- Plan B now starts like Plan A with one Duplex system and one Classic,
but takes none of the six levers: owned solar and battery (with the BOI
solar measure), the full metrology stack, the visitor corridor, cassette
and CD-R, the bought crane and Thai-supplied utilities (user, 17 October
2026). ~193.8M THB before the reserve, ~209M with it (~150M to 268M),
~32M (~18 %) more than Plan A; the second Duplex is a growth step from
revenue in both (~15.4M THB, estimate).
- total-investment.md "Two plans" re-based (heading and anchor now
"B at ~210M THB", README and roadmap links updated); revenue-model.md
operating pictures: same volume and EBITDA as Plan A, depreciation on
Plan B's capital (operating profit 1.26M USD central, payback ~3.7 yr);
the extra earns nothing in the modelled table, which the docs say.
- Calculator: Plan B preset = the launch plant with contingency kept out
(EBITDA 2.07M USD, cash payback year ~4.3, IRR ~21 %); budget card marks
180M and 180M plus 25 %; preset label "Plan B (~210M, all in)".
- Business plan draft 0.3, both versions rebuilt: every Plan B branch of
the three content files rewritten; renders regenerated with the
isometric view turned to the front of the site (road, car park, office,
corridor facade) for the cover and Figures 8 to 10.
- Cover and section 6.2 now use the isometric plant view of the plant and
business plan calculator, drawn with each version's own preset: the
cover (roofs, no labels), Figure 8 the site from above, Figure 9 the
ground floor cut open, Figure 10 the press hall close up. The FreeCAD
aerial render, the Mueang Chi site plan and the hall layout sketch are
no longer in the plan; the captions say the calculator draws the Payap
scenario model while the 6.2 text and zone table are the Mueang Chi
hall.
- New section 5.5 "The software: plant overview, factory console and
artist platform" with six screenshots of the demos: the plant overview
(simulated SCADA), the factory console press floor and its ERPNext
link, the artist ordering offer, fan funding and the record passport.
Simulated data is marked as such; the platform name stays undecided.
- Figures renumbered (budget card 11, cash 12) and named in the
section 15 source table. Renders in docs/renders/calculator/ and
docs/renders/demos/; README bullet updated.
- One build makes both documents: plan_variant.py switches the
plan-specific text (pick / is_a / label); build_plan.py writes
CNX-Vinyl-Business-Plan-A and -B (docx), export_pdf.py exports both PDFs
with the table of contents filled in. Draft 0.2 (single launch-plant
plan with contingency) is removed; it stays in the history.
- Plan A: the launch plant with every machine and six cost levers, ~177M
THB with the ramp-up reserve, no contingency. Plan B: the second Duplex
at launch, five presses, ~224M THB on the same basis. Each version reads
as a complete plan with one table comparing it with the other; the
216M investor-question text is gone, Pheenix is priced at OMS's
reference plus 20 %.
- Calculator renders in both documents, each from its own preset: the
plant at a glance (Figure 4), the budget check (Figure 5) and ten years
of cash (Figure 6), in docs/renders/calculator/.
- Calculator budget card: the verdict and third KPI now name the tightest
budget the midpoint fits (Plan A: 3.3M to spare under 180M; Plan B:
0.8M under 225M) instead of always 225M.
- Fixes: CD replication cross-references point to section 4.10; the
blended price in section 3.3 and roadmap item 1 is 3.76 to 5.27 USD at
60 % specials (3.50 to 4.60 at a standard-heavy mix).