; neither range includes water
treatment. Utilities from the sheets (~27 kVA connected per line, DI water,
12-20 C cooling water, extraction sizes), ~5.6 m2 of footprint, and a cell
count estimate (one PDPU at the low end, two at the high end). The Sibert
machines are single-phase, 200/250/600 kg on castors, centre manually and
list no data interface; the VSC locates on the punched hole; the finisher's
water carries nickel. Weights, cycle times, prices and mould fit are listed
as quote questions.

Backlinks and small updates: README (bullet, layout tree, vendor list),
roadmap items 6 and 23, vendor landscape, supplier map, exhibitor briefing
(on-file notes, Sibert three-phase question answered), digital factory
(Pheenix PLC data, Sibert data question, RFQ clause 5), quality automation
(hardness on the centre slug, BD paper as the acceptance-spec model),
sustainability (finisher water), total investment block label (numbers
unchanged), scale (galvanics feeder note), crane weight table, process
flow, pressing-line stamper-fit question, plant page detail lines.
2026-10-03 21:05:00 +02:00
grabowski 917a3eb933 Plan the overhead crane, maintenance workshop and visitor corridor
New docs/crane-workshop-tours.md: a 5 t single-girder EOT crane over the
whole production compartment (stops at the warehouse fire wall), a
machine door and crane-served workshop/machine bay at the ramp end, and
a glazed ground-level visitor corridor along the car-park elevation with
stations in process order, its own air and acoustic glazing so tours
need no PPE. Covers what each changes in the shell (crane-ready frame,
hook height under the 7.0 m eave, no full-height cross walls in the
crane zone, room lids and crane hatches), safety, costs and open
decisions.

Propagated: construction RFQ (crane-ready frame, new section 1c, machine
door, accessible 1:12 entrance now required), scale zone table (+210 to
280 m2, total ~1,400 to 2,000 m2), facility security, worker safety,
roadmap items 9 and 15, total investment added-scope table, README.
2026-10-02 17:34:24 +02:00
grabowski 1bbef055c4 Remove em dashes where the replacement is unambiguous
The project has a standing style rule against em dashes that was missed
when these docs were written. This removes the 42 occurrences where the
substitution is mechanical and cannot change meaning:

- table cells using an em dash as a placeholder, now a hyphen
- em dashes immediately followed by a conjunction or subordinator
  (but, and, or, so, though, while, which, where, because, since),
  where a comma is simply correct

115 remain. Those join independent clauses, where a comma would create a
splice and a colon often reads wrong, so each needs a judgement call
rather than a pattern. A blanket regex over them was attempted and
reverted: it produced double colons and broken sentences.
2026-08-06 15:31:09 +07:00
grabowski 4deaa2c57c Correct errors found by review; hedge unmarked inferences
A four-agent review audited arithmetic, cross-document consistency,
epistemic honesty and style. It found substantially more than the
manual pass in the previous commit. Errors that changed conclusions,
not decimals:

Arithmetic
- production-timeline: the headline lead times did not reconcile with
  the stage table on the same page. Launch is 22-49 days (was 21-39),
  mature 11.5-22 (was 14-20), repress 6.5-11.5. Including gates,
  launch is 6-17 weeks, not 8-14.
- Consequence: at 17 weeks the launch configuration is at parity with
  EU/US plants, not ahead of them. The page now compares quote to
  quote rather than a stage sum to a quoted lead time, and says so.
- The galvanics turnaround saving is 1.5-5 weeks, not 3-5.
- scale.md Duplex capacity 300-600k/yr did not reproduce from its own
  stated basis; corrected to 175-540k. production-timeline disagreed
  with scale.md on the same fleet; both now agree.
- "300 units is under an hour of pressing" was out by an order of
  magnitude on the semi-auto line: 5-8 hours.
- project-timeline carried two totals for the same quantity. Now
  27-33 months throughout, with the Gantt's two ordering breaks fixed.
- scale.md: 300 kWp covers 28-45% of consumption, not 20-35%; roof PV
  stated as both 150-200 and 247 kWp for the same roof; parking canopy
  dimensions and PV disagreed with the RFQ.
- RFQ: fire tank stated 200 m3 where both its geometry (254 m3) and
  its own mass (250 t) say 250. Drainage now gives total sealed area
  66%, not the 46% paving figure, since that is what attenuation needs.
- Galvanics payback used only the top of the saving range: 1-5 years,
  not 1-4.

Inference marked as inference
- The 22,000 THB stamper figure is an invoice RESIDUAL. It carries
  lacquer cutting, test pressings, setup and margin, so it is an upper
  bound on the stamper component, not a measurement. Everything derived
  from it now says so, and a line-itemised invoice is the top question.
- The saving was also benchmarked against the wrong supplier: CNX buys
  from Stamper Discs, not a Thai reseller. Stated as 175-665 USD until
  that quote exists.
- The stamper-bottleneck hypothesis now names its alternatives. Jacket
  print runs would produce the same symptom and would constrain CNX
  equally, which would remove the competitive read entirely.
- Competitor capacity relabelled as nameplate times an assumed OEE,
  with the assumed shift pattern stated; all rows on one 300-day basis.
- The fixed/variable decomposition keeps the shape and drops the point
  estimates: the solve point inside the flat 1000-3000 tier is
  arbitrary and moves the fixed component by nearly half.
- "Nobody in Thailand plates" reduced to "we have found no evidence",
  with a desk check named as the action.
- Cut the USD 450-700k valuation of a competitor's presses entirely.
  It extrapolated a semi-auto quote onto a different machine, ignored
  the used market, and supported no decision.
- The collaboration payback divided capex by revenue where the same
  page uses contribution elsewhere: 5-10 years, not 1-3.

