OMS introduction letter and links, Sibert's answer (9 October 2026)
OMS (Lou Wullms) sent its introduction letter, filed in docs/equipment/oms/: wet-room units with reference prices, two 4-cell configurations (EUR 224,000 basic with two EFS2-200, EUR 311,000 advanced with one AEFS4-250 and PLC; installation days extra), capacities of 24 and 32 shells in an 8-hour day, utilities, rooms, staffing, used equipment, and five contacts for buying a cutting lathe. Recorded in galvanics.md (tables, our reading: the advanced units add up to EUR 314,000, know-how transfer is left out of both totals although CNX has no plating know-how, the basic set has no passivation unit), the exhibitor follow-ups, vendor landscape (new section on used lathes and cutting-room contacts, plus Lou's three websites), supplier map, roadmap items 6 and 13, total investment (basis note only, block unchanged) and the scale people estimate. Open: forward the letter to Simona, as Lou asked. Sibert (Ian Locke, 9 October): footprints and formal quotations when we are ready; settle the pressing side first, hopefully with Pheenix, and mention his recommendation if we do; impressed by the green-factory plans (supplier feedback). Open: pass on the recommendation if Pheenix is chosen. CNX-01 in proplan: OMS basic and advanced added as options to D-002 with their reference prices in THB; budget line 3 notes the OMS range.
This commit is contained in:
1 parent
90d8a3778a
commit
f1334f4756
9 files changed
+235
-27
No files matched your search
+5
-3
@@ -52,8 +52,9 @@ These three run in parallel and gate everything downstream:
|
||||
6. **Galvanics quotes**: Digital Matrix, and Pheenix Alpha in the same
|
||||
conversation as item 5 (it builds the electroforming line too), plus
|
||||
OMS (Optical Media Services), named by Sibert as the alternative to a
|
||||
Pheenix turnkey line (first contact from Lou Wullms 7 October 2026;
|
||||
Alexander has replied; OMS sends material to calculate from next), and
|
||||
Pheenix turnkey line (reference prices of 9 October 2026: EUR 224,000
|
||||
basic and 311,000 advanced for a 4-cell wet room, installation extra; a
|
||||
dedicated offer needs our plans, ideally after a visit to Baarlo), and
|
||||
Sibert's itemised quotation for the stamper
|
||||
prep machines (a USD 250k budget for all three is confirmed, its time,
|
||||
spares, shipping and travel extra); equipment data in
|
||||
@@ -86,7 +87,8 @@ These three run in parallel and gate everything downstream:
|
||||
12. Secure the site (lease preferred for the phased entry; purchase only
|
||||
with land privileges under BOI)
|
||||
13. Order long-lead items: mastering lathe (Agnew or Sillitoe, both built
|
||||
to order, see [vendor landscape](suppliers/vendor-landscape.md)),
|
||||
to order, or second-hand through the contacts OMS named, see
|
||||
[vendor landscape](suppliers/vendor-landscape.md)),
|
||||
stamper-prep machines, first utility packages
|
||||
14. Engage Stamper Discs for the bridge-stamper relationship with written
|
||||
turnaround SLAs, and settle where lacquers are cut meanwhile: SST in
|
||||
|
||||