Missing caveats added
- No financing is committed or modelled anywhere in this repo;
  project-timeline previously asserted money was not a constraint.
- Leasing cannot pull the launch forward on its own, since the press
  chain governs and construction has float against it.
- The whole competitive analysis is one buyer, one plant, one
  afternoon, and the primary evidence is not archived in the repo.
- ResurRec is a competitor and may decline to buy from a new entrant.
2026-08-06 12:35:37 +07:00
grabowski 20c8d283d5 Rebase costs on USD/THB; add timelines and first market data
Currency
- Base currency moves from EUR to USD and THB throughout. Rates at
  5 Aug 2026: 1 USD = 33 THB, 1 EUR = 1.155 USD, 1 GBP = 1.35 USD.
  EUR/THB lands at ~38, so existing THB research needed no change.
- Vendor quotes keep their original currency with a USD/THB equivalent
  alongside, so they stay checkable against the source PDFs.
- Full vision ~4.7-8.9M USD; phased entry ~1.7-2.9M USD.

New documents
- production-timeline.md: order turnaround stage by stage. Launch
  8-14 weeks, mature 5-10, repress 2-3. Quantifies the in-house
  galvanics turnaround claim the repo had asserted without a number,
  and flags artwork as an unmodelled fourth approval gate.
- project-timeline.md: calendar to first paying release, ~Q4 2028.
  Critical path is BOI certificate to press order to build to
  commissioning. Two findings: Newbilt build time is absent from the
  repo yet carries ~40% of the schedule, and the BOI rule may be
  over-serialised since duty exemption attaches at importation rather
  than at contract signature.

First market data (ResurRec, Bangkok)
- Invoice-derived prices, a factory tour, and a confirmed fleet of one
  Newbilt Classic 12" automatic plus one semi-automatic.
- Price ladder recorded at 300/500/1000-3000/3000+ units. Decomposes
  to roughly 34-50k THB fixed per title and 535-780 THB variable per
  unit, which is 4-7x the price this model assumes.
- The incumbent presses 230-350k records/yr but buys every stamper as
  an import. That single constraint plausibly explains their 150-unit
  floor, their flat discount ladder and their large-run lead time, and
  it is what an in-house galvanics line attacks. Logged as an open
  question on whether galvanics should move from phase 5 to phase 1.
- Inferences are marked as inferences; the whole set is one buyer and
  one plant, and the model is deliberately left unrebased until a
  second data point exists.

Corrections
- Gross margin arithmetic did not follow from its own inputs. Restated
  as ~1.95 USD at the midpoint with the 0.75-3.15 spread shown; the
  previous "40 to 55%" was not supported.
- Direct cost low total 1.50 to 1.45 USD; contingency THB high 40M
  to 38M.
- README indexes the construction RFQ, which was missing.
2026-08-06 12:22:40 +07:00
grabowski c4d0e08c9f Add site massing model for the Mueang Chi candidate parcel
Models the plot and everything on it in FreeCAD, and writes up the
decisions the modelling forced.

Parcel geometry is traced from the DOL LandsMaps cadastral polygon and
reconciled against that portal's own measured edge lengths (40.86 + 26.61
/ 166.81 / 42.48 + 14.94 / 152.46 m), which the trace reproduces to within
about 1% with 1.67 m of closure error over a 444 m perimeter. Note the
mapped extent comes out near 9,570 sqm against a deed area of 8,266 sqm,
a ~16% gap that needs a surveyor before any offer.

On the site: 60x25 m production building on a 10 degree monopitch, a
45x38 m phase-2 building, roof and carport PV, fire and raw water tanks,
a detached boiler/chiller utility yard, perimeter wall and gate, guard
house, roofed staff parking, and the loading and fire-access roads.

Docs:
- scale.md: expansion headroom for a second building, and the detached
  utility yard, which frees ~126 sqm inside the main shed
- sustainability.md: roof orientation study (rotating the building for
  solar gains under 1 point and costs 4 m of clearance, so it stays
  aligned to the plot), and a new water supply section
- facility-security.md: fire water supply behind the existing
  suppression design

Figures marked as estimates are planning-grade, not engineering
calculations; the PV module spec is a generic placeholder, and zoning for
factory use on this plot is still unverified.
2026-07-29 23:00:09 +07:00
grabowski c95874ce6f Add project scale summary: capacity, building, land, electrical, solar, headcount
All derived figures reviewer-recomputed; BESS runtime corrected to the
chiller's electrical draw (2-3 h, not 1 h of thermal rating)
2026-07-17 17:37:20 +07:00